Proto DUNE 2 Installation Steps William Miller University

  • Slides: 24
Download presentation
Proto. DUNE 2 Installation Steps William Miller University of Minnesota 1/8/2020 Proto. DUNE 2

Proto. DUNE 2 Installation Steps William Miller University of Minnesota 1/8/2020 Proto. DUNE 2 Installation 1

Rough Estimated Proto. DUNE 2 Schedule • CPA assembly frame is being picked up

Rough Estimated Proto. DUNE 2 Schedule • CPA assembly frame is being picked up January 13 th. We are still on schedule to have the assembly frame installed by the end of January 1/8/2020 Proto. DUNE 2 Installation 2

Many Open Questions – Decommissioning/Installation What happens to Proto. DUNE? • 7 APA’s and

Many Open Questions – Decommissioning/Installation What happens to Proto. DUNE? • 7 APA’s and only one shipping box are we saving them all? • Photon Detectors and cables? • What needs to be saved and what needs to be purged/recycled? • Can we just leave the roof open in the “cleanroom” if we are just removing everything? • What kind of area can we use for putting the old TPC components • TPC cables? Electronics? 1/8/2020 • Purity Monitor, temperature sensors, cameras? • Setup of new DSS alignment, new APA/CPA positions • Better cleanroom set-up, we did not have appropriate ventilation and cleaning • Do we test the new floor concept we are using at DUNE? • How much consortia/CERN help to we get, or is most of the work done by the Ash River crew? Proto. DUNE 2 Installation 3

MAIN A DSS MAIN B DSS MAIN D DSS MAIN C DSS Runway Beam

MAIN A DSS MAIN B DSS MAIN D DSS MAIN C DSS Runway Beam MAIN E DSS 1: Runway & Bridge Beams • Modifications are made to both runway beams so that Bridge beams A-E can be bolted into their final positions • Modifications are made all Bridge beams so CPA/FC Assemblies and APAs can be bolted into their proper positions TCO BEAM Runway Beam 1/8/2020 Proto. DUNE 2 Installation 4

Runway Beam MAIN B DSS MAIN C DSS MAIN D DSS MAIN A DSS

Runway Beam MAIN B DSS MAIN C DSS MAIN D DSS MAIN A DSS 1 4 MAIN E DSS 2: MAJOR Cleaning • Entire Cryostat is super cleaned • Old Floor sections are removed and adjusted to the new lay-out required for the 4 APA TPC. • Do we use new DUNE design floor for Proto. DUNE 2? Elevation of floor should be adjusted so FC latches and APA hardware can be installed. 2 3 TCO BEAM Runway Beam 1/8/2020 Proto. DUNE 2 Installation 5

3: Under the floor • Entire Cryostat is super cleaned a second time! •

3: Under the floor • Entire Cryostat is super cleaned a second time! • Any changed to cryogenic plumbing is made • All new temperature sensors are installed • All grounding cables installed. MAIN B DSS MAIN C DSS MAIN D DSS MAIN A DSS 1 4 MAIN E DSS 2 3 Runway Beam TCO BEAM All this work should be completed and tested before new floor is installed. We removed the floor in Proto. DUNE WAY to many times. Runway Beam 1/8/2020 Proto. DUNE 2 Installation 6

1 MAIN A DSS MAIN B DSS MAIN C DSS MAIN D DSS MAIN

1 MAIN A DSS MAIN B DSS MAIN C DSS MAIN D DSS MAIN E DSS 4 APA #1 4 a APA #1 & #2 • APA #1 is rolled into position thru the TCO opening • APA #2 is rolled into position thru the TCO opening • Floor sections below APAs are removed to allow clearance for FC latches 2 TCO BEAM APA #2 3 1/8/2020 Proto. DUNE 2 Installation 7

1/8/2020 Inverted APA #1 in position 2 TCO BEAM 3 APA #2 MAIN A

1/8/2020 Inverted APA #1 in position 2 TCO BEAM 3 APA #2 MAIN A DSS MAIN B DSS MAIN C DSS MAIN D DSS APA #1 1 4 MAIN E DSS 4 a APA #1 & #2 • Bridge Beam a is moved into it’s final position and bolted into place as beam trolleys are removed • APA #1 and #2 are mechanically pushed together with alignment pins • APA #1 and #2 are attached to center support and APA trolleys are removed • APA electrical isolation is tested • Cable trays are installed and TPC electronics cables and PD cables are installed thru Cable feed-thru • All electrical connections are tested Proto. DUNE 2 Installation Inverted APA #2 in position 8

TCO BEAM CPA/FC SUPER ASSEMBLY 2 APA #2 MAIN A DSS 2 3 APA

TCO BEAM CPA/FC SUPER ASSEMBLY 2 APA #2 MAIN A DSS 2 3 APA #1 1 MAIN B DSS MAIN C DSS MAIN D DSS MAIN E DSS 4 CPA/FC SUPER ASSEMBLY 1 5 a: CPA/FC Assembly #1 & #2 • CPA/FC Assembly #1 is rolled into position thru the TCO opening 1/8/2020 Proto. DUNE 2 Installation 9

2 APA #1 CPA/FC Assembly #1 APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY

2 APA #1 CPA/FC Assembly #1 APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 MAIN B DSS MAIN C DSS MAIN D DSS 1 TCO BEAM 3 CPA/FC SUPER ASSEMBLY 2 4 MAIN E DSS 5 b : CPA/FC Assembly #1 & #2 • Bridge Beam B is rolled into final position and bolted in place. Beam trolleys are removed • Floor section under CPA/FC Assembly is removed • Bridge Beam C is rolled into final position bolted in place. Beam Trolleys are removed • CPA/FC assemblies are moved to final position, bolted into place and CPA trolleys are removed • Bridge Beam D is rolled into final positon and bolted into place, Trolleys are removed CPA/FC Assembly #1 & #2 1/8/2020 Proto. DUNE 2 Installation 10

2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY

2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 1 MAIN B DSS MAIN C DSS MAIN D DSS Ground Plane DEPLOYED TCO BEAM 3 CPA/FC SUPER ASSEMBLY 2 4 MAIN E DSS 6: Ground Plane 1 and 2 While you still have access with the scissor lift install • All light pulse fibers are routed and connected to CPAs • Install any temperature sensors • Ground plane support tubes are installed • Ground Planes 1 -2 are installed • All electrical connections are made and tested. 1/8/2020 Proto. DUNE 2 Installation 11

2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY

2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 1 MAIN B DSS MAIN C DSS MAIN D DSS Ground Plane DEPLOYED TCO BEAM APA #4 3 CPA/FC SUPER ASSEMBLY 2 APA #3 4 MAIN E DSS 7 a: APA #3 & #4 • APA #3 is rolled into position thru the TCO opening • APA #4 is rolled into position thru the TCO opening • Floor sections below APAs are removed to allow clearance for FC latches 1/8/2020 Proto. DUNE 2 Installation 12

Ground Plane DEPLOYED 2 APA #1 APA #3 in position APA #2 MAIN A

Ground Plane DEPLOYED 2 APA #1 APA #3 in position APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 1 MAIN B DSS MAIN C DSS Ground Plane DEPLOYED TCO BEAM CPA/FC SUPER ASSEMBLY 2 APA #4 3 MAIN D DSS APA #3 4 MAIN E DSS 7 b: APA #3 & #4 • Bridge Beam E is moved into it’s final position and bolted into place as beam trolleys are removed • APA #3 and #4 are mechanically pushed together with alignment pins • APA #3 and #4 are attached to center support and APA trolleys are removed • APA electrical isolation is tested • Cable trays are installed and TPC electronics cables and PD cables are installed thru Cable feed-thru • All electrical connections are tested APA #3 & #4 in position 1/8/2020 Proto. DUNE 2 Installation 13

Ground Plane DEPLOYED 2 APA #1 1 TCO BEAM APA #2 MAIN A DSS

Ground Plane DEPLOYED 2 APA #1 1 TCO BEAM APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS APA #4 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED MAIN D DSS APA #3 4 MAIN E DSS 8: Ground plane 3 & 4 Ground Plane 3 and 4 While you still have access with the scissor lift install • All light pulse fibers are routed and connected to CPAs • Install any temperature sensors • Ground plane support tubes are installed • Ground Planes 1 -2 are installed • All electrical connections are made and tested. 1/8/2020 Proto. DUNE 2 Installation 14

1/8/2020 APA #1 Top EW panel MAIN A DSS MAIN B DSS CPA/FC SUPER

1/8/2020 APA #1 Top EW panel MAIN A DSS MAIN B DSS CPA/FC SUPER ASSEMBLY 1 1 Ground Plane DEPLOYED 2 APA #2 Ground Plane DEPLOYED Top & middle EW panel TCO BEAM APA #4 3 MAIN C DSS Ground Plane DEPLOYED CPA/FC SUPER ASSEMBLY 2 4 MAIN D DSS APA #3 END WALL 1 MAIN E DSS 9 a-End Wall 1 • Bridge beam B and D are bolted in final position, trollies are removed • End wall is erected in 3 sections about ~10 cm from APA/CPA to avoid damage • They are hung on trolleys • End Wall sections are rolled in via carts thru the TCO into position • The top section is attached to the 2 winches mounted on Bridge beam A and Bridge Beam B. It is raised up enough to allow the middle section to be bolted into place • Middle section and then lower section are added Proto. DUNE 2 Installation EW #1 complete 15

1/8/2020 APA #1 Top EW panel MAIN A DSS MAIN B DSS CPA/FC SUPER

1/8/2020 APA #1 Top EW panel MAIN A DSS MAIN B DSS CPA/FC SUPER ASSEMBLY 1 1 Ground Plane DEPLOYED 2 APA #2 Ground Plane DEPLOYED END WALL 2 Top & middle EW panel TCO BEAM APA #4 3 MAIN C DSS Ground Plane DEPLOYED CPA/FC SUPER ASSEMBLY 2 4 MAIN D DSS APA #3 END WALL 1 MAIN E DSS 9 b-End Wall 2 • End wall is erected in 3 sections about ~10 cm from APA/CPA to avoid damage • They are hung on trolleys • End Wall sections are rolled in via carts thru the TCO into position • The top section is attached to the 2 winches mounted on Bridge beam A and Bridge Beam B. It is raised up enough to allow the middle section to be bolted into place • Middle section and then lower section are added Proto. DUNE 2 Installation EW #2 complete 16

END WALL 3 Ground Plane DEPLOYED 2 APA #1 1 Top EW panel APA

END WALL 3 Ground Plane DEPLOYED 2 APA #1 1 Top EW panel APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED MAIN D DSS APA #3 4 APA #4 END WALL 1 MAIN E DSS END WALL 2 Top & middle EW panel EW #3 complete TCO BEAM 9 c-End Wall 3 • End wall is erected in 3 sections about ~10 cm from APA/CPA to avoid damage • They are hung on trolleys • End Wall sections are rolled in via carts thru the TCO into position • The top section is attached to the 2 winches mounted on Bridge beam A and Bridge Beam B. It is raised up enough to allow the middle section to be bolted into place • Middle section and then lower section are added 1/8/2020 Proto. DUNE 2 Installation 17

END WALL 3 1 Ground Plane DEPLOYED 2 Top EW panel APA #2 MAIN

END WALL 3 1 Ground Plane DEPLOYED 2 Top EW panel APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS APA #4 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED MAIN D DSS APA #3 4 APA #1 END WALL 4 MAIN E DSS END WALL 2 Top & middle EW panel EW #4 complete TCO BEAM 9 d-End Wall 4 • End wall is erected in 3 sections about ~10 cm from APA/CPA to avoid damage • They are hung on trolleys • End Wall sections are rolled in via carts thru the TCO into position • The top section is attached to the 2 winches mounted on Bridge beam A and Bridge Beam B. It is raised up enough to allow the middle section to be bolted into place • Middle section and then lower section are added 1/8/2020 Proto. DUNE 2 Installation 18

1/8/2020 Access Scaffolding END WALL 4 2 APA #1 Ground Plane DEPLOYED APA #2

1/8/2020 Access Scaffolding END WALL 4 2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 1 END WALL 2 TCO BEAM END WALL 3 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED MAIN D DSS APA #3 4 APA #4 END WALL 1 MAIN E DSS 10 a-Field Cage 1 -End Wall • Remove 1 floor sections • Install bottom ground plane supports and ground plane panels, make and test all electrical connections • Access is via access scaffolding and must be moved as needed • Using winch on the ground plan to deploy bottom FC • Deploy Top FC • Roll End wall into final position, mechanical connections made and trolleys removed • Make and test all HV electrical connections Proto. DUNE 2 Installation 19

Access Scaffolding END WALL 4 2 APA #1 Ground Plane DEPLOYED APA #2 MAIN

Access Scaffolding END WALL 4 2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 1 END WALL 2 TCO BEAM END WALL 3 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED MAIN D DSS APA #3 4 APA #4 END WALL 1 MAIN E DSS 10 b-Field Cage 2 • Remove 2 floor sections • Install bottom ground plane supports and ground plane panels, make and test all electrical connections • Access is via scissor lift • Using winch on the ground plan to deploy bottom FC • Deploy Top FC • Roll End wall into final position, mechanical connections made and trolleys removed • Make and test all HV electrical connections 1/8/2020 Proto. DUNE 2 Installation 20

Access Scaffolding END WALL 4 2 APA #1 Ground Plane DEPLOYED APA #2 MAIN

Access Scaffolding END WALL 4 2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 1 END WALL 2 TCO BEAM END WALL 3 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED MAIN D DSS APA #3 4 APA #4 END WALL 1 MAIN E DSS 10 c-Field Cage 3 • Remove 3 floor sections • Install bottom ground plane supports and ground plane panels, make and test all electrical connections • Access is via scissor lift • Using winch on the ground plan to deploy bottom FC • Deploy Top FC • Roll End wall into final position, mechanical connections made and trolleys removed • Make and test all HV electrical connections 1/8/2020 Proto. DUNE 2 Installation 21

1/8/2020 Access Scaffolding 2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS

1/8/2020 Access Scaffolding 2 APA #1 Ground Plane DEPLOYED APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 1 END WALL 2 TCO BEAM END WALL 3 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED END WALL 1 MAIN D DSS APA #3 4 APA #4 END WALL 4 MAIN E DSS 10 d-Field Cage 4 • Remove 4 floor sections • Install bottom ground plane supports and ground plane panels, make and test all electrical connections • Access is via access scaffolding and must be moved as needed • Using winch on the ground plan to deploy bottom FC • Deploy Top FC • Roll End wall into final position, mechanical connections made and trolleys removed • Make and test all HV electrical connections Proto. DUNE 2 Installation 22

11 -Install Beam Plug • Install beam plug support system on bridge beam B

11 -Install Beam Plug • Install beam plug support system on bridge beam B and C • Install and test Beam Plug • Remove floor sections upstream beam right Access Scaffolding TCO BEAM 1/8/2020 Ground Plane DEPLOYED 2 APA #1 1 APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 MAIN E DSS END WALL 3 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED END WALL 1 MAIN D DSS APA #3 4 APA #4 END WALL 2 Beam Plug Proto. DUNE 2 Installation 23

Access Scaffolding TCO BEAM END WALL 3 1/8/2020 Ground Plane DEPLOYED 2 APA #1

Access Scaffolding TCO BEAM END WALL 3 1/8/2020 Ground Plane DEPLOYED 2 APA #1 1 APA #2 MAIN A DSS CPA/FC SUPER ASSEMBLY 1 Ground Plane DEPLOYED MAIN B DSS Ground Plane DEPLOYED MAIN C DSS 3 CPA/FC SUPER ASSEMBLY 2 Ground Plane DEPLOYED END WALL 1 MAIN D DSS APA #3 4 APA #4 END WALL 4 MAIN E DSS 12 -TPC is completed • Ready to deploy plastic shield to protect detector during TCO closing • Access is via narrow walkway past cryogenic plumbing, may want to put some protection on APAs ? • TCO can now be welded shut • Only Access is via scaffolding END WALL 2 Beam Plug Proto. DUNE 2 Installation Completed TCP 24