RF power FPC status 20150216 Eric Montesinos CERN

  • Slides: 27
Download presentation
RF power & FPC status 20150216 Eric Montesinos, CERN BE-RF on behalf of all

RF power & FPC status 20150216 Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !

RF Power system & FPC Flexwell cable Final Driver RF power systems including :

RF Power system & FPC Flexwell cable Final Driver RF power systems including : Waveguides Load FPC Cryo module SSPA Driver surface building Flexwell cable Tetrode Final (from 1996) WR 2300 Waveguide Circulator & Load Fundamental Power Coupler (FPC) • • • Two complete systems operating: 400 MHz 45 k. W CW 1 MHz maximum BW • • • LLRF Crab Cavity RF power & FPC status 2 16 February 2015

RF Amplifiers Drivers • New SSPA driver to be built • 10 European companies

RF Amplifiers Drivers • New SSPA driver to be built • 10 European companies already contacted • First prototype by June 2015 Finals • One old SPS amplifier (1996 -2000) has been successfully tested at 400 MHz up to 45 k. W CW • Five amplifiers to be modified from 352 MHz to 400 MHz • Characteristics have been checked by Philippe in January, but driver (tube) was not ok • Tests to be repeated in June Crab Cavity RF power & FPC status 3 16 February 2015

Power supplies All present HVPS are out of date Will be one HVPS per

Power supplies All present HVPS are out of date Will be one HVPS per two amplifiers to reduce the cost First new system by June 2015 Two additional new systems for SM 18 & SPS Crab Cavity RF power & FPC status 4 16 February 2015

WG & Coaxial Waveguides • Regarding frequency only WR 2300 & WR 2100 •

WG & Coaxial Waveguides • Regarding frequency only WR 2300 & WR 2100 • WR 2300 LHC standard WR Fmin MHz Fmax MHz a inch b inch Flange mm 2300 320 490 23. 0 11. 5 677 385 2100 350 530 21. 0 10. 5 626 359 Coaxial lines from SSPA Driver to Final • Pfwd = 2. 5 k. W • 1 -5/8 EIA line Coaxial lines from Final to Circulator • Pfwd = 50 k. W • 6 -1/8 EIA line Crab Cavity RF power & FPC status 5 16 February 2015

Circulators & Loads We decided to buy LHC circulators and Loads • 330 k.

Circulators & Loads We decided to buy LHC circulators and Loads • 330 k. W power capability • Re-usable with LHC main RF system Loads have already been delivered (to be modified from 4 sections to 2 sections) Circulators will be delivered by March 2015 Crab Cavity RF power & FPC status 6 16 February 2015

FPC 1. 0 (x 3 - 2013) 400 MHz 50 k. W CW FPC

FPC 1. 0 (x 3 - 2013) 400 MHz 50 k. W CW FPC full reflection all phases Agreed coaxial line OD 62 mm - ID 27 mm Coaxial disk window • Outer titanium flange • Al 2 O 3 97. 6% ceramic • Inner copper tube Coupler body • Massive copper • 316 LN Stainless Steel flanges on both sides Crab Cavity RF power & FPC status 7 16 February 2015

FPC 1. 0 (x 3 - 2013) Monitoring ports • 1 port for vacuum

FPC 1. 0 (x 3 - 2013) Monitoring ports • 1 port for vacuum gauge • 1 port for e- monitoring • 1 port for arc detector Coaxial to WG WR 2300½H transition without doorknob DC capacitor included for DC polarization Crab Cavity RF power & FPC status 8 16 February 2015

FPC 2. 0 (x 3 - 2014) Still agreed sizes on cavity side OD

FPC 2. 0 (x 3 - 2014) Still agreed sizes on cavity side OD 62 mm - ID 27 mm Conical vacuum line to increase the diameter of the ceramic in order to avoid arcing on the air side Ceramic & Air coaxial line increased OD 100 mm – ID 43. 5 mm Robust ceramic Thickness 20 mm Crab Cavity RF power & FPC status 9 16 February 2015

FPC 2. 0 Pseudo-conical air extension cooled with forced air Even if against CERN’s

FPC 2. 0 Pseudo-conical air extension cooled with forced air Even if against CERN’s rules regarding joining, as no other way to do it, water cooled antenna Mandatory vacuum gauge for coupler protection No more arc detector window neither e- antenna to ease integration Crab Cavity RF power & FPC status 10 16 February 2015

FPC 2. 0 (x 3 - 2014) Crab Cavity RF power & FPC status

FPC 2. 0 (x 3 - 2014) Crab Cavity RF power & FPC status 11 16 February 2015

Antenna overheating Looking at the size of the hook, no way to design a

Antenna overheating Looking at the size of the hook, no way to design a cooling circuit which also cools down the curved part of the hook Initial design of coupling elements (BNL-ODU) shown overheating up to an unacceptable temperature New coupling element shapes have been designed allowing acceptable temperature for the three couplers Crab Cavity RF power & FPC status 12 16 February 2015

FPC 3. 0 (x 2 - Fall 2014) Two versions only Pseudo-conical air extension

FPC 3. 0 (x 2 - Fall 2014) Two versions only Pseudo-conical air extension cooled with forced air Water cooled antenna Slightly different hook & RFD longer than DQW Mandatory vacuum gauge for coupler protection Crab Cavity RF power & FPC status 13 16 February 2015

FPC 3. 0 (x 2 - Fall 2014) June 2015 Crab Cavity RF power

FPC 3. 0 (x 2 - Fall 2014) June 2015 Crab Cavity RF power & FPC status December 2015 14 16 February 2015

Test boxes Two test boxes will be built allowing the preparation of pair of

Test boxes Two test boxes will be built allowing the preparation of pair of couplers They have to be customized regarding the coupling element for each cavity design Coupling element has been defined very late (November 2014) Need 12 months to build these test boxes, ready by beginning 2016 Crab Cavity RF power & FPC status 15 16 February 2015

FPC 3. 0 as delivered to clean room Q 2 -2016 Crab Cavity RF

FPC 3. 0 as delivered to clean room Q 2 -2016 Crab Cavity RF power & FPC status 16 16 February 2015

Schedule February 2015 2013 Hook definition 2014 →→→ 2015 →→→ 2016 RF processing →

Schedule February 2015 2013 Hook definition 2014 →→→ 2015 →→→ 2016 RF processing → → → 2017 SPS → → ? ? ? FPC Construction SM 18 tests SM 18 FPC Construction tests Ø FPC design was missing coupling element definition until November 2014 (Test cavity impossible to be designed) Ø Couplers processed 40 k. W SW CW all phases Q 2 -2016 Ø Cavities to be installed in the SPS in December 2016 ? ? ? Crab Cavity RF power & FPC status 17 16 February 2015

Space request HVPS RF Finals Surface building • • • 10 racks equivalent Ua

Space request HVPS RF Finals Surface building • • • 10 racks equivalent Ua (8 racks equivalent RF amplifiers) 2 racks Grids 2 racks SSPA Drivers 2 racks Controls & Monitoring 3 x 5 m 4 x 5 m 2. 8 x 5. 6 m Machine • (Space on moveable platform) (2 amplifiers + 2 circulators + 2 loads) • Water pump • Blowers • HV filtering box Crab Cavity RF power & FPC status 18 Controls SSA Driver 16 February 2015 Grids

Movable table Phoevos Kardasopoulos Crab Cavity RF power & FPC status 19 16 February

Movable table Phoevos Kardasopoulos Crab Cavity RF power & FPC status 19 16 February 2015

Two Tetrodes Amplifiers onto the table Phoevos Kardasopoulos Crab Cavity RF power & FPC

Two Tetrodes Amplifiers onto the table Phoevos Kardasopoulos Crab Cavity RF power & FPC status 20 16 February 2015

Circulators & power Loads (with adjustable supporting system for integration of all three designs)

Circulators & power Loads (with adjustable supporting system for integration of all three designs) Phoevos Kardasopoulos Crab Cavity RF power & FPC status 21 16 February 2015

Waveguides to FPC Phoevos Kardasopoulos Crab Cavity RF power & FPC status 22 16

Waveguides to FPC Phoevos Kardasopoulos Crab Cavity RF power & FPC status 22 16 February 2015

Cryomodule with FPC Phoevos Kardasopoulos Crab Cavity RF power & FPC status 23 16

Cryomodule with FPC Phoevos Kardasopoulos Crab Cavity RF power & FPC status 23 16 February 2015

Flexible WG (allowing integration of all three designs) Phoevos Kardasopoulos Crab Cavity RF power

Flexible WG (allowing integration of all three designs) Phoevos Kardasopoulos Crab Cavity RF power & FPC status 24 16 February 2015

Flexible WG (allowing integration of all three designs) Phoevos Kardasopoulos Crab Cavity RF power

Flexible WG (allowing integration of all three designs) Phoevos Kardasopoulos Crab Cavity RF power & FPC status 25 16 February 2015

Services Electrical network • Power: 250 k. VA • UPS: 10 k. VA Cooling

Services Electrical network • Power: 250 k. VA • UPS: 10 k. VA Cooling & Ventilation • Water: 100 k. W • Air: 20 k. W Crab Cavity RF power & FPC status HVPS + SSPA Drivers accessible with beam Finals accessible with RF on short at the output of the circulator Control room for Controls and Monitoring & LLRF 26 16 February 2015

Thank you Crab Cavity RF power & FPC status 27 16 February 2015

Thank you Crab Cavity RF power & FPC status 27 16 February 2015