Heat loads due to impedance update and required

  • Slides: 58
Download presentation
Heat loads due to impedance: update and required upgrades G. Arduini, M. Barnes, P.

Heat loads due to impedance: update and required upgrades G. Arduini, M. Barnes, P. Baudrenghien, N. Biancacci, R. Calaga, F. Carra, F. Caspers, H. Day, J. Esteban Mueller, O. Frasciello, G. Iadarola, T. Jin, A. Lechner, E. Métral, G. Rumolo, B. Salvant, E. Shaposhnikova, J. Uythoven, N. Wang, R. Wanzenberg, O. Zagorodnova, C. Zannini, M. Zobov. Many thanks to WP 2 members and the relevant equipment groups for their input and for the very efficient teamwork over the years Special thanks to our collaborators at INFN Frascati, la Sapienza, DESY, TU Darmstadt and IHEP Beijing!

 • Follow up of many talks and work over the last years at

• Follow up of many talks and work over the last years at the Hi. Lumi meetings, WP 2 task leader meetings and task 2. 4 meetings.

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • •

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • • Scaling heat load Status of current issues Current devices to monitor What we do not know • Possible mitigations • Perspectives 3

Beam induced heating? Energy Intensity Temp TOTEM Roman pots Temp MKI Temp ATLAS-ALFA Roman

Beam induced heating? Energy Intensity Temp TOTEM Roman pots Temp MKI Temp ATLAS-ALFA Roman pot TOTEM “IN” Example of temperature of certain LHC devices during physics fills MKI: injection kicker TOTEM Roman pots ATLAS-ALFA Roman pots Temperature increase due to the interaction of beam induced wake fields with the surrounding Beam induced heating has affected operation since intensity ramp up started in mid-2011 4

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • •

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • • Scaling heat load Status of current issues Current devices to monitor What we do not know • Possible mitigations • Perspectives 5

Heating issues in LHC before LS 1 Damaged synchrotron light monitor in 2012 Damaged

Heating issues in LHC before LS 1 Damaged synchrotron light monitor in 2012 Damaged vacuum module in 2011 Damaged injection collimator in 2011 ALFA detector could be damaged Injection kicker delays injection Some collimators are heating one single cryogenic module (Q 6 R 5) has no margin for cooling. 6

Summary table of LHC issues equipment Problem VMTSA 2011 2015 HL-LHC? Damage removed TDI

Summary table of LHC issues equipment Problem VMTSA 2011 2015 HL-LHC? Damage removed TDI Damage Beam screen reinforced, copper coating on the jaw New design underway MKI Delay Beam screen and tank emissivity upgrade Current upgrade may not be enough Collimators Few dumps Non conformity solved. TCTVB removed 400 W expected for 7 k. W cooling Beam screen Regulation at the limit Upgrade of the valves + TOTEM check Upgrade should be sufficient ALFA Risk of damage New design + cooling No forward physics after LS 3? BSRT Deformation suspected New design + cooling New design underway BGI vacuum increase Q 6 R 5 and TOTEM 2012 Q 6 R 5 and TOTEM 2012 was a bad year for heating issues! Damage Limits operation Worry that can limit operation 7 Should be fine

Summary table of LHC issues equipment Problem VMTSA 2011 2015 HL-LHC? Damage removed TDI

Summary table of LHC issues equipment Problem VMTSA 2011 2015 HL-LHC? Damage removed TDI Damage Beam screen reinforced, copper coating on the jaw New design underway MKI Delay Beam screen upgrade and non conformity solved Current upgrade may not be enough Collimators Few dumps Non conformity solved. TCTVB removed 400 W expected for 7 k. W cooling Beam screen Regulation at the limit Upgrade of the valves + TOTEM check Upgrade should be sufficient ALFA Risk of damage New design + cooling No forward physics after LS 3? BSRT Deformation suspected New design + cooling New design underway BGI vacuum increase To be followed up Q 6 R 5 and TOTEM 2012 Q 6 R 5 and TOTEM Most problems were seriously and efficiently addressed 2015 went much better! Other devices may show up in the list Beam screen heating critical, but impedance contribution small Damage Limits operation Worry that can limit operation 8 Should be fine

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • •

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • • Scaling heat load Status of current issues Current devices to monitor What we do not know • Possible mitigations • Perspectives 9

Increase in heat load only from intensity increase Factor from situation before LS 1

Increase in heat load only from intensity increase Factor from situation before LS 1 Nominal ultimate Before LS 1 HL-LHC (25 ns) (50 ns) (25 ns) M Nb 2808 1. 15 2808 1. 8 1374 1. 6 2748 2. 2 Broadband (M*Nb 2) 1. 1 2. 6 1 3. 8 Narrow band (M*Nb)2 2. 2 5. 3 1 7. 6 *Narrow band is a worst case scenario assuming that the resonance stands exactly at a multiple of 40 MHz Significant increase in heat load from impedance with HL-LHC intensity (factor 4 to 7) 10

Increase in heat load from intensity increase and bunch length decrease to 8. 1

Increase in heat load from intensity increase and bunch length decrease to 8. 1 cm (1. 08 ns) -> 30% more heat load Factor from situation before LS 1 Nominal ultimate Before LS 1 HL-LHC (25 ns) (50 ns) (25 ns) M Nb 2808 1. 15 2808 1. 8 1374 1. 6 2748 2. 2 Broadband (M*Nb 2) 1. 3 3. 3 1 4. 8 Narrow band (M*Nb)2 2. 7 6. 7 1 9. 6 *Narrow band is a worst case scenario assuming that the resonance stands exactly at a multiple of 40 MHz Significant increase in heat load from impedance with HL-LHC parameters (factor 5 to 10) Hardware that are limiting now or marginal need to be upgraded for HL-LHC Bunch length decrease during the fill to 0. 8 ns (~6 cm) would lead to a factor 2 increase (at constant intensity) 11 Note: a further reduction of bunch length to 4 cm leads to an additional factor of at least 3 in power loss

Summary table of LHC issues equipment Problem VMTSA 2011 2015 HL-LHC? Damage removed TDI

Summary table of LHC issues equipment Problem VMTSA 2011 2015 HL-LHC? Damage removed TDI Damage Beam screen reinforced, copper coating on the jaw New design underway MKI Delay Beam screen upgrade and non conformity solved Current upgrade may not be enough Collimators Few dumps Non conformity solved. TCTVB removed 400 W expected for 7 k. W cooling Beam screen Regulation at the limit Upgrade of the valves + TOTEM check Enough cooling for arc beam screen for intensity ramp-up? ALFA Risk of damage New design + cooling No forward physics after LS 3? BSRT Deformation suspected New design + cooling New design underway BGI vacuum increase To be followed up Q 6 R 5 and TOTEM 2012 Q 6 R 5 and TOTEM Most problems were seriously and efficiently addressed 2015 went much better! Other devices may show up in the list Damage Limits operation Worry that can limit operation 12 Should be fine

Why these good results in 2015? • Very strong effort by equipment groups to

Why these good results in 2015? • Very strong effort by equipment groups to improve the impedance of their device: only the TDI suggestions could not be implemented • Strict rules enforced by impedance team for installation of new hardware into LHC or modification • Effort on heating monitoring tools: • • Additional monitoring requested and implemented Temperature and vacuum fixed displays in control room and analyzers Alarms by interlock system (SMS) to detect abnormal behavior (no dump) Tools to display Synchronous phase error and beam spectra allowed detecting issues already with low intensity beam • Most heating issues are expected to be linked to broadband impedance: 25 ns beam with 2000 bunches is less demanding than 50 ns before LS 1 for broadband impedances. bunch length at the beginning of physics was increased to 1. 35 ns during the intensity ramp-up (and then was let decreased thanks to SR damping)

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling heat load • Status of current issues • Current devices to monitor • • • Beam screen (triplets and arc) Injection kickers (MKI) Injection protection collimators (TDI) Crab cavities And… • What we do not know • Possible mitigations • Perspectives 14

Triplet beam screen heat load vs beam screen temperature E. Métral and C. Zannini,

Triplet beam screen heat load vs beam screen temperature E. Métral and C. Zannini, “Temperature effects on image current losses in the triplets”, 33 rd Hi. Lumi WP 2 Task Leader Meeting, Friday, September 5, 2014 E. Métral and C. Zannini G. Iadarola at KEK 2014: • Impact of the operating temperature up to about factor 2 • Triplets should be coated (i. e. no electron cloud) and synchrotron radiation expected to be negligible in LSS (impact of crossing angle to be evaluated ) Values well within the available cooling capacity (4. 8 W/m)

Effect of the weld(s) - “Transverse” weld - “Longitudinal” weld note: not easy to

Effect of the weld(s) - “Transverse” weld - “Longitudinal” weld note: not easy to get convergence with CST simulations for this case Requires refined mesh near the weld.

Effect of transverse weld (IP 1, IP 5 new beam screen) Na Wang Power

Effect of transverse weld (IP 1, IP 5 new beam screen) Na Wang Power loss for 2*2748 bunches at 2. 2 e 11 p/b Elem ent Length [mm] Numb er Power loss [W] Q 1 8 4 0. 2 Q 2 8 8 0. 32 Q 3 8 4 0. 16 D 1 8 4 0. 16 D 2 16 4 0. 46 Q 4 8 4 0. 28 Total -- -- 1. 6 Power loss per meter for 1 beam (for D 2) in transverse weld: 3. 6 [W/m] in beam screen: 0. 13 [W/m] Small increase expected for the whole length However, this will generate longitudinal hot spots. Is that an issue?

Study for new design of triplet beam screen (in collaboration with TE-VSC) • Coating

Study for new design of triplet beam screen (in collaboration with TE-VSC) • Coating with amorphous carbon for electron cloud reduction Small impact only on imaginary part of impedance. No impact on beam induced RF heating. • Proposed geometry with two welds instead of one Octogonal beam screen with 2 welds (4 mm wide) 1 weld : 70% increase in heat load with respect to no weld 2 welds : factor 2 increase in heat load with respect to no weld

Started study on triplet beam screen holes Very small impact of holes on beam

Started study on triplet beam screen holes Very small impact of holes on beam screen heat load F. Riminucci et al

Beam screen heat load from impedance (LHC and HL-LHC) Power dissipated by the beam

Beam screen heat load from impedance (LHC and HL-LHC) Power dissipated by the beam in the beam screen in m. W/m (for 2 beams) Beam screen Radius (mm) 2012 4 Te. V 1374 b 1. 7 e 11 1. 25 ns 2015 6. 5 Te. V 2248 b 1. 2 e 11 1. 25 ns Nominal 7 Te. V 2808 b 1. 15 e 11 1 ns HL-LHC 7 Te. V 2748 b 2. 2 e 11 1. 08 ns Arc(*) 18. 4 187 176 290 927 Current Q 1(*) 24 143 135 222 710 Current Q 2 -Q 3(*) 18. 95 181 171 282 900 New Q 1(**) 49 - - 151 483 New Q 2 -Q 3(**) 59 - - 126 401 More than factor 5 ( *) Assumes 1 weld (2 mm wide) on the side of the beam screen (**) Assumes 2 weld (4 mm wide) on each side of the beam screen

Beam screen heat load from impedance (LHC and HL-LHC) Power dissipated by the beam

Beam screen heat load from impedance (LHC and HL-LHC) Power dissipated by the beam in the beam screen in W/half cell (for 2 beams) Beam screen Radius (mm) 2012 4 Te. V 1374 b 1. 7 e 11 1. 25 ns 2015 6. 5 Te. V 2248 b 1. 2 e 11 1. 25 ns Nominal 7 Te. V 2808 b 1. 15 e 11 1 ns HL-LHC 7 Te. V 2748 b 2. 2 e 11 1. 08 ns Arc(*) 18. 4 10 W 9 W 15. 5 W 49 W ( *) Assumes 1 weld (2 mm wide) on the side of the beam screen Assumes 2 weld (4 mm wide) on each side of the beam screen (**)

Comparing with cooling capacity Beam screen Coated for HLLHC? Synchrotron radiation(*) Impedance heating Secondaries

Comparing with cooling capacity Beam screen Coated for HLLHC? Synchrotron radiation(*) Impedance heating Secondaries What is left for ecloud? Assumed available cooling capacity Triplets in IR 1 and IR 5 Yes 0 0. 44 W/m ? Coating assumed 4. 8 W/m Will be upgraded Triplets in IR 2 and IR 8 Yes 0 0. 805 W/m ? Coating assumed 4. 8 W/m Will be upgraded? Arc beam screen No 33 W 50 W 0 W 77 W 160 W (*) Data from L. Tavian, annual Hi. Lumi workshop 2013 Heat load to beam screen from impedance will increase significantly and is expected not to be minor anymore with respect to cooling capacity, in particular for the arcs. Electron cloud heatload in IT and MS presented by G. Iadarola at KEK 2014 (could reach 20 W/m for non coated MS quadrupoles with SEY=1. 3, see appendix) Activity to be followed up by the heat load working group

Comparing with cooling capacity Arc beam screen Synchrotro n radiation(*) Impedance heating What is

Comparing with cooling capacity Arc beam screen Synchrotro n radiation(*) Impedance heating What is left for ecloud? Assumed current cooling capacity 2015 11 W 9 W 140 W 160 W Nominal 18 W 15. 5 W 126 W 160 W HL-LHC 33 W 50 W 77 W 160 W scaled from L. Tavian, annual Hi. Lumi workshop 2013 To be confirmed by TE-CRG (*) Data 2015 Nominal HL-HLC Heat load to beam screen from impedance will increase significantly and is expected not to be small anymore with respect to cooling capacity, in particular for the arcs. Could this cause a significant slow down of the intensity ramp up? Activity to be followed up by the heat load working group

Heating from electron cloud

Heating from electron cloud

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling heat load • Status of current issues • Current devices to monitor • • • Beam screen (triplets and arc) Injection kickers (MKI) Injection protection collimators (TDI) Crab cavities And… • What we do not know • Possible mitigations • Perspectives 25

Injection kicker MKI M. Barnes, H. Day et al • LHC Run 1: •

Injection kicker MKI M. Barnes, H. Day et al • LHC Run 1: • heating on one non-conforming kicker limited Run 1 performance (+1 -2 h turnaround, on a few occasions) was due to a twisted beam screen. • Ferrites reached Curie temperature of 120 C with an estimated power loss of 160 W/m (averaged over the length) for this non-conforming magnet. • Significant effort of the TE-ABT team during LS 1: • Increase number of screen conductors from 15 to 24 to better screen the ferrite • Change of geometry at capacitively coupled end of the ceramic chamber to reduce electric field Upgrade worked very well: no further limitation! 26

MKI: expectation for HL-LHC M. Barnes, H. Day, L. Vega Cid et al Power

MKI: expectation for HL-LHC M. Barnes, H. Day, L. Vega Cid et al Power deposition 2012 Run 2 HL-LHC 161 W/m 42 W/m (max 52 W/m) 138 W/m (max 170 W/m) HL-LHC: 2748 bunches 2. 2 e 11 p/b and 1. 08 ns Different geometry The power loss will not be deposited at the same location Was more spread along the MKI length Expected to be now more localized at the upstream (capacitively coupled) end (simulations and temperature measurements during 2015 in general agreement) Need to be careful as the upstream end could reach Curie temperature well before the rest. Studies ongoing. In case bunch length is too short, possibility to blow up at the start of the ramp and during the fill 27

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling heat load • Status of current issues • Current devices to monitor • • • Beam screen (triplets and arc) Injection kickers (MKI) Injection protection collimators (TDI) Crab cavities And… • What we do not know • Possible mitigations • Perspectives 28

Injection protection collimators (TDIS) - Serious issues with the current TDIs (in particular TDI

Injection protection collimators (TDIS) - Serious issues with the current TDIs (in particular TDI 8) very careful check of the new TDIS - Optimization of impedance and improvement of cooling has high priority: Recommended in particular: - To reduce resistive contribution: Copper coating on the jaw - To reduce geometric contribution: - Closing the gap between the jaws and the beam screen with RF fingers - Avoiding cavities and steps at the transitions (difficult due to dose constraints) - Find a good compromise between low impedance at injection and flat top - Geometry not finalized T. Jin et al Need to see the effect of reducing the resistive wall impedance with copper coating in 2016

TDI simulation studies at INFN Frascati (O. Frasciello, M. Zobov et al) Proposal from

TDI simulation studies at INFN Frascati (O. Frasciello, M. Zobov et al) Proposal from INFN: (1) damp modes resonating inside the transitions with waveguide, ferrites or coupler, (2) reduce by a factor 2 the taper impedance using a nonlinear taper.

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling heat load • Status of current issues • Current devices to monitor • • • Beam screen (triplets and arc) Injection kickers (MKI) Injection protection collimators (TDI) Crab cavities And… • What we do not know • Possible mitigations • Perspectives 31

Crab cavities N. Biancacci et al

Crab cavities N. Biancacci et al

N. Biancacci et al

N. Biancacci et al

N. Biancacci et al Rs= 25800 Q = 1270 Fr=595 MHz Rs= 70100 Q

N. Biancacci et al Rs= 25800 Q = 1270 Fr=595 MHz Rs= 70100 Q = 7200 Fr=959 MHz Dangerous beam modes are separated by 40 MHz, Q are already low for superconducting cavities (~1000 to 10000) it should be more efficient to detune the modes in case they are in the dangerous region (+/- 3 MHz from multiples of 40 MHz)

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling heat load • Status of current issues • Current devices to monitor • • • Beam screen (triplets and arc) Injection kickers (MKI) Injection protection collimators (TDI) Crab cavities And… • What we do not know • Possible mitigations • Perspectives 35

Other devices to monitor for HL-LHC • Experimental beam pipes (CMS and ATLAS data

Other devices to monitor for HL-LHC • Experimental beam pipes (CMS and ATLAS data from R. Wanzenberg and O. Zagorodnova DESY) • • • CMS chamber (e. g. mode 750 MHz, R=1. 5 k. Ohm): from 50 W before LS 1 to potentially more than 350 W ATLAS chamber: no significant mode expected ALICE chamber (e. g. mode 530 MHz, R=1. 5 k. Ohm): from 150 W before LS 1 to potentially more than 1 k. W LHCb chamber (e. g. mode 620 MHz, R=0. 6 k. Ohm): from 30 W before LS 1 to potentially more than 250 W LHCb VELO: plan to reduce aperture with colliding beams from 5 mm to 3. 5 mm. • Instrumentation • Upgraded BSRT so far very stable temperatures! • striplines, button BPMs, wall current monitor some electronics may need to be changed to accept more power. • Accelerating RF cavities • R. Calaga: very small power extracted from the RF couplers before LS 1 (a few Watts). • Possibility to detune the modes in case of problem. • New collimators, MKD, recombination chambers, electron lens, beam-beam compensation (strong impact expected if outside of collimator) • Other ideas? 36

Power from resonant modes for ALICE Modes from R. Wanzenberg and O. Zagorodnova, DESY

Power from resonant modes for ALICE Modes from R. Wanzenberg and O. Zagorodnova, DESY Significant increase of power loss with HL-LHC parameters (here with 1. 2 ns) even the modes at higher frequencies are significant (of the order of 20 to 50 W) Similar case for CMS and LHCb

Measured ALICE beam pipe temperatures

Measured ALICE beam pipe temperatures

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling

Agenda • Beam induced heating? • Current issues • Reaching HL-LHC parameters • Scaling heat load • Status of current issues • Current devices to monitor • • • Beam screen (triplets and arc) Injection kickers (MKI) Injection protection collimators (TDI) Crab cavities And… • What we do not know • Possible mitigations • Perspectives 39

What we don’t know • Many devices are not yet designed • Non conformities

What we don’t know • Many devices are not yet designed • Non conformities Need more systematic temperature monitoring on near beam hardware Need to check cooling system before/during installation Need to check longitudinal impedance of new equipment before installation to detect problems • Fruitful work with thermal simulation experts to predict temperature distribution, but still a difficult process (already started within TE-ABT for MKIs) 40

Agenda • Main messages • Current issues in LHC • Beam induced heating? •

Agenda • Main messages • Current issues in LHC • Beam induced heating? • Reaching HL-LHC parameters • • Scaling heat load Status of current issues Other devices to monitor What we do not know • Possible mitigations • Perspectives 41

Possible mitigations in case of issues • Reduce longitudinal impedance • Avoid unnecessary cavities

Possible mitigations in case of issues • Reduce longitudinal impedance • Avoid unnecessary cavities (contact RF fingers, elliptical bellows for elliptical chambers, tapered transitions) • If the heating is due to resistive wall, increase material conductivity • If the heating is due to trapped modes, reduce material conductivity • Reduce impedance overlap with beam spectrum • For resistive wall or broad resonance, increase bunch length. • For narrow resonance, detune the resonant mode (with ferrite or coupler) • Possibility to tune the beam spectrum with the longitudinal distribution (higher harmonic cavity) • Reduce bunch or beam intensity • Use flat bunches (very successful MDs by E. Shaposhnikova et al) • Extract the heat from critical locations (ferrite, RF fingers, all mode coupler) 42

Bunch Flattening J. E. Mueller, E. Shaposhnikova et al. ATLAS CMS 29/10/2015 3 x

Bunch Flattening J. E. Mueller, E. Shaposhnikova et al. ATLAS CMS 29/10/2015 3 x 1033 2 x 1033 some reduction on lumi seen 5% / ~ 0. 15 x 1033 but no optimization (lumi scan done) to be checked what fraction from abort gap cleaning from geometric factor or simply offset LHC Morning meeting – WH & JW 43

Significant impact of bunch flattening on heating MKI tube Intensity Bunch length Beam screen

Significant impact of bunch flattening on heating MKI tube Intensity Bunch length Beam screen AFP S 12 TOTEM Bunch flattening applied Effective tool against heating of several hardware (e. g. MKI tube, beam screen, Roman pots)

Agenda • Main messages • Current issues in LHC • Beam induced heating? •

Agenda • Main messages • Current issues in LHC • Beam induced heating? • Reaching HL-LHC parameters • • Scaling heat load Status of current issues Other devices to monitor What we do not know • Possible mitigations • Perspectives 45

Main messages • Many heating issues related to beam impedance in 2011 and 2012.

Main messages • Many heating issues related to beam impedance in 2011 and 2012. • Strong effort by equipment groups to modify existing hardware and optimize new ones paid off less issues in 2015 so far. • Still need to optimize LHC hardware as the conditions will be much tougher in HL-LHC era (~factor 5 more ) Hardware already at the limit will likely require modifications: • TDI (planned for LS 2), already significant improvement expected after this YETS • MKI (ongoing effort to assess the limits with reasonable confidence and further improve the situation) • Arc beam screen cooling needs to be assessed in collaboration with WP 9 (heat load WG) • Beware of non-conformities • Check carefully all devices and cooling that are supposed to be put in the LHC • Need of efficient temperature monitoring during intensity ramp up to detect problems early • Strategies for mitigation: • • Optimize designs to reduce heat load If cavities are necessary, detune and localize the heat loss in ferrites. Working now on extracting the heat from the system (longer term) Higher harmonic system will give flexibility to tune the bunch distribution in case of problem 46

Thank you very much for your attention!

Thank you very much for your attention!

L. Tavian, Hi. Lumi 2013

L. Tavian, Hi. Lumi 2013

Flat bunches: another degree of freedom in case of abnormal heating Juan Esteban Mueller,

Flat bunches: another degree of freedom in case of abnormal heating Juan Esteban Mueller, Elena Shaposhnikova et al Temperature [ºC] ALFA TCTVB Bunch lengths Voltage variation RF phase modulation UTC Time 50 LHC MD in 2012: excitation to flatten bunches reduced temperature on TCTVB and ALFA

Power from main mode of DQW Probability of getting more than 1 k. W:

Power from main mode of DQW Probability of getting more than 1 k. W: 20% (if the mode is within 3 MHz of a beam spectrum line). More effective to detune the mode than to reduce R.

Heat load due to impedance Impact of the operating temperature up to about factor

Heat load due to impedance Impact of the operating temperature up to about factor 2 Values well within the available cooling capacity (4. 8 W/m)

Beam screens in matching quadrupoles (Type 1) BSMQ_1 (22. 5, 17. 6) mm •

Beam screens in matching quadrupoles (Type 1) BSMQ_1 (22. 5, 17. 6) mm • Beam screen shape very similar to that of the LHC arcs • The dependence on the magnetic gradient is quite weak • The increase in bunch intensity causes a slight decrease of the electron flux and a slight increase of the multipacting threshold • For large SEY the heat load is stronger for HL-LHC intensity • e-cloud mitigation through scrubbing, low SEY coating (a-C) and/or clearing electrodes is needed to operate within the cryo cooling capacity 1. 15 x 1011 ppb 2. 20 x 1011 ppb Impedance heating Cryo cooling capacity

Beam screens in matching quadrupoles (Type 2) BSMQ_2 (28. 9, 24. 0) mm •

Beam screens in matching quadrupoles (Type 2) BSMQ_2 (28. 9, 24. 0) mm • The increase in bunch intensity causes a slight increase of the multipacting threshold • For large SEY the heat load is stronger for HL-LHC intensity • The dependence on the magnetic gradient is quite weak • e-cloud mitigation through scrubbing, low SEY coating (a-C) and/or clearing electrodes is needed to operate within the cryo cooling capacity 1. 15 x 1011 ppb 2. 20 x 1011 ppb Impedance heating Cryo cooling capacity

Beam screens in matching quadrupoles (Type HL) BSMQ_HL • Beam screen shape not installed

Beam screens in matching quadrupoles (Type HL) BSMQ_HL • Beam screen shape not installed in the present machine • The dependence on the magnetic gradient is quite weak • Multipacting threshold very similar for nominal and HL-LHC intensity • Heat load is stronger for HL-LHC intensity • e-cloud mitigation through scrubbing, low SEY coating (a-C) and/or clearing electrodes is needed to operate within the cryo cooling capacity (37, 32) mm 1. 15 x 1011 ppb 2. 20 x 1011 ppb Impedance heating Cryo cooling capacity

Beam screen in D 2 separation dipoles (IR 2&8) BSD 2 (26. 4, 31.

Beam screen in D 2 separation dipoles (IR 2&8) BSD 2 (26. 4, 31. 3) mm • The increase in bunch intensity causes a decrease of the multipacting threshold • For all the SEY values the heat load is stronger for HL-LHC intensity • The dependence on the beam size is quite weak (except for the smallest, simulation numerically quite challenging, further checks needed) • e-cloud mitigation through scrubbing, low SEY coating (a-C) and/or clearing electrodes is needed to operate within the cryo cooling capacity 1. 15 x 1011 ppb Beam size factor w. r. t. fully squeezed round optics 2. 20 x 1011 ppb Cryo cooling capacity

Inner triplets and D 1 dipoles (IR 1&5) Q 1 IR 1: Q 2

Inner triplets and D 1 dipoles (IR 1&5) Q 1 IR 1: Q 2 Q 3 D 1 D 2 Q 4 Q 5 Q 6 ATLAS EC much weaker close to long range encounters Modules with the same beam screen and field structure behave very similarly Q 1 Q 2 Q 3 Locations of long range encounters D 1 Q 7

Inner triplets and D 1 dipoles (IR 2&8) Q 1 Nominal LHC HL-LHC Q

Inner triplets and D 1 dipoles (IR 2&8) Q 1 Nominal LHC HL-LHC Q 2 Q 3 D 1