RISK MODULE 7 Risk Identification and management of

  • Slides: 23
Download presentation
RISK MODULE 7

RISK MODULE 7

Risk • Identification and management of project risks throughout the life of the project.

Risk • Identification and management of project risks throughout the life of the project.

Risk Allocation Decisions Risk Party Recommended to Assume the Risk How Risk is Assigned

Risk Allocation Decisions Risk Party Recommended to Assume the Risk How Risk is Assigned or Managed Site access Owner Advance planning Constriction means/methods Contractor Specific contract clause Labor productivity Contractor’s management Subsurface conditions Owner Adequate investigation of geotechnical and other conditions, contract clause Weather, acts of God Shared-owner assumes delay risk, contractor assumes dollar risk Contract clause Other delays Responsible party-shared if neither responsible Contract clause Design professional Use QBS procedures Unanticipated hazardous materials Owner Site investigation, contract clause Unresolved disputes Shared-owner, contractor, design professional Contract clause

Management and allocation of Risk • Risk management is a PM/CM responsibility • Role

Management and allocation of Risk • Risk management is a PM/CM responsibility • Role and responsibilities • Site • Relationships • Contract documents • Transfer of risk thru design intent/contractor • City hires the contractor to build (transferring of risk)

Negating Risk – Allocated to the Contractor • Helping with the work • Directing

Negating Risk – Allocated to the Contractor • Helping with the work • Directing the work • Discovering unforeseen conditions • Waiving specs • Accepting inferior work

Why Risk Management • Perhaps the most compelling argument for pursuing risk assessment and

Why Risk Management • Perhaps the most compelling argument for pursuing risk assessment and allocation as a standard practice is that the best agencies and organizations worldwide are doing it, and with great success. • What if you do nothing?

How Do You Effectively Manage Risk? Active, thoughtful risk taking is just as important

How Do You Effectively Manage Risk? Active, thoughtful risk taking is just as important as risk mitigation. • Does the agency have adequate and dynamic processes in place to identify existing and new risks faced? • Does the agency have the right balance of arrangements in place to deal with these risks? • Does the agency have an adequate framework for risk analysis and evaluation to support decision making processes?

Examples of Risk • Designer designs a deep utility requires…. trench …. • Design

Examples of Risk • Designer designs a deep utility requires…. trench …. • Design requires utilization of a traffic control to perform the work. City allowed ….

Example of Risk - Safety • Code of Safe Practices • Public Safety -

Example of Risk - Safety • Code of Safe Practices • Public Safety - MUTCD • Contractor Safety - Cal. OSHA • Reports

Risk Management Process • Identification • Assessment • Analysis • Mitigation • Allocation •

Risk Management Process • Identification • Assessment • Analysis • Mitigation • Allocation • Tracking and updating

Outputs from Risk Assessment and Allocation • Risk Registers • Expected value analyses of

Outputs from Risk Assessment and Allocation • Risk Registers • Expected value analyses of cost and duration with probability values for other • • • potential outcomes. Value of information and control. Contingency assessments for cost and duration. Sensitivity analysis for individual risks. Risk management mitigation plans and strategies. Risk-based analyses of preferred project contracting/procurement approach. Risk allocation decisions that align team members with customer-oriented performance measures.

Risk Register Project Phase Long-range Planning/Programming Status • • Preliminary Engineering • • Typical

Risk Register Project Phase Long-range Planning/Programming Status • • Preliminary Engineering • • Typical Risk Issue Focus is on general alignment and mode Project details not defined; environmental reviews incomplete Funding possibly not committed Public support uncertain • Comprehensive definition of project goals Environmental reviews approaching completion (Record of Decision) Initial approvals received but long-term funding commitments still to be determined High cost and schedule contingencies • • • Objectives for Assessment Fatal or significant environmental economic impacts Funding uncertainty Uncertain political and public support Competing interests and competing projects • Changes to project scope and budget Costs of environmental compliance Appropriate procurement methods Changes in design requirements Right-of-way acquisition Technical uncertainties Errors or omissions in quantities, inaccurate unit prices Market conditions Funding uncertainty • • • Expected Outcome Identify implementation challenges - political, public acceptance, approvals Establish order of magnitude costs by option Identify major design and construction risks • • • Better understanding of environmental, engineering, and construction issues facing each project alternative Order of magnitude risk costs and possible total cost range for each option

Risk Register (cont. ) Project Phase Final Design Status • • Project goals communicated

Risk Register (cont. ) Project Phase Final Design Status • • Project goals communicated to contracting partners Project scope, cost, and schedule well defined Minor open issues since all cost and design detail well advanced Construction approvals, including permits and agreements, not yet final Typical Risk Issue • • Changes to project scope and budget Errors or omissions in quantities, inaccurate unit prices Changes in design requirements Market conditions, permit requirements Objectives for Assessment • • • Construction • • • Design complete; project defined Commitments (funding, policy, etc. ) in place Construction in progress • • • Contractor performance, construction quality Final permitting, right-ofway acquisition Unanticipated site/working conditions Field design changes Construction safety • • Expected Outcome Identification, quantification, and likelihood of all identifiable scope, budget, and schedule risks for all project components Detailed definition of base costs, risk costs, and total probable project costs Validation of reasonableness of contingencies in project budget and schedule • Targeted assessment of construction problems, causes, and potential cost/ schedule impacts Identification and systematic evaluation of possible corrective actions • • • List of major critical risks, prioritization of risks based on impacts to total project cost and duration Estimate of risk costs and probable total project costs and duration Costs/benefits of risk mitigation and risk allocation strategies Risk management and allocation plan Analysis of specific problems Costs/benefits of possible corrective actions Corrective action plan that will allow project sponsors/owners to maintain (or recover) schedule and avoid cost overruns

Successful Risk Management Programs Feasible, stable, and well-understood user requirements. A close relationship with

Successful Risk Management Programs Feasible, stable, and well-understood user requirements. A close relationship with user, industry, and other appropriate participants. A planned and structured risk management process integral to the acquisition process. An acquisition strategy consistent with risk level and risk-handling strategies. Continual reassessment of project and associated risks. A defined set of success criteria for all cost, schedule, and performance elements (e. g. , performance baseline thresholds). • Metrics to monitor effectiveness of risk-handling strategies. • Effective test and evaluation program. • Formal documentation. • • •

Sample Construction Risk Register

Sample Construction Risk Register

Managing the Risk Exercise • Use Risk Register to discuss how to manage on

Managing the Risk Exercise • Use Risk Register to discuss how to manage on a monthly basis

Claims and Disputes • Notice (Unforeseen Conditions) • Protest (CCO or Contract Time) •

Claims and Disputes • Notice (Unforeseen Conditions) • Protest (CCO or Contract Time) • Potential Claim (before Final Estimate) • Claim

Claim Mitigation • Liability Protection • Be Prepared • Understand Your Contract • Be

Claim Mitigation • Liability Protection • Be Prepared • Understand Your Contract • Be Reasonable • Response = Firm, Fair, Fast • Document, Document

Graphic depiction -Risk Management

Graphic depiction -Risk Management

Graphical Standpoint

Graphical Standpoint

Success Management • Identification • Probability Risk # 1 2 • Impact • Mitigation

Success Management • Identification • Probability Risk # 1 2 • Impact • Mitigation Measures 3 4 5 Risk Description Utility: Underground utilities investigation and coordination Traffic Handling/Staging: Port access and local truck traffic circulation Differing Site Conditions: Unforeseen subsurface conditions High ground water and treatment Contaminated Soil Permits: Coastal Permitting and Army Corps Environmental Issues: Protected species – birds (least tern) Eel grass and wetlands protection Impact Mitigation GPR H, M, L TMP H, M, L Preliminary Investigation H, M, L Bid Allowance Compliance Monitoring ECR H, M, L

Proactive Resolution of Construction Issues • Partnering • Independent field investigations and contract document

Proactive Resolution of Construction Issues • Partnering • Independent field investigations and contract document verification • Timely resolution at the lowest level • Escalate unresolved issues quickly • Provide claim support if necessary

Conclusion The rigorous process of risk identification, assessment, analysis, mitigation, allocation, and monitoring and

Conclusion The rigorous process of risk identification, assessment, analysis, mitigation, allocation, and monitoring and updating allows for a more transparent and informed allocation of project risk. When risks are understood and their consequences are measured, decisions can be made to allocate risks in a manner that minimizes costs, promotes project goals, and ultimately aligns the construction team (agency, contractor, and consultants) with the needs and objectives of the traveling public.