Cost Analysis and Estimating for Engineering and Management

  • Slides: 61
Download presentation
Cost Analysis and Estimating for Engineering and Management Chapter 8 Product Estimating © 2004

Cost Analysis and Estimating for Engineering and Management Chapter 8 Product Estimating © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -1

Overview l Processes for Determining Price -Bottom Up and Top Down l Using Productive

Overview l Processes for Determining Price -Bottom Up and Top Down l Using Productive Hour Costs l Learning in Product Cost Estimating l Methods to Establish Price l Purchasing Contracts l Benchmarking © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -2

The Product Estimate l Must Include All Parts -All Operations, Direct and Indirect -Overhead,

The Product Estimate l Must Include All Parts -All Operations, Direct and Indirect -Overhead, Engineering, Sales l Determines -Price, Cost, Profit -Cash Flow, Rate of Return -Labor Requirement, Scheduling © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -3

Market Place l Market Determines Price Paid l Attainable Price Should Exceed Cost l

Market Place l Market Determines Price Paid l Attainable Price Should Exceed Cost l Price Also Determines Quantity Sold l Price from the “Top Down” -Sets Allowable Costs © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -4

Price Elements © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle

Price Elements © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -5

Estimated Cost l Components of “Cost of Goods Manufactured” and Overhead (Gen & Admin)

Estimated Cost l Components of “Cost of Goods Manufactured” and Overhead (Gen & Admin) Previous Discussions l Engineering and Sales l Contingencies -Provides for Unknowns -Radically New Products/Processes -Not for “Pad” or Poor Estimates © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -6

Product Cost Elements © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper

Product Cost Elements © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -7

Selecting Method vs Quantity © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education,

Selecting Method vs Quantity © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -8

Engineering Costs l Design of the Product l R & D l Engineering for

Engineering Costs l Design of the Product l R & D l Engineering for Products Not Produced l Support Engineering -Manufacturing, Industrial -Test, QC © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -9

Handling Engineering Costs l Overhead -Mass Production, Few New / Changes l Separate Line

Handling Engineering Costs l Overhead -Mass Production, Few New / Changes l Separate Line Item(s) -High Tech, Services l Amortize to Products Produced Eq 8. 1 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -10

Finding Engr Costs l Include All Elements -Salaries -Expenses -Overhead -Fees Paid Ce =

Finding Engr Costs l Include All Elements -Salaries -Expenses -Overhead -Fees Paid Ce = S + E + OH + F Eq 8. 2 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -11

Example of Engr Costs Work Category Hr Rate / hr Totals Engineer, senior design

Example of Engr Costs Work Category Hr Rate / hr Totals Engineer, senior design 40 $33. 00 $1, 320 Engineer, design 800 30. 00 24, 000 Designer/engineering. aide 160 18. 75 3, 000 CAD operator 80 17. 00 1, 360 Total Engineering Labor 1080 $29, 680 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -12

Information for Estimating l Need to Know: -What Does It Look Like? -How Many?

Information for Estimating l Need to Know: -What Does It Look Like? -How Many? (Will Be Made) l Determines: -Manufacturing Processes -Labor Requirements © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -13

RFE Should Include l Engineering Documents -Drawings, BOM Specs l Schedule Dates -Estimate, Production

RFE Should Include l Engineering Documents -Drawings, BOM Specs l Schedule Dates -Estimate, Production l Build Quantities © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -14

Bill of Material l One for Every Part and Assembly l Collect from the

Bill of Material l One for Every Part and Assembly l Collect from the Top Down l Include Quantities l Assemble a Structure (Tree) to Collect Estimates - From the Bottom Up l Estimate Individual Parts and Assembly © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -15

Product Tree with Costs © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education,

Product Tree with Costs © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -16

Costed Bill of Material Lvl Desc Qty Next Unit Matl Unit Labor Total Unit

Costed Bill of Material Lvl Desc Qty Next Unit Matl Unit Labor Total Unit Cost to Next 1 2 2 3 3 3 3 Top Gskt Tank Chas Screw Assy Hatch Sheet Stiffer Chas Screw N/A 1 1 4 4 1 8 4 2 3 8 $396. 24 0 10. 41. 10. 04 6. 68 46. 22 9. 57 2. 39. 10. 04 $17. 21 2. 39. 24. 04 0 3. 01 1. 68. 52. 17. 04 0 $413. 45 2. 39 10. 65. 14. 04 9. 69 47. 90 10. 09 2. 56. 14. 04 ---2. 39 10. 65. 56. 16 9. 69 383. 2 40. 36 5. 12. 42. 32 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -17

Compiling the Estimate l Need to Determine Full Cost -Includes Overhead Allocations l Two

Compiling the Estimate l Need to Determine Full Cost -Includes Overhead Allocations l Two Methods -Productive Hour Cost (PHC) -Activity Based Costing (ABC) l The Product Estimate is a Formal Document © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -18

PHC Method l Labor Estimates in Hours l Need “Rate” to Multiply for Cost

PHC Method l Labor Estimates in Hours l Need “Rate” to Multiply for Cost l PHC Rate (Section 4. 9. 5) l Labor Including -Wages, Fringes, Overhead, Indirect l Machine Costs © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -19

Calculating PHC Costs l Total Unit Cost Eq 8. 3 l Total Product Cost

Calculating PHC Costs l Total Unit Cost Eq 8. 3 l Total Product Cost Eq 8. 6 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -20

PHC Cost Example © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper

PHC Cost Example © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -21

Activity Based Costing (ABC) l PHC Ties Overhead to All Products without Regard for

Activity Based Costing (ABC) l PHC Ties Overhead to All Products without Regard for What Is Used l ABC Attempts to Allocate Overhead to Products Usage -What Is Used -How Much Is Used © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -22

ABC Concepts l Associate Overhead Costs to Activities l Predetermine O/H Costs per Unit

ABC Concepts l Associate Overhead Costs to Activities l Predetermine O/H Costs per Unit of Activity -Units May Not Always Be Hours -Total Expected Cost Divided by Total Expected Units of Activity for Rate -e. g. Purchasing Dept Cost / No. of POs © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -23

Using ABC for an Estimate l Determine O/H Activities Needed l Determine Amount of

Using ABC for an Estimate l Determine O/H Activities Needed l Determine Amount of Each Activity l Use Rate for Each Activity Eq 8. 7 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -24

Learning at the Product Level l Performance Improves with Experience l First Unit Labor

Learning at the Product Level l Performance Improves with Experience l First Unit Labor Hours Depend on -Company Experience -Amount of Preparations -Product Characteristics l Apply Learning Factor per Cost Element Eq 8. 8 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -25

Sources for Improvement l Operator (15%) l Design (50%) l Manufacturing Engineering (35%) l

Sources for Improvement l Operator (15%) l Design (50%) l Manufacturing Engineering (35%) l Requires Specific Effort l Best Candidate Products -High Cost, Low Volume © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -26

Learning Uses l Price Negotiations l Make-Buy Decisions l Product Cost Based on Prototype

Learning Uses l Price Negotiations l Make-Buy Decisions l Product Cost Based on Prototype l Costs for Additional Orders -Follow-On Procurement -Engineering Change Orders -Breakeven Analysis © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -27

Follow-On Procurement l Ref. Chapter 6 (Learning) l Determine a Learning Curve (K, s)

Follow-On Procurement l Ref. Chapter 6 (Learning) l Determine a Learning Curve (K, s) l Calculate Total Costs l Subtract Cost for First Units from Cost of All Units Through Follow On Build © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -28

Engineering Change Order (ECO) l Design Change(s) to Existing Product l ECO Affects Future

Engineering Change Order (ECO) l Design Change(s) to Existing Product l ECO Affects Future Units l Does ECO Require Change (Retrofit) to Existing Units (Prior Production)? l Is There a Change to Cost? © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -29

Simple ECO (No Retrofit) © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education,

Simple ECO (No Retrofit) © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -30

ECO with Retrofit © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper

ECO with Retrofit © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -31

Calculating a Retrofit ECO 1) Find Cost for Production of Existing 2) Find Retrofit

Calculating a Retrofit ECO 1) Find Cost for Production of Existing 2) Find Retrofit Cost 3) Find Cost for Continuing Production From ECO Incorporation to End of Run 4) Sum 1 -3 Above 5) Compare to Cost without ECO © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -32

Breakeven with Learning l Conventional Breakeven Assumes Variable Cost Is Constant Pnbe = nbe

Breakeven with Learning l Conventional Breakeven Assumes Variable Cost Is Constant Pnbe = nbe Cv + Cf Eq 8. 9 l Learning Assumes Variable Cost Decreases Eq 8. 10 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -33

Conventional Breakeven © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle

Conventional Breakeven © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -34

Breakeven with Learning © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper

Breakeven with Learning © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -35

Determining Price l Market Determines “Economic Want” l Supply and Demand l Price Customer

Determining Price l Market Determines “Economic Want” l Supply and Demand l Price Customer Will Pay l Customer’s Price Includes -Vendors Price (Cost Plus Profit) -Transportation Costs -Wholesale & Retail Costs and Profit © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -36

Producer’s Price l For Engineering Estimating -Expected Price Minus Expected Cost l Estimated Profit

Producer’s Price l For Engineering Estimating -Expected Price Minus Expected Cost l Estimated Profit May NOT Equal Actual Profit l Engineering Wants Costly Designs l Manufacturing Over-Estimates Costs l Marketing Wants Low Price l Need “Reasonable” Compromise © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -37

Pricing Concepts l Price Proportional to (Total) Cost l Price Proportional to Conversion Cost

Pricing Concepts l Price Proportional to (Total) Cost l Price Proportional to Conversion Cost l Price Proportional to Variable Cost l Price Determined by Market l Price Is Not Always the Sole Basis for Competition © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -38

Judgment Pricing l Experience l Discussion (Opinion, Conference, Comparison) l Future Will Not Be

Judgment Pricing l Experience l Discussion (Opinion, Conference, Comparison) l Future Will Not Be Like the Past © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -39

Markup on Cost l Full Cost Eq 8. 11 P = Ct + Rm(Ct)

Markup on Cost l Full Cost Eq 8. 11 P = Ct + Rm(Ct) l Value Added (Direct Labor + Overhead) P = Cdl(1 + Roh)(1 + Rm) + Cdm Eq 8. 12 l Direct Cost (Labor + Materials) P = ( Cdl + Cdm)(1 + Rm) + Coh Eq 8. 13 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -40

More Markup l Return on Investment -Return Must Exceed Capital Cost Eq 8. 14

More Markup l Return on Investment -Return Must Exceed Capital Cost Eq 8. 14 l Markup on Sales Eq 8. 15 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -41

Contribution l Price Based on Variable Costs Eq 8. 16 l Contribution Is the

Contribution l Price Based on Variable Costs Eq 8. 16 l Contribution Is the Amount Left After Paying Variable Costs l Covers Fixed Costs and Profit © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -42

Price Estimating Relationships l Prices Predicted Over a Period of Time l Market Establishes

Price Estimating Relationships l Prices Predicted Over a Period of Time l Market Establishes a Price Ceiling l Producer Establishes a Price Floor -Cost Plus Profit Required l Difference Is the Opportunity Margin l Supply and Demand Controls © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -43

Opportunity Margin l Can Be Used to Set Price l Prices Usually Decline with

Opportunity Margin l Can Be Used to Set Price l Prices Usually Decline with Time l Also Determines Life Cycle l Market Model Eq 8. 17 © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -44

Opportunity Margin Model © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper

Opportunity Margin Model © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -45

Break Even with Margins © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education,

Break Even with Margins © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -46

Contracts l Buying and Selling Involves Contracts -Purchase Orders -Quotations / Estimates -Legal Consequences

Contracts l Buying and Selling Involves Contracts -Purchase Orders -Quotations / Estimates -Legal Consequences l Two Types of Sales Contracts -Firm Fixed Price -Cost-Reimbursable © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -47

Fixed-Price Contracts l Used for -Low Tech, Well Developed Products -High Quantities -Short Duration

Fixed-Price Contracts l Used for -Low Tech, Well Developed Products -High Quantities -Short Duration l Supplier Assumes Risks If Costs Go Up l Supplier Benefits from Any Savings l Buyer Benefits from Known Price © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -48

Fixed-Price Based on Hourly Cost l Quoted Hourly Rate (PHC + Profit) l Multiplied

Fixed-Price Based on Hourly Cost l Quoted Hourly Rate (PHC + Profit) l Multiplied by Actual Time Spent l Used If Job Scope Is Unpredictable l Sometimes Bid as “Time and Materials” l Also: -Quote or Price in Effect -Pass Through Material Cost Increases © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -49

Cost Reimbursement l High Technology l High Risk l Low Degree of Definition l

Cost Reimbursement l High Technology l High Risk l Low Degree of Definition l Customer Assumes Most or All of Risk -Negotiated Risk/Benefit Sharing Proportion l “Cost Plus” a Fee or Profit -Negotiated, Sometimes with Incentives © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -50

Other Uses for Estimates l Make / Buy Decisions l Breakeven Analysis l Value

Other Uses for Estimates l Make / Buy Decisions l Breakeven Analysis l Value Engineering l Concurrent Engineering -DFM and DFA -Design to Cost © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -51

Make vs. Buy l Be Sure to Compare Equal Situations -If Make Cost Includes

Make vs. Buy l Be Sure to Compare Equal Situations -If Make Cost Includes Design Cost -Design Cost Must Be Added to Buy Price l Include ALL Costs of Buying -Transportation -In House Costs for Purchasing/Receiving -Intangibles (Quality, Schedule, etc) © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -52

Concurrent Engineering l Saves Money and Time l Reduces Changes and Time to Market

Concurrent Engineering l Saves Money and Time l Reduces Changes and Time to Market l Recognizes Cost as a Design Reqm’t l Savings -30% Less Development Time -65% Fewer Engineering Changes -20% Less Time to Market © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -53

Benchmarking – Exclusion Chart © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education,

Benchmarking – Exclusion Chart © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -54

Benchmarking – Feature Map © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education,

Benchmarking – Feature Map © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -55

Benchmarking – Envelope Fan © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education,

Benchmarking – Envelope Fan © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -56

Benchmarking – Design to Cost © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson

Benchmarking – Design to Cost © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -57

© 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ

© 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -58

© 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ

© 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -59

© 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ

© 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -60

Summary l Determined Product Costs -Applied Learning and PHC l Studied Tools for Establishing

Summary l Determined Product Costs -Applied Learning and PHC l Studied Tools for Establishing Prices -Bottom Up and Top Down l Looked at Purchasing Contracts l Peeked into the Future of Estimating © 2004 Pearson Education, Inc. Pearson Prentice Hall, Pearson Education, Upper Saddle River, NJ 07458 Ostwald and Mc. Laren / Cost Analysis and Estimating for Engineering and Management Ch 8 -61