SPSRFD and Series DQW Cryomodule Production in the

  • Slides: 23
Download presentation
SPS-RFD and Series DQW Cryomodule Production in the UK Thomas Jones (STFC) on behalf

SPS-RFD and Series DQW Cryomodule Production in the UK Thomas Jones (STFC) on behalf of the UK team International Review of the Crab Cavity system design and production plan for the HL-LHC

Contents § UK Design Contribution to SPS-RFD Cryomodule § Magnetic Shielding § Thermal Shield

Contents § UK Design Contribution to SPS-RFD Cryomodule § Magnetic Shielding § Thermal Shield § DL Infrastructure upgrades § Transportation Frame § Schedule for SPS-RFD Cryomodule build in UK § HL-LHC-UK 2 § Scope of WP 2, Series Crab Cavity Cryomodule Build in UK § Schedule for Series Crab Cryomodule Build Thomas Jones (STFC) 2

SPS-RFD Cryomodule Fundamental Power Coupler Cavity Tuner Cryogenic Safety System Frequency Scanning Interferometery Cavity

SPS-RFD Cryomodule Fundamental Power Coupler Cavity Tuner Cryogenic Safety System Frequency Scanning Interferometery Cavity Support Blades Sector Valve Vacuum Diagnostics Thermal Shield Cold Magnetic Shield Outer Magnetic Shield RF Dipole Crab Cavity Thomas Jones (STFC) 3

SPS-RFD Cold Magnetic Shield • RFD Cold Magnetic Shields designed & delivered to CERN

SPS-RFD Cold Magnetic Shield • RFD Cold Magnetic Shields designed & delivered to CERN in Apr ‘ 16 • Changes in cavity design mean shield designs require revision • Approach taken to modify & reuse existing shields (as much as possible) • Detailed design: Complete • Integration checks: On-going • Specification & Tender: On-hold New Parts Modified Parts Unchanged Thomas Jones (STFC) 4

DQW Series Cold Magnetic Shield Prototype Design New Design (Modelled in CREO) (Modelled in

DQW Series Cold Magnetic Shield Prototype Design New Design (Modelled in CREO) (Modelled in CATIA V 5) Modifications: Modifications STATUS: • Add Pick-Up Port (Mandatory) • Add Pick-Up Port (DONE) • Radius Elimination (Highly desirable) • Radius Elimination (DONE) • Brackets review (Highly desirable) • Brackets review (On-going) Thomas Jones (STFC) 5

SPS-RFD Warm Magnetic Shield Top Joint EM Gasket 2 mm Mu Metal Top Assembly

SPS-RFD Warm Magnetic Shield Top Joint EM Gasket 2 mm Mu Metal Top Assembly FPC Cover Tapped OVC Spacers Window Joint Spring Fingers Windows Lower Assembly ~150 kg Sliding Joints for OVC Tolerance Thomas Jones (STFC) 6

Thermal Shield § Al 1100 panels give significant cost and weight savings for series

Thermal Shield § Al 1100 panels give significant cost and weight savings for series production § SS 316 Cooling circuit for cryoline integration and pressure safety ‘Semi-Active’ Cooling Pin-Jointed Bracket Design Cooling Circuit Ø 15/19 316 LN ~100 kg 3 mm Al 1100 Panels Clamped Pipe. Panel Connections Thomas Jones (STFC) 7

Assembly Tooling Cleanroom Cavity String Assembly Frame Acceptance Test Frame now delivered to DL

Assembly Tooling Cleanroom Cavity String Assembly Frame Acceptance Test Frame now delivered to DL (First hardware on site) Thomas Jones (STFC) 8

Transportation Tooling See talk on ‘Transport Aspects’ by Kurt and Ed later today. Thomas

Transportation Tooling See talk on ‘Transport Aspects’ by Kurt and Ed later today. Thomas Jones (STFC) 9

Cryomodule Integration QUALITY MANAGEMENT SYSTEM – ISO 9001 : 2008 10

Cryomodule Integration QUALITY MANAGEMENT SYSTEM – ISO 9001 : 2008 10

Daresbury Engineering Technology Centre Floor Plan 23 m 21 m Survey Magnet Test ISO

Daresbury Engineering Technology Centre Floor Plan 23 m 21 m Survey Magnet Test ISO 4 Cleanroom CMM Large Systems Assembly Area 30 Tonne Crane coverage 15 m Soft wall Clean Room Vacuum Laboratory Ovens Precision Machining Centre Electrical Lab. CAM UHV Cleaning Meeting Room 30 m 40 m Reception 92 m 11

Machine Centre Cleaning in Vacuum Lab Ovens in Vacuum Lab Magnet Test Lab

Machine Centre Cleaning in Vacuum Lab Ovens in Vacuum Lab Magnet Test Lab

30 Tonne Crane 30 T Crane Assembly Hall Softwall cleanroom Large ISO 4 Cleanroom

30 Tonne Crane 30 T Crane Assembly Hall Softwall cleanroom Large ISO 4 Cleanroom Magnet Test Room ISO 4 Cleanroom Assembly Hall ISO 4 Cleanroom

SPS-RFD Schedule Thomas Jones (STFC) 14

SPS-RFD Schedule Thomas Jones (STFC) 14

HL-LHC-UK 2 § HL-LHC-UK is a collaboration of UK institutes and Universities delivering hardware

HL-LHC-UK 2 § HL-LHC-UK is a collaboration of UK institutes and Universities delivering hardware for the High Luminosity Upgrade of the Large Hadron Collider at CERN. § The current collaboration, funded by STFC, has been successful in providing Research and Development into several key areas of the upgrade including; § Work Package 1 - Beam Dynamics (led by Manchester University) § Work Package 2 - Crab Cavities (STFC-Lancaster) § Work Package 3 - Beam Diagnostics (RHUL and Liverpool University) § Work Package 4 - Cold Powering (Southampton University). § In parallel the Laser Engineered Surface Structures (LESS) project has positioned the UK (Dundee University) as a leader in LESS technology for the mitigation of Secondary Electron Yield issues in the LHC. § LESS will join the HL-LHC-UK collaboration as WP 5 for the next phase of the project known as HL-LHC-UK 2. § The project will officially commence on the 1 st April 2020, with some pre-work ongoing in 19/20. Thomas Jones (STFC) 15

HL-LHC-UK 2 Key Dates Project subject to review through STFC Projects Peer Review Panel

HL-LHC-UK 2 Key Dates Project subject to review through STFC Projects Peer Review Panel (PPRP). § 13 th September 2018 – Statement of Interest (So. I) reviewed by STFC Accelerator Strategy Board (ASB) § 16 th October 2018 – Feedback received from ASB § 4 th June 2019 – PPRP Documentation Submission § 4 th September 2019 – PPRP Review Meeting § Date TBD (October 2019) – STFC PPRP Visiting Panel meeting § Date TBD (December 2019) - STFC Science board § 1 st January 2020 – WP 5 project start § 1 st April 2020 – WP 1 to WP 4 Start. § Start Q 1 2024 to end Q 2 2026 – Long Shutdown 3 16

HL-LHC-UK 2 Project Organisation HL-LHC-UK 2 Steering Committee WP 0 HL-LHC-UK 2 Principle Investigator

HL-LHC-UK 2 Project Organisation HL-LHC-UK 2 Steering Committee WP 0 HL-LHC-UK 2 Principle Investigator R. Appleby HL-LHC-UK 2 Project Board WP 2 Oversight Committee HL-LHC-UK 2 Project Manager T. Jones STFC Programme Review Committee HL-LHC-UK 2 Technical Co. Ordinator G. Burt TD Sponsor – Ian Lazarus WP 1 Beam Dynamics Leader R. Appleby WP 2 Crab Cavities Leader N. Templeton STFC - TD WP 3 Beam Diagnostics Leader S. Gibson WP 4 Cold Powering Leader Y. Yang WP 5 LESS 2 Leader A. Abdolvand

WP 2 Scope of Work Goal: Design and procure necessary components and then to

WP 2 Scope of Work Goal: Design and procure necessary components and then to assemble 4 Double Quarter Wave Crab Cavity Cryomodules Included; Review the design of pre-series cryomodule and undertake any design modifications. The procurement from industry of the required components to produce 4 cryomodules. Assembly of 4 x Double Quarter Wave cavity strings and associated ancillaries in ISO-4 clean room. Assembly of the cryomodules (cryostating). Undertake vacuum leak tests after thermal cycling with liquid nitrogen. Design and fabrication of the transport frame. Organise shipment of Cryomodules to CERN (CERN to fund). QA management for all the above. 18

WP 2 Scope of Work Excluded Design and procurement of cavities, tuners, HOMs, RF

WP 2 Scope of Work Excluded Design and procurement of cavities, tuners, HOMs, RF Couplers, RF Probes, beam line components and Cryogenic Safety equipment. Conducting Cryogenic and/or RF performance tests at 4 K and 2 K. The conditioning and testing of the RF input couplers (It is assumed that the conditioning and testing of the RF input couplers will be performed at and by CERN). Any-reprocessing of the cavities or RF Couplers in case of contamination at any stage between arrival, assembly and transport. Transportation costs from DL to CERN. Facilities The project will utilise the infrastructure developed for the RFD-prototype cryomodule located within ETC at Daresbury Laboratory. 19

WP 2 Scope of Work Assumptions STFC will share the efforts for design with

WP 2 Scope of Work Assumptions STFC will share the efforts for design with CERN and University of Lancaster. The details of responsibilities have been agreed with CERN. Procurement responsibility will also be shared with the collaborators depending upon respective funding allocations. All required cryomodule drawings and CAD will be delivered by CERN to STFC upon project initiation. Assembly procedures for the cryomodule will be shared by CERN at timescales appropriate for the STFC project delivery. Drawings and/or CAD models for cryomodule assembly tooling will be made available to STFC by CERN at timescales appropriate for the STFC project delivery. Periodical review/progress meetings will be held with the collaborators. 20

Series Crab Cavities High Level Schedule FY - 20/21 FY - 21/22 FY -

Series Crab Cavities High Level Schedule FY - 20/21 FY - 21/22 FY - 22/23 FY - 23/24 Key RFD Pre-Series @ DL Clean room Assembly DQW Pre-Series @ CERN (CM 1) Cryomodule Assembly Acceptance and shipping from DL Cryogenic and RF testing at CERN CM 2 CM 3 CM 4 CM 5 Internal Constraints FY - 20/21 ESS BTM FY - 21/22 FY - 22/23 3 Months Same facility LHC Schedule 21 LHC Long Shutdown 2 (LS 2) FY - 23/24 PIP-II CM 1 Same staff LHC Run 3 PIP-II CM 2 LS 3 Modules installed in LHC

Conclusions and further work • • 22 Progress is on schedule for RFD SPS

Conclusions and further work • • 22 Progress is on schedule for RFD SPS Prototype assembly at Daresbury from Summer 2020. UK design responsibilities progressing well. Cold Shield designs complete, lessons learned from DQW SPS tests have been incorporated into Outer Magnetic Shield and thermal shield. Good progress on the transportation frame and internal transportation restraints working with CERN-UK need to finalise designs and begin negotiations with suppliers for Long Lead items (OVC and Cryogenic lines) • Orders to be placed for long lead items by end of September 2019. • HL-LHC-UK 2 proposal was submitted, to be reviewed in September 2019. Alan Grant

Thank you for your attention Any Questions? Thomas Jones (STFC) 23

Thank you for your attention Any Questions? Thomas Jones (STFC) 23