INTRODUCTION OF CONSTRUCTION CLAIMS What are Claims Types

  • Slides: 30
Download presentation
INTRODUCTION OF CONSTRUCTION CLAIMS • What are Claims • Types of Claims • Objectives

INTRODUCTION OF CONSTRUCTION CLAIMS • What are Claims • Types of Claims • Objectives of Claims • Points to be considered before proceeding • Notices of Claims • Interference by the Employer • Claims against Consultants • Construction Contracts • Documents relating to claims • Procedures of Claims

WHAT ARE CLAIMS? The definition of a claim in a dictionary is an assertion

WHAT ARE CLAIMS? The definition of a claim in a dictionary is an assertion of a right to something. Claim is the demand for something supposed to be due TIME CLAIMS COST CLAIMS PAYMENT CLAIMS Consideration & normal, therefore excluded from this topic

TYPES OF COST CLAIMS • Loss / expenses (Damages) • Additional payment under specific

TYPES OF COST CLAIMS • Loss / expenses (Damages) • Additional payment under specific provisions of the contract • Variations • Disruption • Prolongation

TYPES OF CLAIMS COMMON LAW/ EX-CONTRACTUAL EX-GRATIA

TYPES OF CLAIMS COMMON LAW/ EX-CONTRACTUAL EX-GRATIA

CONTRACTUAL CLAIMS Where the contract provides for the event or circumstances being complained of.

CONTRACTUAL CLAIMS Where the contract provides for the event or circumstances being complained of. Clearly this should be the first line of consideration as it is pointless to look elsewhere and rely upon common law rights when express provision exists. Further, contractual matters are usually within the powers of the Architect/Engineer to settle. (SFBC Cl 11(6), 24 & 34(3)

EX-CONTRACTUAL / COMMON LAW CLAIMS • Where the contract does not make express provision

EX-CONTRACTUAL / COMMON LAW CLAIMS • Where the contract does not make express provision and therefore grounds outside the contract have to be sought - i. e. in common law. • Such claims are usually outside the Architect's /Engineer's power and require specific authority from the Employer for them to examine the claims and make appropriate recommendations.

EX-GRATIA CLAIMS • By definition such claims have no grounds upon which either side

EX-GRATIA CLAIMS • By definition such claims have no grounds upon which either side could successfully sue the other at law. • Their only basis is that a loss has been made and that something more tangible than sympathy is being sought, but anything paid will be an 'act of grace' with, at best, some possible acknowledgement of morale obligation. • These claims should not be resorted to if contractual or extra-contractual claims exist. • Ex-gratia claims are sympathy claims

CAUSES OF CLAIMS • Late payments • Changes in conditions • Delay / interference

CAUSES OF CLAIMS • Late payments • Changes in conditions • Delay / interference • Acceleration • Errors / omissions in design / document • Suspension of the work • Variations • Rejection of "or similar" substitutions • Unclear responsibilities of the contractor / employer • Failure in precontract planning

OBJECTIVES OF CLAIMS Objectives of time claims • To extend the contract completion time

OBJECTIVES OF CLAIMS Objectives of time claims • To extend the contract completion time • To reduce the amount of L. D. liable to pay to the Employer • To prepare for the claims for the cost claims (remember this is not automatically) Objectives of cost claims • To reimburse the loss & expenses incurred • To compensate the extra preliminaries due to delay by the faults of the Architect, etc. Objectives of ex-gratia claims • To ask for sympathy in compensation, which has no contractual grounds for the claims, for the best efforts the contractor has put.

POINTS TO BE CONSIDERED BEFORE PROCEEDING • Claims should be well planned at the

POINTS TO BE CONSIDERED BEFORE PROCEEDING • Claims should be well planned at the beginning of the contract rather than at the end of the contract • Check the contractual grounds before claim contractual justification, i. e. identify the contract condition(s) • The event giving rise to the claim should be actually occurred • True cause(s) of the claim should be identified • Surrounding circumstance relating to the claim should be recorded • A good claim should be well organised and presented in a concise way • Understand the attitude of the Employer to claims

NOTICES OF CLAIMS A contractor MUST GIVE NOTICE of his intention to claim extension

NOTICES OF CLAIMS A contractor MUST GIVE NOTICE of his intention to claim extension of time or additional payment - for whatever reason; and the notice must be given as soon as it becomes apparent or within the time limited set out in the contract. Failing to do this may • prejudice (not necessarily invalidating the claim) the establishment of claims • affect the ability of the Architect/Engineer/Quantity Surveyor to consider and evaluate them properly • damage or seriously impair credibility of such claims.

PURPOSES OF THE NOTICES OF CLAIMS • Proper notice will enable the pros and

PURPOSES OF THE NOTICES OF CLAIMS • Proper notice will enable the pros and cons of entitlement to be discussed, • The setting up of records (if necessary without prejudice to liability in the first place) required to establish the quantum of the claim. • In some cases it may enable the Architect/Engineer to take action to reduce or mitigate potential loss by issuing a variation order - which would not be possible if notices were delayed until work was complete or the claim itself presented. • If the Contractor has not submitted a written claims at all, there would be no consideration and the claim procedure would not even commence.

NOTICES OF CLAIMS Is giving notice of claim a condition precedent to the contractor's

NOTICES OF CLAIMS Is giving notice of claim a condition precedent to the contractor's entitlement of claims ? No in most cases. Crosby v. Portland UDC "Provided that the contractor shall not be entitled to recover any extra cost unless he gives written notice of his intention to claim to the Engineer within twenty-eight days of the Engineer's order" The claim was rejected as the contractor has not given notice within the specified period.

HOW CAN NOTICES OF CLAIMS BE PRECEDENT TO CLAIM ? To be a condition

HOW CAN NOTICES OF CLAIMS BE PRECEDENT TO CLAIM ? To be a condition precedent to claim, two elements must be presented: G The precise time within which the notice was to be served should be stated AIt was expressly stated that the rights of claims are forfeited unless notice was served within that time.

INTERFERENCE BY THE EMPLOYER Architect should act: fairly impartially Employer influenced the Architect to

INTERFERENCE BY THE EMPLOYER Architect should act: fairly impartially Employer influenced the Architect to undercertify the payment Contractor can claim interest on the undercertified amount

INTERFERENCE BY THE EMPLOYER Employer influenced the Architect not to issue EOT even if

INTERFERENCE BY THE EMPLOYER Employer influenced the Architect not to issue EOT even if the grounds are valid Contractor accelerated the program Contractor later recognized Employer's interference Recover the acceleration costs OR Rescind the contract + quantum meruit

CLAIMS AGAINST CONSULTANTS Sutcliffe V. Thackrah (1974) Consultants have duty of care owed to

CLAIMS AGAINST CONSULTANTS Sutcliffe V. Thackrah (1974) Consultants have duty of care owed to the contractor 'Negligence' is the label given to certain courses of conduct which fall below a standard acceptable to the community. The criterion is the model conduct of a 'reasonable man'. Claim for damages against the consultants

CLAIMS FOR PROFESSIONAL NEGLIGENCE For a successful claim, the contractor suing in negligence must

CLAIMS FOR PROFESSIONAL NEGLIGENCE For a successful claim, the contractor suing in negligence must prove three points to maintain a successful claim: • The consultant was under a duty of care to the contractor • There had been a breach of that duty • As a result the contractor has suffered damage

DUTY OF CARE You must take reasonable care to avoid acts or omissions which

DUTY OF CARE You must take reasonable care to avoid acts or omissions which you can reasonably foresee would be likely to injure your neighbour. Neighbour - persons who are so closely and directly affected by your act that you ought reasonably have them in contemplation as being so affected when you are directing your mind to the acts or omissions which are called in question.

STANDARD OF CARE A reasonable man would use or show in the circumstances of

STANDARD OF CARE A reasonable man would use or show in the circumstances of the particular case under consideration. So, the injury must have been reasonably foreseeable, and the effect must be the direct result of the defendant's act. The test of foreseeablility is applied much more positively by the courts when the source of the liability is active misconduct than when is failure to act.

FORESEEABILITY OF CARE Therefore, • The damage or harm to the plaintiff was reasonably

FORESEEABILITY OF CARE Therefore, • The damage or harm to the plaintiff was reasonably foreseeable by the defendant • The relationship between them was sufficiently proximate to give rise to a duty • It is just and reasonable to impose such a duty (which includes considerations of public policy)

BREACH OF DUTY • When there is a greater risk of injury, more precautions

BREACH OF DUTY • When there is a greater risk of injury, more precautions will be expected. • If reasonable precautions are taken against the risk of harm, the duty of care will be discharged, and no action will lie.

DAMAGES • Merely exposing someone to danger is not an actionable wrong, there must

DAMAGES • Merely exposing someone to danger is not an actionable wrong, there must be some actual detriment as a result of the exposure. • The damages are subject to the test of remoteness of damage. The problem of 'proximate cause' involves two factors; the factual question of whether the defendant's breach of duty and the plaintiff's injury constitute a cause-and-effect relationship, and where to draw the line in a consequential sequence of events which result in injury.

CONCLUSION OF NEGLIGENCE · · · In laying down the limits of liability for

CONCLUSION OF NEGLIGENCE · · · In laying down the limits of liability for negligent conduct, the courts have developed certain concepts which form the basic ingredients of actionable negligence. These elements are : a duty, legally recognized, not to expose others to unreasonable risks, conduct which falls below the accepted standard, or breach of that duty, material injury resulting from the sub-standard conduct, a reasonably close connection between the conduct and the injury ( the question of 'remoteness of damage') and the absence of conduct by the plaintiff which caused his injuries

CONSTRUCTION CONTRACTS In the forthcoming lectures, the following forms of contract will be referred

CONSTRUCTION CONTRACTS In the forthcoming lectures, the following forms of contract will be referred to : • Agreement & Schedule of Conditions of Building Contract for use in the Hong Kong Special Administrative Region (Private Edition - with or without quantities) - Second amendments published in July 1999 • Sub-contract for use where the Subcontractor is nominated under the Standard Form of Building Contract for Hong Kong Second amendments published in February 2000

TIME & COST CLAIMS IN SFBC(HK) EVENT TIME BORNE BY Force majeure Employer Inclement

TIME & COST CLAIMS IN SFBC(HK) EVENT TIME BORNE BY Force majeure Employer Inclement weather Employer Fire, lightning, etc. Employer Civil commotion Employer Discrepancy Employer A. I. Employer Postponement Employer Late instructions Employer NSC delay Employer's worker Employer Opening up Employer Labor & materials Employer Antiquities Employer ………. CLAUSE 23(a) 23(b) 23(c) 23(d) 23(e) 23(f) 23(g) 23(h) 23(i) 23(j) 23(k) COST BORNE BY Contractor Employer Employer Contractor Employer CLAUSE 24 24 24(1)(c) 11 24(1)(e) 24 24(1)(a) 24(1)(d) 24(1)(b) 24 34(3)

DOCUMENTS RELATING TO CLAIMS Pre-tender documents • • Contract bills • • Schedules of

DOCUMENTS RELATING TO CLAIMS Pre-tender documents • • Contract bills • • Schedules of work • • Specification • • Contract drawings • • Programs • Method statements Post-tender documents • • Instructions / variations • • • Further drawings • • Levels & setting out • information Correspondence Minutes of meetings Site diaries /Daily report Progress photos & chart Materials delivery schedules Invoices Payroll sheet Plant records Scaffolding records Daywork schedule

PROCEDURES OF CLAIM • • • Notices of claims Establishing the Claims Examining the

PROCEDURES OF CLAIM • • • Notices of claims Establishing the Claims Examining the claims Evaluating the Claims Negotiating and settling the claims

ESTABLISHING CLAIMS Establishing a claim simply means making the other party being convinced that

ESTABLISHING CLAIMS Establishing a claim simply means making the other party being convinced that the claim is valid and that the integral parts are claimable and correctly valued. The establishing procedure shall consist of two steps : n Establishing the validity of the grounds of claim. n Proofing the effects of such disruption / disturbance of regular progress of the works by substantiating the accurate and factual documentation of performance, records, correspondence, inspection reports, photographs programmes, etc.

EXAMINING, EVALUATING NEGOTIATING & SETTLING CLAIMS • Early settlement / evaluation of claims are

EXAMINING, EVALUATING NEGOTIATING & SETTLING CLAIMS • Early settlement / evaluation of claims are preferred as the facts are fresh in the parties' minds • Details to be discussed in Lecture 6