Description of the LCLS Undulator System Stephen Milton Argonne National Laboratory Office of Science

Description of the LCLS Undulator System Stephen Milton Argonne National Laboratory Office of Science U. S. Department of Energy A U. S. Department of Energy Office of Science Laboratory Operated by The University of Chicago

Overview Pioneering Science and Technology Office of Science U. S. Department of Energy

Overview Pioneering Science and Technology Office of Science U. S. Department of Energy

Undulator Systems WBS 1. 2. 3 Undulator Systems WBS 1. 4 Pioneering Science and

Undulator Systems WBS 1. 2. 3 Undulator Systems WBS 1. 4 Pioneering Science and Technology Office of Science U. S. Department of Energy

Cell structure of the LCLS Undulator Line 3420 657 421 UNDULATOR 11528 mm Horizontal

Cell structure of the LCLS Undulator Line 3420 657 421 UNDULATOR 11528 mm Horizontal Steering Coil Vertical Steering Coil Beam Position Monitor X-Ray Diagnostics 33 Undulators ~ 130 -m Overall Length Quadrupoles Pioneering Science and Technology Office of Science U. S. Department of Energy

List of the Undulator Line Systems • Undulator module – Magnets – Poles –

List of the Undulator Line Systems • Undulator module – Magnets – Poles – Strongback – Other • Mechanical support - movers • Quadrupole Lens • Coils - correctors • E-beam position monitors • X-ray diagnostics • Undulator vacuum chamber and diagnostics station • Controls and data acquisition • Support laboratory - magnet measurement facility – Technical Definition and Oversight Only Pioneering Science and Technology Office of Science U. S. Department of Energy

LCLS Project Engineering Design Organization Pioneering Science and Technology UCLA Office of Science U.

LCLS Project Engineering Design Organization Pioneering Science and Technology UCLA Office of Science U. S. Department of Energy

PED Organization LCLS Undulator Management Project Leader Fabrication Management Project and Contract Assistant S.

PED Organization LCLS Undulator Management Project Leader Fabrication Management Project and Contract Assistant S. Milton J. Noonan F. Coose Diagnostics And Vacuum Controls Magnet Systems D. Walters J. Stein J. Noonan Low Power X-ray Diag. Magnet Systems 2 nd Prototype High-Power X-Ray Diag. X-ray Diagnostics Undulator Magnets End of Und. X-ray Diag. Electron Beam Diagnostics Quadrupole Magnets Electron Beam Diag. Vacuum System Supports Vacuum System Machine Protection System Pioneering Science and Technology Office of Science U. S. Department of Energy

Prototypes Pioneering Science and Technology Office of Science U. S. Department of Energy

Prototypes Pioneering Science and Technology Office of Science U. S. Department of Energy

Undulator Design Issue • Field Variations – Must Maintain DB/B < 1 x 10

Undulator Design Issue • Field Variations – Must Maintain DB/B < 1 x 10 -4 • Implies gap changes of < 1 mm • And to maintain temperature to within 0. 4 C • Partial Compensation – Accomplished by Differential expansion of the titanium strong back and the aluminum magnet array comb. – This helped, but did not fully compensate the device – A Clever Field Control Scheme will be used Pioneering Science and Technology Office of Science U. S. Department of Energy

Full Length Prototype Performance Measured to be within the Design Specification Device completed over

Full Length Prototype Performance Measured to be within the Design Specification Device completed over a year and ½ ago. Pioneering Science and Technology Office of Science U. S. Department of Energy

2 nd Prototype Pioneering Science and Technology Office of Science U. S. Department of

2 nd Prototype Pioneering Science and Technology Office of Science U. S. Department of Energy

Undulator System Schedule Pioneering Science and Technology Office of Science U. S. Department of

Undulator System Schedule Pioneering Science and Technology Office of Science U. S. Department of Energy

Milestone Summary of Schedule Milestone Design of 2 nd undulator prototype complete Assembly and

Milestone Summary of Schedule Milestone Design of 2 nd undulator prototype complete Assembly and Testing of 2 nd prototype undulator complete Bid package for undulator assembly complete First production undulator complete 33 rd production undulator complete Installation of undulator system complete Date 2/04 9/04 7/1/05 6/1/07 7/1/07 See J. Noonan’s presentation for a more thorough summary and explanation Pioneering Science and Technology Office of Science U. S. Department of Energy

Where We Stand • In the Project Engineering Design Phase • Need to ramp

Where We Stand • In the Project Engineering Design Phase • Need to ramp up in staffing…quickly! • 10 to 15 people working full time within 6 months to 1 year • People will be drawn from APS and ANL when possible • Contract work out as necessary • Project will be Baselined in April 2004 • Long-lead procurements begin in FY 05 • “Real” Construction begins in FY 06 • Undulator installed and ready to go in Summer 2007 • First Operations in Winter 2008 Pioneering Science and Technology Office of Science U. S. Department of Energy

Charge for the LCLS Undulator Magnet Review Committee: Nov. 14 th, 2003 1. Review

Charge for the LCLS Undulator Magnet Review Committee: Nov. 14 th, 2003 1. Review the overall design and design/engineering decisions/solutions used for the 1 st prototype undulator magnet and comment on the appropriateness of these decisions with respect to minimizing risk in meeting LCLS performance specifications. In particular, is this a robust design capable of being mass produced. 2. Assess the overall quality and appropriateness of the measurements and tuning methods. In particular, has a suitable set of measurements been carried out on the 1 st prototype to prove that it has achieved the required specifications without undue difficulty in manufacturing, and has this design been proven to be sufficiently stable over time? 3. Based on the knowledge gained from the 1 st prototype have the appropriate design modifications been made and, in your opinion, will they be successful in a mass produced device? 4. The 2 nd prototype will be constructed in a manner similar to the acquisition plan for the production run. I would like your comments on the acquisition plan and schedule for the 2 nd prototype and the production magnets. Pioneering Science and Technology Office of Science U. S. Department of Energy