Laser Deposited and PreHardened Steel Rapid Tooling Case

  • Slides: 38
Download presentation
Laser Deposited and Pre-Hardened Steel Rapid Tooling Case Western Reserve University / NADCA David

Laser Deposited and Pre-Hardened Steel Rapid Tooling Case Western Reserve University / NADCA David Schwam

Die Cast Aluminum Heat Sinks for Tank Tracks Material: A 380 Size: 4. 5”x

Die Cast Aluminum Heat Sinks for Tank Tracks Material: A 380 Size: 4. 5”x 2. 5”x 1. 15” Weight: 1. 1 pounds ABSORBS HEAT FROM THE RUBBER, EXTEND TRACK LIFE, PREVENT STRIP-OFF FAILURE

Die Cast Aluminum Heat Sinks for Tank Tracks Industrial Partner: St. Clair Die Casting,

Die Cast Aluminum Heat Sinks for Tank Tracks Industrial Partner: St. Clair Die Casting, St. Clair. MO Die Material: Pre-hardened 42 HRC Dievar Leadtime: Three weeks Key Advantage: Short lead time. 49, 000 parts (x 4) were die cast with this pre-hardened tool.

Shovel Nut DLA part. Industrial Partner: Empire Die Casting-Twinsburg, OH Die Material: Pre-hardened 42

Shovel Nut DLA part. Industrial Partner: Empire Die Casting-Twinsburg, OH Die Material: Pre-hardened 42 HRC Dievar Leadtime: Three weeks (instead of 14 weeks) Key Advantage: Two hundred prototype parts were initially required. Production run is expected to exceed 100, 000. So far at 49, 000. The projects is running production with the prototyping tool, thus saving the entire cost of tooling.

Display Control Module DRS’s Driver’s Vision Enhancer (DVE) Display Control Module (DCM) is a

Display Control Module DRS’s Driver’s Vision Enhancer (DVE) Display Control Module (DCM) is a 10. 4" liquid-crystal display (LCD) providing a rugged display technology to the warfighter on today’s digital battlefield.

Warfighter Relevance

Warfighter Relevance

Objectives Problem • Current tool building practices are costly and time consuming • require

Objectives Problem • Current tool building practices are costly and time consuming • require sequential rough machining • heat treating • machining to final size • use steel that does not allow fast heat removal and optimal control of thermal profile Objective • Demonstrate rapid tooling methods • Use of pre-hardened steels to shorten lead times and extend die life • Use of high thermal conductivity materials including Toolox 44, Anviloy and laser deposited rapid and bimetallic tooling to improve rate of production

Benefits • Accelerate fabrication of parts made by metal mold technologies • Rapid tooling

Benefits • Accelerate fabrication of parts made by metal mold technologies • Rapid tooling for die and permanent mold casting – More adaptive to frequent changes in design than traditional tool making methods – Can quickly provide small, prototype batches yet, if needed, make production quantities • Demonstrate increased productivity and better mechanical properties of the castings by use of high thermal conductivity die materials

Technical Approach Utilization of pre-hardened advanced steels to shorten lead-time and lower tooling cost

Technical Approach Utilization of pre-hardened advanced steels to shorten lead-time and lower tooling cost Use of high thermal conductivity materials (laser deposited H 13 on copper, Toolox 44 and Anviloy cores)

Utilization of Pre-Hardened Superior Steels to Shorten Lead-Time and Lower Tooling Cost

Utilization of Pre-Hardened Superior Steels to Shorten Lead-Time and Lower Tooling Cost

Display Control Module

Display Control Module

Implementation at Twin Cities Die Casting • Anticipated production was 40, 000 parts •

Implementation at Twin Cities Die Casting • Anticipated production was 40, 000 parts • Using Pre-hardened tool steels of various types. Heat treat was 40 – 42 RC. • Machining method was primarily High Speed but some Electro-Discharge Machining also.

Project Volume Increased • Original plan was to cast no more than 40, 000

Project Volume Increased • Original plan was to cast no more than 40, 000 parts. • Tooling started to show some washout and heat checking around 20, 000 shots. • Notified by customer that there would be a second order coming after completing the first 40, 000 parts.

Heat Check and Washout Inside after 24, 000 shots

Heat Check and Washout Inside after 24, 000 shots

Heat Checking Outside after 24, 000 Shots

Heat Checking Outside after 24, 000 Shots

Steel Repair Method • Steel checked for hardness. Steel had softened through usage to

Steel Repair Method • Steel checked for hardness. Steel had softened through usage to 39– 40 HRC down from 40 -42 HRC. • Cavity steel was ultrasonically cleaned, machined, welded and re-cut, polished and then nitrocarburized after 28, 000 shots. • Repair lasted balance of first order.

After Repair at 38, 000 Shots

After Repair at 38, 000 Shots

After Repair at 38, 000 Shots

After Repair at 38, 000 Shots

Tool Steel after First 40, 000 Shots

Tool Steel after First 40, 000 Shots

Next Order is Being Processed for 20, 000 Parts • Steel has been polished

Next Order is Being Processed for 20, 000 Parts • Steel has been polished and then Shot Peened. • Nitride re-applied after last maintenance. • Steel checks 39– 40 HRC; no change from 20, 000 shots. • Estimated life to replacement is another 40, 000 shots. • Cost and time metrics needed

Use of High Thermal Conductivity Materials: Laser Deposited H 13 on Copper, Toolox 44

Use of High Thermal Conductivity Materials: Laser Deposited H 13 on Copper, Toolox 44 and Anviloy cores

Rapid Tooling Method 1 Direct Metal Deposition of H 13 on Copper - the

Rapid Tooling Method 1 Direct Metal Deposition of H 13 on Copper - the POM Method *-Courtesy POM

Die Cast Part for Evaluation of Improved Cores The core is surrounded by molten

Die Cast Part for Evaluation of Improved Cores The core is surrounded by molten aluminum therefore overheats and solders. Extracting heat more efficiently from the core can lower temperature, prevent soldering and allow shorter cycle times.

H 13 Deposited on Cu – ready for machining

H 13 Deposited on Cu – ready for machining

H 13/ Copper Core after 250 cycles The core creeps due to insufficient stiffness

H 13/ Copper Core after 250 cycles The core creeps due to insufficient stiffness and strength at high temperature.

Remedial Approaches Caves in Bulges out The distortion of the core seems to originate

Remedial Approaches Caves in Bulges out The distortion of the core seems to originate from insufficient strength and stiffness at the operating temperature. Anviloy and H 13 cores do not suffer from this problem. Priority 1 - Increase strength: use core as deposited w/o tempering (downside-lower toughness). Priority 2 - Increase thickness of H 13 layer(downsideslows down heat transfer). Use computer simulation

Technical Progress • The life of the laser deposited core has been extended to

Technical Progress • The life of the laser deposited core has been extended to 5, 000+ shots. • A computer modeling effort is underway to optimize thickness of the laser deposited H 13 layer. • Other high thermal conductivity die materials (Toolox 44, Anviloy) are being tested. • A current NADCA/NEMAK/GM project is leveraging this effort.

Finite Element Model Steel H 13 solidification cavity fill 1 cycle Copper Alloy 300

Finite Element Model Steel H 13 solidification cavity fill 1 cycle Copper Alloy 300 o. F constant Axi-symmetric analysis model Temperature variation along outer surface

Temperature and stress field at the end of cavity fill (deformation is enlarged by

Temperature and stress field at the end of cavity fill (deformation is enlarged by 100) Temperature (o. F) σVon Mises (Psi)

Project Plans • High cooling rates the mechanical properties. Shown is the improvement in

Project Plans • High cooling rates the mechanical properties. Shown is the improvement in Dendrite Arm Spacing (DAS) and respective tensile strength caused by a water cooled core.

Improving Mechanical Properties with High Thermal Conductivity Cores High thermal conductivity, cooled cores in

Improving Mechanical Properties with High Thermal Conductivity Cores High thermal conductivity, cooled cores in die cast aluminum blocks

H 13 Toolox 44 Anviloy 3 C Cu. Be 32

H 13 Toolox 44 Anviloy 3 C Cu. Be 32

Project Plans • Continue Utilization of Pre-Hardened Superior Steels to Shorten Lead-Time and Lower

Project Plans • Continue Utilization of Pre-Hardened Superior Steels to Shorten Lead-Time and Lower Tooling Cost for Control Display Module • A computer modeling effort is underway to optimize thickness of the laser deposited H 13 layer.

Implementation

Implementation

Conclusions • Use of high conductivity alloys in die components can shorten cycle time

Conclusions • Use of high conductivity alloys in die components can shorten cycle time significantly. • In the present case, the cycle time dropped from 55 sec. for H 13 to 40 sec. (13% ) • The life of a tempered, 40 HRC H 13/ Copper laser deposited core was 250 cycles. By using the core in the as -deposited condition at 51 HRC, life was extended to 5, 000+ cycles and going. • The balance between strength and toughness is critical to ensure durability of the core. High strength is required to prevent distortion while high toughness avoids cracking.

Project Metrics Description Baseline Goal Target Date (Month/Year) 6 ft-lb 8 ft-lb Dec 2008

Project Metrics Description Baseline Goal Target Date (Month/Year) 6 ft-lb 8 ft-lb Dec 2008 7. 75 ft-lb No. Shots • Pre. Hardened 10, 000 shots(P 20) 30, 000 July 2009 20, 000 in progress 50% Enhanced cooling • Spray formed – Die Temperature Die Surface 800 o. F Die Surface 700 o. F July 2010 720 o. F 80% Improved Elongation • Cooled core- 0. 5% 2% July 2010 New task for 2009/2010 Toughness • Spray formed Progress % Accomp. 87. 5%

JDMTP Criteria - Summary Jointness B – Benefit to more than one service, but

JDMTP Criteria - Summary Jointness B – Benefit to more than one service, but not jointly funded Needs and Benefits • Needs : Short lead times for rapid prototyping and legacy parts. • Benefits: Up to 75% shorter lead time, depending on the part. • Benefits: 20% shorter cycle time Transition • Parts under evaluation at Empire Die Casting-2007 • Parts under evaluation at St. Clair Die Casting-2007 • Production of new part at Twin City Die Casting • Composite cores in production at General Die Casters • Results disseminated through NADCA committee meetings, NADCA publications for industry, and the Metalcasting Congress Leveraging • Building on previous AMC and NADCA/DOE work • Leveraged by current NADCA/NEMAK/GM project Relevance to Sustainment of Weapons Systems • Strengthen supply chain by increasing number of metal mold suppliers able to meet DLA requirements. • Shorten lead time for procurement of components for legacy systems. • Improved mechanical properties of components. MRL 6 - Manufacturing capability to produce in a production representative environment

Laser Deposited and Pre-Hardened Steel Rapid Tooling DLA - POC: Dean Hutchins (dean. hutchins@dla.

Laser Deposited and Pre-Hardened Steel Rapid Tooling DLA - POC: Dean Hutchins (dean. hutchins@dla. mil, 804 -279 -5033) Partners: – Case Western Reserve, Twin City Die Casting, POM, DCD, NADCA, St. Clair Die Casting, Genral Die Casting, Empire Die Casting Problems: • Standard tooling for metal mold processes requires long lead times • High cycle times in the production of metal mold castings Objective: • Evaluate advanced cooling techniques and rapid tooling techniques to reduce lead times Benefits: • Demonstrate increased productivity by utilizing rapid tooling techniques and improve properties by incorporating high thermal conductivity die materials Milestones / Deliverables • Evaluation of toughness and thermal fatigue of dies with deposited materials • Optimization of laser deposited H 13 layer Transition Plan • The optimized laser deposited cores will be evaluated in production