EKONOMI REKAYASA PERTEMUAN 1 PENDAHULUAN NPV Oleh Arwan

  • Slides: 37
Download presentation
EKONOMI REKAYASA PERTEMUAN 1 PENDAHULUAN & NPV Oleh : Arwan Apriyono P. Setyo Nugroho

EKONOMI REKAYASA PERTEMUAN 1 PENDAHULUAN & NPV Oleh : Arwan Apriyono P. Setyo Nugroho PROGRAM STUDI TEKNIK SIPIL JURUSAN TEKNIK FAKULTAS SAINS DAN TEKNIK UNSOED TAHUN 2011

Lay Out Presentasi 1. Pengertian ekonomi teknik 2. Formula/Rumus 3. Tingkat bunga 4. NPW

Lay Out Presentasi 1. Pengertian ekonomi teknik 2. Formula/Rumus 3. Tingkat bunga 4. NPW

INTRODUCTION ?

INTRODUCTION ?

INTRODUCTION ?

INTRODUCTION ?

INTRODUCTION Menyewa/ Membeli?

INTRODUCTION Menyewa/ Membeli?

INTRODUCTION Finansial Decision Making Infuence Factor -Inflasi & Deflasi -Pajak -Depreciation Metode Pengambilan Keputusan

INTRODUCTION Finansial Decision Making Infuence Factor -Inflasi & Deflasi -Pajak -Depreciation Metode Pengambilan Keputusan -NPV/NPW -ROR/IRR -B/C Pengetahuan Dasar -Nilai uang (PV, FV, AV) -Suku bunga (Rerata , Majemuk) -Cost and Benefit -Cast flow diagram

RENCANA KULIAH Materi : 1. 2. 3. 4. 5. 6. 7. Pendahuluan dan NPW

RENCANA KULIAH Materi : 1. 2. 3. 4. 5. 6. 7. Pendahuluan dan NPW Analisis investasi ROR/IRR Analisis investasi B/C Inflasi & Deflasi Pajak Depreciation/Penurunan nilai Replacement Analysis Referensi : 1. Donald G Newnan et al, 2004, Engineering Economic Analysis, Oxford University Press, Newyork 2. Abol Ardalan, 2000, Economic & Financial Anaysis for Engineering & Project Management, Technomic Publishing Company Book, Pennsylvania 3. Perry Beaumon, 2004, Financial Engineering Principle, Wiley, New Jersey 4. Chan S Park, Fundamental of Engineering Economics, Pearson Education Inc, New Jersey 5. Peter Cassimatis, 1992, Introduction to Engineering Economic, Taylor & Francir Routledge, London MESTI BANYAK EXERCISE.

MARR = Minimum Attractive Rate of Return

MARR = Minimum Attractive Rate of Return

MANFAAT -----

MANFAAT -----

EUAW : Equivalent Uniform Annual Worth

EUAW : Equivalent Uniform Annual Worth

P/F : mencari nilai P dari nilai F; jadi nilai F sudah diketahui A/F

P/F : mencari nilai P dari nilai F; jadi nilai F sudah diketahui A/F : mencari nilai A dari nilai F; jadi nilai F sudah diketahui

Langkah perhitungan 1. Tuliskan yang diketahui 2. Gambarkan dalam bentuk diagram 3. Hitung yang

Langkah perhitungan 1. Tuliskan yang diketahui 2. Gambarkan dalam bentuk diagram 3. Hitung yang ditanyakan

Latihan (15’) 1. Berapa uang harus diinvestasikan untuk mendapatkan 750. 000 selama waktu 3

Latihan (15’) 1. Berapa uang harus diinvestasikan untuk mendapatkan 750. 000 selama waktu 3 tahun dengan bunga majemuk 10% per tahun ? 2. Berapa yang harus disimpan di bank untuk mendapatkan 15. 500. 000 selama 2 tahun pada bunga majemuk 1, 5 % per bulan ?

No. 1 F = 750. 00000 n = 3 tahun I = 10 %

No. 1 F = 750. 00000 n = 3 tahun I = 10 % P = F(F/P, i, n) = 750. 000(F/P, 0. 1, 3) = 563. 486 No. 2 F = 15. 500. 000 n = 2 tahun = 24 bulan i = 1. 5 % P = F(F/P, i, n) = 15. 500. 000(F/P, 0. 015 , 24) = 10. 842. 930, 75

Contoh : Suatu lembaga pembiayaan dalam iklannya menyatakan bahwa bunga pinjaman bunga nominal 12%

Contoh : Suatu lembaga pembiayaan dalam iklannya menyatakan bahwa bunga pinjaman bunga nominal 12% setahun (sebesar 1% sebulan, dihitung per bulan karena pembayaran biasanya tiap bulan) Berapa sebetulnya bunga efektif dalam setahun? I efektif = (1+0, 12/12)12 - 1 = Dalam perhitungan ekonomi teknik, jika tanpa penjelasan maka bunga yang dimaksud adalah bunga nominal, bukan bunga efektif. Jika dinyatakan bahwa bunga setahun 36%, maka 36% adalah bunga nominal dalam setahun, sehingga bunga dalam sebulan adalah 3% Bunga efektif selalu lebih besar daripada bunga nominal

INTRODUCTION Prinsip dasar Metode Pengambilan Keputusan Menghitung total biaya dan manfaat yang dihasilkan dari

INTRODUCTION Prinsip dasar Metode Pengambilan Keputusan Menghitung total biaya dan manfaat yang dihasilkan dari suatu kasus/proyek.

NPV/NPW NET PRESENT VALUE / NET PRESENT WORTH Ø The net difference of the

NPV/NPW NET PRESENT VALUE / NET PRESENT WORTH Ø The net difference of the present benefits and costs Ø NPV = PV of Benefit – PV of cost Ø Alternatif yang paling baik adalah yang memiliki NPV terbesar

NPV/NPW Example A car leasing company buys a car from a wholesaler for $24,

NPV/NPW Example A car leasing company buys a car from a wholesaler for $24, 000 and leases it to a customer four years at $5, 000 per year. Since the maintenance is not included in the lease, the leasing company has to spend $400 per year in servicing the car. At the end of the four years, the leasing company takes back the car and sells it to a secondhand car dealer for $15, 000. Calculate the NPV for the case if we will not consider tax, inflation, and depreciation (interest of rate 10%)?

NPV/NPW ANALYSIS Step 1 : Making cost flow diagram

NPV/NPW ANALYSIS Step 1 : Making cost flow diagram

NPV/NPW ANALYSIS Step 2 : Calculate PV of Cost and Benefit PV of cost

NPV/NPW ANALYSIS Step 2 : Calculate PV of Cost and Benefit PV of cost = $24000 PV of Benf = A(P/A, i, n) + F(P/F, i, n) = 4600 * ((1+0. 1)3 – 1)/(0. 1(1+0. 1)3) + 19600*(1+0. 1)-4 = 11439, 52 + 13387, 1 = $24826, 62

NPV/NPW ANALYSIS Step 3 : Calculate NPV Total Cost = 24, 000 Total Benefit

NPV/NPW ANALYSIS Step 3 : Calculate NPV Total Cost = 24, 000 Total Benefit = 11439. 52 + 13387. 1 = 24826. 62 Net Worth of the Project = 826. 62

NPV/NPW ANALYSIS Step 3 : Calculate NPV Total Cost = 24, 000 Total Benefit

NPV/NPW ANALYSIS Step 3 : Calculate NPV Total Cost = 24, 000 Total Benefit = 11439. 52 + 13387. 1 = 24826. 62 Net Worth of the Project = 826. 62

NPV/NPW CONTOH SOAL Suppose the leasing company of Example 2. 1 has to choose

NPV/NPW CONTOH SOAL Suppose the leasing company of Example 2. 1 has to choose between the following two projects: 1. Lease the car exactly as the case in Example 2. 1 which had a net present worth of $826. 62 2. Buy a car at $40, 000, lease it for two years at $12, 000 per year with no maintenance cost, and sell it for $24, 000 at the end of two years.

NPV/NPW ANALYSIS Step 1 : Making cost flow diagram 36000 16000

NPV/NPW ANALYSIS Step 1 : Making cost flow diagram 36000 16000

NPV/NPW ANALYSIS = -40000 + 12000 (P/A, 10, 3) - 16000 (P/F, 10, 2)

NPV/NPW ANALYSIS = -40000 + 12000 (P/A, 10, 3) - 16000 (P/F, 10, 2) + 36000 (P/F, 10, 4) = -40000 + 12000 (2. 487) -16000 (0. 8264) + 36000 (0. 6830) = 1, 209. 6 Since project 2 has a higher NPW, it would be the project to choose NPW makin besar, makin baik untuk investasi.

Task 1. (due date 24 Oct 2011) diketik diprint pada kertas A 4, diberi

Task 1. (due date 24 Oct 2011) diketik diprint pada kertas A 4, diberi cover tugas 1 ekonomi rekayasa 1 -In a housing project the following sequence of events occurs. At the start of the project (time zero), land is bought at $1, 000 Two months later, $100, 000 is paid to the architect for preparing the design In month 4, construction is started and the cost of construction (labor and material) is $ 150, 000 per month. Every month, one house is built (a total of 12 houses); the first one is ready for sale in month 6. During every month starting from month 8, one house is sold for a price of $ 250, 000 each. After all of the houses are built and before all are sold, the cost of maintaining the site is $10, 000 per month. Draw the cash flow diagram. 2 -Mr. Shop purchases a pizza shop for $120, 000. Its operation will result in a net income of $15, 000/Yr for the first year, increasing by $2, 000 each year after year 1. At the end of the fifth year, the shop is sold for $155, 000. Draw the cash flow diagram for this project. 3 -A credit card company announces that its interest rate is 1. 5% per month. What is the corresponding effective annual interest rate?