Systems Analysis and Design in a Changing World
- Slides: 65
Systems Analysis and Design in a Changing World, Fifth Edition 3
3 Learning Objectives Explain the elements of project management and the responsibilities of a project manager Explain project initiation and the activities in the project planning phase of the SDLC Describe how the scope of the new system is determined Systems Analysis and Design in a Changing World, 5 th Edition 2
3 Learning Objectives (continued) Develop a project schedule using Gantt charts Develop a cost/benefit analysis and assess the feasibility of a proposed project Discuss how to staff and launch a project Systems Analysis and Design in a Changing World, 5 th Edition 3
3 Overview Fundamental principles of project management Role of project manager Project management as part of the SDLC Project management knowledge areas How information system projects initiated RMO project initiation Systems Analysis and Design in a Changing World, 5 th Edition 4
3 Overview (continued) The project planning activities within the SDLC Planning the problem needing an IS solution Developing a project schedule Confirming Staffing Project project feasibility and Launching a project planning at RMO Systems Analysis and Design in a Changing World, 5 th Edition 5
3 Project Success Factors Project management important for success of system development project 2000 Standish Group Study Only 28% of system development projects successful 72% of projects canceled, completed late, completed over budget, and/or limited in functionality Thus, project requires careful planning, control, and execution Systems Analysis and Design in a Changing World, 5 th Edition 6
3 Reasons for Project Failure Incomplete or changing requirements Limited user involvement Lack of executive support Lack of technical support Poor project planning Unclear objectives Lack of required resources Systems Analysis and Design in a Changing World, 5 th Edition 7
3 Reasons for Project Success Clear system requirement definitions Substantial user involvement Support from upper management Thorough and detailed project plans Realistic work schedules and milestones Systems Analysis and Design in a Changing World, 5 th Edition 8
3 Role of the Project Manager Project management – organizing and directing people to achieve a planned result within budget and on schedule Success or failure of project depends on skills of the project manager Beginning of project – plan and organize During project – monitor and control Responsibilities are both internal and external Systems Analysis and Design in a Changing World, 5 th Edition 9
3 Internal Responsibilities Identify project tasks and build a work breakdown structure Develop the project schedule Recruit and train team members Assign team members to tasks Coordinate activities of team members and subteams Systems Analysis and Design in a Changing World, 5 th Edition 10
3 Internal Responsibilities Assess project risks Monitor and control project deliverables and milestones Verify the quality of project deliverables Systems Analysis and Design in a Changing World, 5 th Edition 11
3 External Responsibilities Report the project’s status and progress Establish good working relationships with those who identify the needed system requirements The people who will use the system Work directly with the client (the project’s sponsor) and other stakeholders Identify resource needs and obtain resources Systems Analysis and Design in a Changing World, 5 th Edition 12
Participants in a System Development Project 3 Figure 3 -1 Systems Analysis and Design in a Changing World, 5 th Edition 13
Various Titles/Roles of Project Managers 3 Figure 3 -2 Systems Analysis and Design in a Changing World, 5 th Edition 14
3 Project Management Tasks Beginning of project Overall project planning During project Project execution management Project control management Project closeout Project management approach differs for Predictive SDLC Adaptive SDLC Systems Analysis and Design in a Changing World, 5 th Edition 15
Project Management and SDLC Tasks for a Predictive Project 3 Figure 3 -3 Systems Analysis and Design in a Changing World, 5 th Edition 16
Project Management and SDLC Tasks for an Adaptive Project 3 Figure 3 -4 Systems Analysis and Design in a Changing World, 5 th Edition 17
3 Level of Formality Independent of type of project (predictive or adaptive) Independent of approach to development (structured or object-oriented) Highly formal projects Formal status reports, formal requirements, etc. Less formal projects Agile Software Development Focus Plan on the team, the users for change, be flexible Systems Analysis and Design in a Changing World, 5 th Edition 18
Project Management Body of Knowledge (PMBOK) 3 Scope management control functions included in system control scope of work done by team Time management Build detailed schedule of all project tasks Monitor progress of project against milestones Cost management Calculate initial cost/benefit analysis Monitor expenses Systems Analysis and Design in a Changing World, 5 th Edition 19
Project Management Body of Knowledge (continued) Quality management 3 Establish quality plan and control activities for each project phase Human resource management Recruit and hire project team members Train, motivate, team build Communications management Identify stakeholders and their communications Establish team communications Systems Analysis and Design in a Changing World, 5 th Edition 20
Project Management Body of Knowledge (continued) 3 Risk management Identify and review risks for failure Develop plans to reduce these risks Procurement management Develop requests for proposals (RFPs) Evaluate bids ﻋﺮﻭﺽ ﺃﺴﻌﺎﺭ , write contracts, monitor performance Integration management Systems Analysis and Design in a Changing World, 5 th Edition 21
3 Project Initiation and Project Planning Driving forces to start project Respond to opportunity Resolve problem Conform ﻳﺴﺎﻳﺮ to directive Project initiation comes from Long-term IS strategic plan (top-down) prioritized by weighted scoring Department managers or process managers (bottomup) Response to outside forces (HIPAA) Systems Analysis and Design in a Changing World, 5 th Edition 22
Initiating Customer Support System RMO Strategic IS plan directs IS development’s project priorities Customer support system (CSS) selected John Mac. Murty – creates project charter Barbara Halifax – project manager Steven Deerfield – senior systems analyst Goal is to support multiple types of customer services (ordering, returns, online catalogs) 3 Project charter describes key participants Systems Analysis and Design in a Changing World, 5 th Edition 23
RMO Project Charter 3 Figure 3 -5 Systems Analysis and Design in a Changing World, 5 th Edition 24
3 Project Planning Activities Figure 3 -6 Systems Analysis and Design in a Changing World, 5 th Edition 25
Project Planning Activities and their key questions 3 Figure 3 -7 Systems Analysis and Design in a Changing World, 5 th Edition 26
3 Defining the Problem Review business needs Use strategic plan documents Consult key users Develop list of expected business benefits Identify expected system capabilities Define scope in terms of requirements Create system scope document Build proof of concept prototype Create context diagram Systems Analysis and Design in a Changing World, 5 th Edition 27
3 System Scope Document Figure 3 -8 Systems Analysis and Design in a Changing World, 5 th Edition 28
Context Diagram for Customer Support 3 Figure 3 -9 Systems Analysis and Design in a Changing World, 5 th Edition 29
3 Defining the Problem at RMO Barbara – Completed problem definition statement Steve – Conducted preliminary research on alternative solutions Barbara, Steve, and William Mc. Dougal – Proceeded with analysis before making solution decisions Barbara and Steve – Began schedule, budget, feasibility statement for new system Systems Analysis and Design in a Changing World, 5 th Edition 30
3 Producing the Project Schedule Develop work breakdown structure (WBS) Build a schedule using Gantt chart Develop resource requirements and the staffing plan Systems Analysis and Design in a Changing World, 5 th Edition 31
3 Work Breakdown Structure (Predictive) Figure 3 -10 Systems Analysis and Design in a Changing World, 5 th Edition 32
Work Breakdown Structure (Adaptive) 3 Figure 3 -11 Systems Analysis and Design in a Changing World, 5 th Edition 33
3 Entering WBS into MS Project Figure 3 -12 Systems Analysis and Design in a Changing World, 5 th Edition 34
Using a Split Window for Duration and Predecessor Information 3 Figure 3 -13 Systems Analysis and Design in a Changing World, 5 th Edition 35
3 Task Definitions Critical path is the sequence of connected tasks that cannot be delayed without causing the project to be delayed Slack time is that amount of time a task can be delayed without delaying the project Float – another term used to define slack time Milestone is a definite completion point that is marked by a specific deliverable or event Systems Analysis and Design in a Changing World, 5 th Edition 36
3 Calculating the Critical Path First develop a good network diagram Add the duration estimates for all activities on each path through the network diagram The If longest path is the critical path one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action 37
Figure 6 -8. Determining the Critical Path for Project X 38 3
PERT Formula and Example PERT weighted average = optimistic time + 4 X most likely time + pessimistic time 6 Example: PERT weighted average = 8 workdays + 4 X 10 workdays + 24 workdays = 12 days 6 where optimistic time = 8 days most likely time = 10 days, and pessimistic time = 24 days 39 3
3 Example ACTIVITY 1 -Requirements Collection 2 -Screen Design 3 -Report Design 3 -Database Design 4 -User Documentation 5 -Programming 6 -Testing 7 - Installation TIME ESTIMATE (in weeks) o r p 1 5 3 1 3 4 1 1 5 6 6 2 6 5 3 1 9 7 9 3 7 6 5 1 EXPECTED TIME (ET) o+4 r+p 6 5 6 6 2 5. 5 5 3 1 4
3 ACTIVITY 1 - Requirements Collection 2 - Screen Design 3 - Report Design 4 - Database Design 5 - User Documentation 6 - Programming 7 - Testing 8 - Installation PRECEDING ACTIVITY ـ 1 1 2, 3 4 4 6 5, 7 4
Gantt Chart 3 4
3 Tracking Gantt Chart for Project Plan Figure 13 -14 Systems Analysis and Design in a Changing World, 5 th Edition 43
3 Resource Sheet with Two Resources Figure 3 -15 Systems Analysis and Design in a Changing World, 5 th Edition 44
3 Entering Resources for Tasks Figure 3 -16 Systems Analysis and Design in a Changing World, 5 th Edition 45
Gantt Chart for Entire Project (with overlapping phases) 3 Figure 3 -17 Systems Analysis and Design in a Changing World, 5 th Edition 46
Gantt Chart for Iterative Project 3 Figure 3 -18 Systems Analysis and Design in a Changing World, 5 th Edition 47
Identifying Risks and Confirming Project Feasibility Risk management Organizational and cultural feasibility Technological feasibility Schedule feasibility Resource feasibility Economic feasibility Cost/benefit analysis Sources of funds (cash flow, long-term capital) Systems Analysis and Design in a Changing World, 5 th Edition 3 48
3 Risk Analysis Figure 3 -19 Systems Analysis and Design in a Changing World, 5 th Edition 49
3 Organizational and Cultural Feasibility Each company has own culture New system must fit into culture Evaluate related issues for potential risks Low level of computer competency Computer phobia Perceived loss of control Shift in power Fear of job change or employment loss Reversal of established work procedures Systems Analysis and Design in a Changing World, 5 th Edition 50
3 Technological Feasibility Does system stretch state-of-the-art technology? Does in-house expertise presently exist for development? Does an outside vendor need to be involved? Solutions include Training or hiring more experienced employees Hiring consultants Changing scope and project approach Systems Analysis and Design in a Changing World, 5 th Edition 51
3 Schedule Feasibility Estimates needed without complete information Management deadlines may not be realistic Project managers Drive realistic assumptions and estimates Recommend completion date flexibility Assign interim ﻣﺆﻘﺘﺔ milestones ﻣﻌﺎﻟﻢ to periodically reassess completion dates Involve experienced personnel Manage proper allocation of resources Systems Analysis and Design in a Changing World, 5 th Edition 52
3 Resource Feasibility Team member availability Team skill levels Computers, equipment, and supplies Support staff time and availability Physical facilities Systems Analysis and Design in a Changing World, 5 th Edition 53
3 Economic Feasibility Cost/benefit analysis Estimate project development costs Estimate operational costs after project Estimate financial benefits based on annual savings and increased revenues Calculate using table of costs and benefits Uses net present value (NPV), payback period, return on investment (ROI) techniques Systems Analysis and Design in a Changing World, 5 th Edition 54
Supporting Detail for Salaries and Wages for RMO 3 Figure 3 -20 Systems Analysis and Design in a Changing World, 5 th Edition 55
Summary of Development Costs for RMO 3 Figure 3 -21 Systems Analysis and Design in a Changing World, 5 th Edition 56
Summary of Annual Operating Costs for RMO 3 Figure 3 -22 Systems Analysis and Design in a Changing World, 5 th Edition 57
3 Sample Benefits for RMO Figure 3 -23 Systems Analysis and Design in a Changing World, 5 th Edition 58
3 RMO Cost Benefit Analysis Figure 3 -24 Systems Analysis and Design in a Changing World, 5 th Edition 59
3 Intangibles in Economic Feasibility Intangible benefits cannot be measured in dollars Increased levels of service Customer satisfaction Survival Need to develop in-house expertise Intangible costs cannot be measured in dollars Reduced employee morale ﻣﻌﻨﻮﻳﺎﺕ Lost productivity Lost customers or sales Systems Analysis and Design in a Changing World, 5 th Edition 60
3 Staffing and Launching the Project Develop resource plan for the project Identify and request specific technical staff Identify and request specific user staff Organize the project team into workgroups Conduct preliminary training and team building exercises Key staffing question: “Are the resources available, trained, and ready to start? ” Systems Analysis and Design in a Changing World, 5 th Edition 61
3 Launching Project Scope defined, risks identified, project is feasible, schedule developed, team members identified and ready Oversight committee finalized, meet to give go-ahead, and release funds Formal announcement made to all involved parties within organization Key launch question: “Are we ready to start? ” Systems Analysis and Design in a Changing World, 5 th Edition 62
3 Recap of Project Planning for RMO Created schedule and plans for CSS Addressed all aspects of project management (project planning and scope) Included project communication and quality Identified desired team members Refined internal working procedures Taught tools and techniques used on project Planned kickoff meeting to officially launch Systems Analysis and Design in a Changing World, 5 th Edition 63
3 Summary Project management tasks Start at SDLC project planning phase Continue throughout each SDLC phase Organizing and directing other people Achieve planned result Use predetermined schedule and budget Knowledge areas needed Scope, time, cost, quality, human resources, communications, risk, procurement Systems Analysis and Design in a Changing World, 5 th Edition 64
3 Summary (continued) Project initiation Information system needs are identified and prioritized in strategic plans Project planning phase Define problem (investigation and scope) Produce project schedule (WBS) Confirm project feasibility (evaluate risks) Staff project (know people’s skills) Launch project (executive formal approval) Systems Analysis and Design in a Changing World, 5 th Edition 65
- System analysis
- Systems analysis and design in a changing world
- Systems analysis and design in a changing world
- System analysis and design in a changing world
- Systems analysis and design in a changing world
- Systems analysis and design in a changing world
- Systems analysis and design in a changing world
- Systems analysis and design in a changing world
- Systems analysis and design in a changing world
- The changing world output and world trade picture
- The changing world output and world trade picture
- Sociology understanding and changing the social world
- Debunking motif definition
- Systems analysis and design kendall
- World changing glasgow
- Unchanging values in a changing world meaning
- Innovative management for a changing world
- Chapter 3 economic activity in a changing world answer key
- Chapter 3 economic activity in a changing world
- Communication in a changing world
- The office in a changing business world
- The economy economics for a changing world
- Culture bound syndrome examples
- Abnormal psychology in a changing world
- The changing world of english
- Chapter 3 economic activity in a changing world
- Section 13-1 changing the living world
- International business challenges in a changing world
- Answert the public
- Communication in a changing world
- Chapter 3 economic activity in a changing world
- Systems analysis and design in an age of options pdf
- Alan dennis system analysis design
- Introduction to system analysis and design
- Major tools of ssadm
- Modern systems analysis and design
- Modern systems analysis and design
- Kendall and kendall system analysis and design
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Ssadm diagram
- Radar systems analysis and design using matlab
- Object-oriented systems analysis and design using uml
- A modern approach to systems analysis and design
- Systems analysis and design kendall
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Systems analysis and design alan dennis
- Modern systems analysis and design 7th edition
- Structured system analysis and design methodology
- Essentials of systems analysis and design
- Systems analysis and design alan dennis
- List the five basic steps of ssa/sd process
- Radar system analysis and design using matlab
- Systems analysis and design kendall
- Format output design
- Changing-criterion design
- Changing conditions design
- Changing criterion design
- Job analysis for a changing workplace
- User interface design in system analysis and design