PLATO TOU KO MEETING H Rauer DLR PF

  • Slides: 15
Download presentation
PLATO TOU KO MEETING H. Rauer (DLR PF) H. Kinter/A. Salado (Kayser-Threde)

PLATO TOU KO MEETING H. Rauer (DLR PF) H. Kinter/A. Salado (Kayser-Threde)

Activities • Mission selection in Feb. 2014 • Payload industrial management is being assigned

Activities • Mission selection in Feb. 2014 • Payload industrial management is being assigned for “bridging period” and B 1 Phase to Kayser-Threde • Status of payload teams, PDC, PSPM is reviewed • „Kick-off“ Phase B 1: July 16/17 2

PLATO Camera Management Support Overview Image Copyright: Mark A. Garlick. Science Credit: Carole Haswell

PLATO Camera Management Support Overview Image Copyright: Mark A. Garlick. Science Credit: Carole Haswell & Andrew Norton (The Open University)

Agenda • KT Team Organization and responsibilities • Main Phase B 1 Preparation Activities

Agenda • KT Team Organization and responsibilities • Main Phase B 1 Preparation Activities • B 1 Schedule Overview: • KT Questions to TOU team

PLATO Payload Management Key Personnel Name Function Richard Haarmann PIPM Bernd Schulz PA/QA Manager

PLATO Payload Management Key Personnel Name Function Richard Haarmann PIPM Bernd Schulz PA/QA Manager Alejandro Salado Payload Sys. Engineering (PTC) Hilda Kinter Camera Project Manager (CPM) PIPM Deputy Valery Mogulsky Camera Systems Engineering Roberto Montedori Payload AIV Manager (PAM) Gisbert Peter DPS Project Manager (DLR)

Main Phase B 1 Preparation Activities Phase B 1 Planning • Detail roadmap until

Main Phase B 1 Preparation Activities Phase B 1 Planning • Detail roadmap until KO Phase B 1 and beyond Synchronization of all partner activities • Major Milestones for the Phase B 1 Date Event 15. -16. July 2014 Phase B 1 Kick-Off March 2015 PLATO Design Consolidation Review (PDCR) October 2015 PLATO B 1 data package delivery for SRR November - December 2015 PLATO System Requirements Review (SRR) March 2016 Mission Adoption & IPC approval April 2016 Kick-off Phase B 2/C/D January 2024 PLATO Launch

Main Phase B 1 Preparation Activities Preparation B 1 Kick-Off Data Package Establish an

Main Phase B 1 Preparation Activities Preparation B 1 Kick-Off Data Package Establish an updated Specification Tree to define the interrelation between the single PLATO P/L component specifications Basis for the traceability of single requirements and interface management Definition of all required documents for the B 1 Kick-Off Comparison with existing documentation to identify necessary inputs Completion / annotation of existing specifications Utilization as applicable documents for the B 1 work upon PDCR

Phase B 1 • 1 st P/L Meeting has been on 06. /07. 05.

Phase B 1 • 1 st P/L Meeting has been on 06. /07. 05. 2014 – Bring P/L consortium together – Start to resume P/L teams • Phase B 1 KO is scheduled for 16. /17. 07. 2014 – Official Start of Phase B 1 – All work packages are already defined – Tasks to be done between KO and 2 nd P/L Consortium Meeting will be defined • 2 nd P/L Meeting proposed Fall 2014 – All specifications and belonging annotations/supplements are available as basis for the B 1 development work

PLATO Phase B 1 Schedule

PLATO Phase B 1 Schedule

Overview of major Phase B 1 Deliverables Meeting Date Deliverables KO 16. 07. 14

Overview of major Phase B 1 Deliverables Meeting Date Deliverables KO 16. 07. 14 * Drafts of TOU Requirements Specification, Camera Development & Verification Plan, List of Deliverables, 2 nd P/L Meeting 15. 09. 14 * First issue of above documents PM 1 18. 11. 14 Progress report + specified deliverables PM 2 20. 01. 15 Progress report + specified deliverables PDCR delivery 02. 03. 15 Progress report + specified deliverables PM 3 12. 05. 15 Progress report + specified deliverables PM 4 21. 07. 15 Progress report + specified deliverables PM 5 22. 09. 15 Progress report + specified deliverables SRR delivery 02. 11. 15 Camera Reports, models, Camera URDs and I/F documents * drafts to be prepared by KT Specified deliverables defined in the List of Deliverables, which may include Camera Reports (design, budgets, performance, straylight, thermal, structural, risk assessment), MAIV plan, Management Plan, mathematical models

Communication between TOU team and KT List of all deliverables to be defined and

Communication between TOU team and KT List of all deliverables to be defined and finalised by 2 nd P/L Meeting PMs to be held at TOU site or by Webex. Required documents and Progress Reports including status of AIs to be delivered at least five working days before the meeting Regular bi-weekly telecons between TOU lead team and KT: brief discussion of working progress, identified problems, needed inputs etc the traceability of single requirements and interface management Meeting when necessary with other Camera/Payload/PLATO teams by Webex (organised by KT). For critical topics, like I/F discussions, face to face meeting are preferable

Payload Camera Subsystem Status Summary: Goals Phase B 1 • Goals Phase B 1:

Payload Camera Subsystem Status Summary: Goals Phase B 1 • Goals Phase B 1: To achieve a sufficient level of technical maturity to ensure a uccessful SRR. • • • system requirements for the selected architectures • • • successfully validated system requirements derived • • confidence on the eadiness levels of various technologies. • consolidating the requirements on system and subsystem level nd their traceability consolidating internal interfaces, assessing requirements for external interfaces consolidating performance models consolidating and defining operational modes of the payload and its arious subsystems and components. validating the set f system and subsystem requirements Establish a verification strategy consistent with programmatic limitations and equired scientific value. Develop technology maturation programs in order to achieve the required TRL levels at RR

Telescope Optical Unit (TOU) Status Summary: • Team? Several Institutions (INAF, Univ. Bern, Stockolm

Telescope Optical Unit (TOU) Status Summary: • Team? Several Institutions (INAF, Univ. Bern, Stockolm Obs. , Univ. Firenze) + Industrial Partners (Selex , Medialario-Sagem, Seso, RUAG, APCO Technologies) led by INAF (Interface to Camera team) • Current Status? – Optical Design + options available – Breadboard/Prototypes: TOU AIV procedure already performed (TOU Optical and Thermal Performance) – Further Breadboard with AIV and thermal behavior identified AIV procedures under development with serial production in mind • Next Steps? – Answer MEMO questions

Issues/questions to the TOU Team Image Copyright: Mark A. Garlick. Science Credit: Carole Haswell

Issues/questions to the TOU Team Image Copyright: Mark A. Garlick. Science Credit: Carole Haswell & Andrew Norton (The Open University)

Main Phase B 1 Preparation Activities Questions to/inputs from TOU team: – List of

Main Phase B 1 Preparation Activities Questions to/inputs from TOU team: – List of TOU team including percentage allocation for PLATO – Is there a Central point for Camera document collection? – List of available technical documents: – List of MEMO Questions • Component I/Fs • Operational modes, states, and transitions • Performance models or simulators • Behavioural models or simulators • Performance wrt requirements • Model philosophy • Assumptions employed in analyses • Requirement specification • Open issues and decisions • Current risks and their mitigation strategies