ENERGY STAR Multifamily High Rise Program Testing and

  • Slides: 57
Download presentation
ENERGY STAR Multifamily High Rise Program Testing and Verification Protocols Webinar – Part I

ENERGY STAR Multifamily High Rise Program Testing and Verification Protocols Webinar – Part I July 2011

EPA Objectives for T&V Protocols • Verify that the As-Built Building has successfully achieved

EPA Objectives for T&V Protocols • Verify that the As-Built Building has successfully achieved the performance levels predicted by the Proposed Design energy model, or as specified in the Prescriptive Path, and is in compliance with the Prerequisites Checklist • Work in conjunction with the ENERGY STAR MFHR Simulation Guidelines, Performance Path, Prescriptive Path, Testing & Verification Worksheets and Photo Template 2

EPA Objectives for MFHR Program • Failure to comply with Prerequisites or Prescriptive Checklist:

EPA Objectives for MFHR Program • Failure to comply with Prerequisites or Prescriptive Checklist: – Corrective action must be taken to bring the building into compliance with the Prerequisites or Prescriptive Checklist. 3

EPA Objectives for MFHR Program • Performance less than predicted in the Proposed Design

EPA Objectives for MFHR Program • Performance less than predicted in the Proposed Design model: – Take corrective action to bring the building component to match the assumptions in the Proposed Design, or – Allow the component to remain as is, but the As-Built energy model must be adjusted to accurately represent this condition and must still demonstrate at least a 15% improvement above the Baseline Building, or – Forfeit ENERGY STAR. • Performance less than level required in Prescriptive Path: – Take corrective action to remedy the problem and bring the building component to the efficiency levels required in the Prescriptive Path, or – Allow the component to remain in its current condition, but an As-Built energy model must be created to accurately represent at least a 15% improvement above the Baseline Building Design, or – Forfeit ENERGY STAR. 4

Plan Review/Inspection Work Flow Design Early in the design, the design team incorporates Prerequisites

Plan Review/Inspection Work Flow Design Early in the design, the design team incorporates Prerequisites and requirements of the Performance or Prescriptive Path into the design. When the construction documents are 75% complete, a full plan review using the T&V Worksheets should be conducted and, if needed, corrective actions taken to ensure the program requirements are represented in the documents. Often a design team meeting with the Architect and Engineer present is needed to clarify program requirements and ensure CDs are revised correctly before they go out to bid. A second plan review at 100% CDs ensures that the program requirements are represented in the final plans. T&V Worksheets are signed and submitted to the EPA for approval, which document the final plan review and includes the Prerequisites Checklist. If needed, the project team must be notified of corrective actions to be taken to ensure the program requirements are being met. Applicable corrections must be reinspected to verify and document compliance. Post construction and inspection, the T&V worksheets are updated to reflect the As-Built building and the Photo Template is completed. The As-Built model for the Performance Path must reflect any changes found during T&V. Construction At or prior to the first inspection, the licensed professional in charge of submissions should schedule a kick off meeting with the GC, Architect and other key members of the project team to identify inspections and clarify expectations. The party responsible for following the MFHR Testing and Verification Protocols, must stay in contact with the GC/Architect to review applicable submittals and visit the site as necessary to conduct the required inspections. Post Construction The designated licensed professional re-submits the Testing and Verification Worksheets to the EPA for approval. This includes the Prerequisite Checklist or Prescriptive Checklist and results of T&V. Photo template is also submitted. Building may be labeled as ENERGY STAR

The Protocols

The Protocols

Testing and Verification Protocols • 1. 1) ENERGY STAR Qualified Appliances • 2. 1)

Testing and Verification Protocols • 1. 1) ENERGY STAR Qualified Appliances • 2. 1) Domestic Water Heating Central Systems (Serving 5 units or more) • 2. 2) Domestic Water Heating Distributed (Individual Apartment) Systems • 3. 1) Wall Construction/Insulation, R-value • 3. 2) Roof Construction/Insulation, R-value • 3. 3) Floor Construction/Insulation, R-value • 3. 4) Window Selection, U-value, and SHGC • 3. 5) Exterior Door Selection, Entranceway Design, Use of Vestibules, Weather stripping, and Air Leakage 7

Testing and Verification Protocols • • • 4. 1) Garage: Heating and Compartmentalization 5.

Testing and Verification Protocols • • • 4. 1) Garage: Heating and Compartmentalization 5. 1) Central Heating Systems (Serving 5 units or more) 5. 2) Central Cooling Systems (Serving 5 units or more) 5. 3) Distributed (Individual Apartment) Heating Systems 5. 4) Distributed (Individual Apartment) Cooling Systems 8

Testing and Verification Protocols • • • 6. 1) Common Areas, In-Unit, Garage and

Testing and Verification Protocols • • • 6. 1) Common Areas, In-Unit, Garage and Exterior Lighting 6. 2) Emergency Lighting (Exit Signs) 6. 3) Controls 7. 1) Motors 8. 1) Envelope Air Sealing and Total Air Leakage - Common Area, Apartments, and Exterior • 8. 2) Common Area and In-Unit Ventilation (CFM), Intake Source, and Intake/Exhaust Fan Efficiency • 9. 1) Metering Configuration 9

Types of Testing Protocols • Visual Inspection – Photos of faceplates, fixture type, insulation

Types of Testing Protocols • Visual Inspection – Photos of faceplates, fixture type, insulation type, NFRC label, etc. must be clear enough to read what is being verified. – Use a ruler to show insulation depth – Caption/Label each photo giving location. – Must use the Photo Template • • Data Sheet Test Procedure Instrumented Measurement Third-Party Commissioning 10

Performance Specification Criteria • Actions to be taken to ensure that appropriate language is

Performance Specification Criteria • Actions to be taken to ensure that appropriate language is included in bid and contract documents so that the building meets program requirements and contractors are aware of expectations. 11

Performance Specification Criteria: Contract Language • For example: “Allow inspection of all energy related

Performance Specification Criteria: Contract Language • For example: “Allow inspection of all energy related components. Provide submittals for review and report installation dates immediately. Ensure the ENERGY STAR label remains attached to products and appliances when applicable. ” 12

Procedure and Documentation • Steps to be followed to ensure that each building element

Procedure and Documentation • Steps to be followed to ensure that each building element is inspected at the appropriate time, that the necessary data is documented in the T&V Worksheets and, if applicable, used in the As-Built energy model or to prove that requirements of the Prescriptive Path have been met. 13

Schedule • Identifies the point in construction when a particular inspection or test should

Schedule • Identifies the point in construction when a particular inspection or test should take place. 14

Responsible Parties • Identifies the parties responsible for a specific inspection or test and

Responsible Parties • Identifies the parties responsible for a specific inspection or test and which other parties need to be available or coordinated with to effectively carry out the inspection. 15

Sampling Requirements • For building components that are duplicated many times throughout the building

Sampling Requirements • For building components that are duplicated many times throughout the building (e. g. , windows, light fixtures) or cover large areas or sections of the building (e. g. , wall insulation), the specific protocol identifies the minimum required area or sample to be inspected. 16

Sampling Requirements: RESNET • Refer to RESNET’s 2006 Mortgage Industry National Home Energy Rating

Sampling Requirements: RESNET • Refer to RESNET’s 2006 Mortgage Industry National Home Energy Rating Systems Standards, Chapter 6 for the full description of RESNET’s sampling protocols; however, the intent is captured in the following sections: • 603. 7. 1 - A complete set of Sampling Controls shall be performed at a minimum ratio of one (1) test or inspection out of seven (7) spaces/apartments within a given sample set… • 603. 7. 2…the sampling controls may be completed collectively on a single space/apartment or distribute the tests and inspections across several spaces/apartments within a given sample set, provided the total number of individual tests and inspections meets or exceeds the minimum ratio set forth in 603. 7. 1. 17

Sampling Requirements: RESNET • 603. 7. 3 - To qualify for sampling in a

Sampling Requirements: RESNET • 603. 7. 3 - To qualify for sampling in a metropolitan area, a builder shall first complete, without any incidence of failure, a complete set of sampling controls on at least seven (7) consecutive apartments in that metropolitan area. For this initial phase of testing and inspections, the complete set of sampling controls shall be performed on each of the seven (7) apartments. • 603. 7. 6 - When an “initial failure” occurs, the failed item(s) shall be tested or inspected in two (2) additional spaces/apartments selected from the sample set. Testing and/or inspections for any item(s) that may become inaccessible during the construction process, (e. g. , wall insulation) must be timed so additional testing and/or inspections can occur on other spaces/apartments in the sample set before they become inaccessible for inspection or testing. 18

Sampling Requirements: RESNET • 603. 7. 7 - When an “additional failure” occurs, in

Sampling Requirements: RESNET • 603. 7. 7 - When an “additional failure” occurs, in one or more of the two (2) additional spaces/apartments, the failed item(s) shall be tested or inspected in the remaining four (4) spaces/apartments selected for the sample set. • 603. 7. 8 - Until the failure is corrected in all identified (failed) spaces/apartments in the sample set, none of the spaces/apartments shall be deemed to meet the threshold or labeling criteria. • 603. 8 - Action is required if three (3) “additional failures” occur within a ninety (90) calendar day period. The required action depends on whether those “additional failures” apply to the same failed item or various failed items. 19

Statements of Substantial Completion

Statements of Substantial Completion

Statement of Substantial Completion • A Statement of Substantial Completion or approved proxy may

Statement of Substantial Completion • A Statement of Substantial Completion or approved proxy may be submitted to establish completion of the work and document compliance for applicable protocols. – Can hold contractors accountable for quality of installations – May reduce the burden on the responsible party for verification. – Licensed professional is still responsible for performing the necessary due diligence to ensure that the Statement of Substantial Completion is accurate and complete. 21

Statement of Substantial Completion • All relevant ENERGY STAR MFHR Testing and Verification Worksheets

Statement of Substantial Completion • All relevant ENERGY STAR MFHR Testing and Verification Worksheets (T&V Worksheets) must be attached and completed with all required information, photographs, cut sheets, etc. – To be completed by the installation contractor or other qualified representative on company letterhead – List name and address of the site – List name and contact information of individual completing the statement – Written confirmation that fixtures and equipment have been installed and tested. – Individual’s signature and date signed. 22

Statement of Substantial Completion • A statement of substantial completion can be submitted for

Statement of Substantial Completion • A statement of substantial completion can be submitted for the following protocols: – 1. 1) ENERGY STAR Qualified Appliances – 3. 4) Window Selection, U-value, SHGC, and Visual Transmittance – 3. 5) Exterior Door Selection, Entrance-way Design, Use of Vestibules, Weather stripping, and Air Leakage – 6. 1) Common Areas, In-Unit, Garage and Exterior Lighting – 6. 2) Emergency Lighting (Exit Signs) – 6. 3) Lighting Controls – 7. 1) Motors – 9. 1) Metering Configuration 23

Statement of Substantial Completion • For the following HVAC protocols a Statement of Substantial

Statement of Substantial Completion • For the following HVAC protocols a Statement of Substantial Completion (SSC) must be completed by a third-party qualified representative: – – – – 2. 1) Central Systems (Serving 5 units or more) 2. 2) Distributed (Individual Apartment) Systems 5. 1) Central Heating Systems (Serving 5 units or more) 5. 2) Central Cooling Systems (Serving 5 units or more) 5. 3) Distributed (Individual Apartment) Heating Systems 5. 4) Distributed (Individual Apartment) Cooling Systems 8. 2) Common Area and In-Unit Ventilation (CFM), Intake Source, and Intake/Exhaust Fan Efficiency 24

Appendix A: Referenced Standards and Data Sources

Appendix A: Referenced Standards and Data Sources

Air Conditioning Contractors Association (ACCA) Manuals J, S, and D • These manuals provide

Air Conditioning Contractors Association (ACCA) Manuals J, S, and D • These manuals provide standardized procedures for completing sizing calculations for heating and cooling systems (Manuals J and S) and duct system sizing and design (Manual D) Available at https: //www. acca. org/store/category. php? cid=1 26

Air-Conditioning, Heating, and Refrigeration Institute (AHRI) • Use this online directory of AHRI ratings

Air-Conditioning, Heating, and Refrigeration Institute (AHRI) • Use this online directory of AHRI ratings to determine efficiencies of heating and cooling systems Available at - www. ahridirectory. org 27

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 62. 1

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 62. 1 -2007: Ventilation for Acceptable Indoor Air Quality • Provides guidance for ventilation system design and other related building features to ensure acceptable indoor air quality. Scope includes all buildings except low-rise residential. • In the MFHR program, this standard applies to common areas. Available at http: //www. techstreet. com/standards/ASHRAE/Stan dard_62_1_2007? product_id=1409997 28

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 62. 2

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 62. 2 -2007: Ventilation and Acceptable Indoor Air Quality in Low-Rise Residential Buildings • Provides guidance for ventilation system design and other related building features to ensure acceptable indoor air quality. • In the MFHR program, this standard is applied to dwelling units. Available at http: //www. techstreet. com/standards/ASHRAE/St andard_62_1_2007? product_id=1409997 29

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 90. 1

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 90. 1 -2007 and 90. 1 -2010: Energy Standard for Buildings Except Low-Rise Residential Buildings • Primary source document for Baseline Building design features and guidance for creating a performance-based evaluation of a proposed building’s energy features. Available at http: //www. techstreet. com/standards/ASHRAE/90_1 _2007_SI_? product_id=1608726 30

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 189. 1

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • ASHRAE Standard 189. 1 -2009: Standard for the Design of High. Performance Green Buildings Except Low-Rise Residential Buildings • Primary source document for Building Envelope Requirements and Minimum Equipment Efficiencies for the Prescriptive Path. Available at http: //www. techstreet. com/standards/ASHRAE/189_ 1_2009? product_id=1668986&ashrae_auth_token= 31

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • (ASHRAE) Standard 160 P:

American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) • (ASHRAE) Standard 160 P: Criteria for Moisture Control Design Analysis in Buildings • The standard sets criteria for moisture design loads, moisture analysis methods, and building performance and applies to the above-grade portions of all types of buildings. Available at – http: //www. techstreet. com/cgibin/detail? product_id=1714308 32

ASTM E 779 – 10 • Standard Test Method for Determining Air Leakage Rate

ASTM E 779 – 10 • Standard Test Method for Determining Air Leakage Rate by Fan Pressurization • This test method measures airleakage rates through a building envelope under controlled pressurization and depressurization. • In the MFHR program, this is one standard used to determine whether measured infiltration of a random sample of apartments does not exceed 0. 30 CFM 50/SF of enclosure. Available at – http: //www. techstreet. com/standards/astm/e 779_10? product_id=1741852 33

ASTM E 1827 – 96 (2007) • Standard Test Methods for Determining Air tightness

ASTM E 1827 – 96 (2007) • Standard Test Methods for Determining Air tightness of Buildings Using an Orifice Blower Door • These test methods describe two techniques for measuring air leakage rates through a building envelope in buildings that may be configured to a single zone. • In the MFHR program, this is one standard used to determine whether measured infiltration of a random sample of apartments does not exceed 0. 30 CFM 50/SF of Available at – enclosure. http: //www. techstreet. com/standards/astm/e 1827_96 _2007_? product_id=1517619 34

ENERGY STAR Homes v 3. 0 Checklists • • Version 3. 0 of the

ENERGY STAR Homes v 3. 0 Checklists • • Version 3. 0 of the ENERGY STAR Qualified Homes HVAC System Quality Installation Rater and Contractor Checklists is referenced for in-unit forced air system commissioning. Version 3. 0 of the ENERGY STAR Qualified Homes Thermal Enclosure System Rater Checklist is referenced to verify envelope installations for buildings with wood framed construction. Available at – www. energystar. gov 35

Illuminating Engineering Society of North America Lighting Handbook • Handbook of lighting design published

Illuminating Engineering Society of North America Lighting Handbook • Handbook of lighting design published by the Illuminating Engineering Society of North America • In the MFHR program, this is referenced for minimum footcandle requirements by space type Available at https: //www. ies. org/handbook_order_fo rm. cfm 36

National Fire Protection Association (NFPA) • These standards provide guidance for the proper installation

National Fire Protection Association (NFPA) • These standards provide guidance for the proper installation of natural gas (Standard 54) and oil-fired (Standard 31) heating systems. Available at http: //www. nfpa. org/catalog/category. asp? categor y%5 Fname=Codes+and+Standards&Page=1 37

Residential Energy Services Network (RESNET) HERS Standards • Chapter 6 of this standard includes

Residential Energy Services Network (RESNET) HERS Standards • Chapter 6 of this standard includes the sampling procedure described in the “How to Use this Manual” section of the Testing and Verification Protocols. Available at – www. resnet. us 38

Appendix B: Recommended Equipment List

Appendix B: Recommended Equipment List

Manometer and Static Pressure Probe • The manometer measures the pressure difference between points

Manometer and Static Pressure Probe • The manometer measures the pressure difference between points and is used together with a variety of equipment, such as the blower door and duct blaster. • The static pressure probe measures static pressure only instead of total pressure. Image courtesy of The Energy Conservatory 40

Pressure Pan and Flow Meter • The pressure pan is used with a manometer

Pressure Pan and Flow Meter • The pressure pan is used with a manometer to measure static pressure at an exhaust grille. • The flow meter is used with a manometer to measure air flow at an exhaust grille. Images courtesy of The Energy Conservatory 41

Balometer and Smoke Pencil • Balometers are also used to measure air flow from

Balometer and Smoke Pencil • Balometers are also used to measure air flow from exhaust grilles, or supply/return registers. • The smoke pencil is used to help identify leaks during blower door testing. Images courtesy of Alnor and American Science and Surplus 42

Duct Blaster • The duct blaster is used in this program to measure leakage

Duct Blaster • The duct blaster is used in this program to measure leakage in heating and cooling ductwork, as well as central ventilation ductwork. • It includes several different orifice plates and is used with a manometer. • 6 or 8 CFM 25/100 ft 2 Images courtesy of The Energy Conservatory 43

Blower Door • The blower door is used to measure air leakage in buildings.

Blower Door • The blower door is used to measure air leakage in buildings. • It consists of a frame, shroud and calibrated fan. It is used with a manometer. • 0. 30 CFM 50/ft 2 Image courtesy of The Energy Conservatory 44

Flow Plates • Flow plates are designed to quickly measure air flow through an

Flow Plates • Flow plates are designed to quickly measure air flow through an air handling unit. • They fit in the place of a filter and the flow is calculated using a manometer. Image courtesy of The Energy Conservatory 45

Camera and Infrared Camera • Cameras are valuable tools for recording field conditions •

Camera and Infrared Camera • Cameras are valuable tools for recording field conditions • Infrared cameras are able to see the temperature of objects and identify air leaks and thermal bridging Images courtesy of FLIR and Canon 46

Electronic Ballast Detector and Light Meter • An electronic ballast checker tests whether fluorescent

Electronic Ballast Detector and Light Meter • An electronic ballast checker tests whether fluorescent ballast are electronic or magnetic • A light meter measures the light level to ensure enough light is being provided Images courtesy of Philips and TES 47

Thermometers • Some digital thermometers can be used with thermocouples for quick and accurate

Thermometers • Some digital thermometers can be used with thermocouples for quick and accurate temperature readings • A simple digital thermometer can easily measure domestic hot water temperature Images courtesy of Fluke and Trutemp 48

Low-E Detector • A Low-E detector is used to check for the presence and

Low-E Detector • A Low-E detector is used to check for the presence and location of a Low-E coating in insulated glazing Image courtesy of Professional Equipment 49

Appendix C: Specifications for Flexible Duct Installation 50

Appendix C: Specifications for Flexible Duct Installation 50

Photo Template • This Word-based template was designed so that pictures used to provide

Photo Template • This Word-based template was designed so that pictures used to provide photo-documentation required by the T&V Protocols could be easily formatted and consistently reported. • Photo documentation must be submitted to the EPA or its designated agent at the end of construction • The Photo Template need only be submitted for the Developer’s first three buildings that participate in the Program. Also, if the licensed professional validating documents has successfully submitted at least three Photo Templates, the requirement is waived. 51

Testing and Verification Worksheets • Mandatory Excel-based worksheets that document the results of plan

Testing and Verification Worksheets • Mandatory Excel-based worksheets that document the results of plan reviews, inspections, verification, and performance testing. – Provide inspection worksheets that can be used in the field that follow the Testing and Verification Protocols, but are organized for the convenience of the site inspector. – Provide a central file to store building information relevant to all members of the design team: architect, energy modeler, site inspector, project manager, plan reviewer, etc. – Must be submitted once prior to construction to document results of the plan review and once after construction is complete, to document the results of testing and verification. • Webinar available online to demonstrate this tool. 52

Tips for Success

Tips for Success

Tips for Success #1 - 3 1. Understand all requirements and T&V protocols before

Tips for Success #1 - 3 1. Understand all requirements and T&V protocols before design is complete! 2. Ensure all energy-related details are included in the bid documents. 3. Use pre-bid meetings to help answer questions and clarify expectations. 54

Tips for Success #4 - 6 4. Identify responsibilities. 5. Attend pre-construction meetings and

Tips for Success #4 - 6 4. Identify responsibilities. 5. Attend pre-construction meetings and call out commonly overlooked details. 6. Stay informed of construction schedule! 55

Tips for Success #7 - 10 7. Don’t select sample set ahead of time!

Tips for Success #7 - 10 7. Don’t select sample set ahead of time! 8. …except when unique details need to be inspected before installed building wide. 9. Mock-ups are your friends. 10. The T&V Worksheets and Photo Template are also your friends! 56

The End Questions? Contact: MFHR@energystar. gov 57

The End Questions? Contact: MFHR@energystar. gov 57