LNG READY SOLUTION USING A MARK FIT LNG

  • Slides: 18
Download presentation
LNG READY SOLUTION USING A MARK FIT LNG FUEL TANK OPERATING UP TO 2

LNG READY SOLUTION USING A MARK FIT LNG FUEL TANK OPERATING UP TO 2 BARG: THE CASE OF VLOC Jacques Danton– GTT Owned and presented by Host IGU Member Supporting Association

Introduction • Emission control area coming into effect -> LNG fuel interesting alternative for

Introduction • Emission control area coming into effect -> LNG fuel interesting alternative for marine propulsion • GTT offering new solutions for the use of LNG as a fuel: – New Mark FIT technology -> better use of space inside the ship – New approach regarding the installation of LNG tanks on ships – Raising of pressure inside the tank to 2 bar -> more flexibility • LNG fuel especially interesting for Australia due to local ressources

Mark FIT: design philosophy

Mark FIT: design philosophy

Mark FIT: volumetric efficiency • Mark FIT allows a wide range of possible angles

Mark FIT: volumetric efficiency • Mark FIT allows a wide range of possible angles • Mark FIT optimizes the space dedicated to LNG fuel thanks to unmatched volumetric efficiency

VLOC • • • LNG interesting for Very Large Ore Carrier Several possibilities regarding

VLOC • • • LNG interesting for Very Large Ore Carrier Several possibilities regarding the retrofit philosophy Typical VLOC: LOA = 300 m; up to 250000 dwt Range: 12000 nm -> 5000 m 3 of LNG required One specifity: 1 additional cargo for use for LNG containment

Newbuild • Identical approach as LNG Carriers • Membrane installed directly on the hull

Newbuild • Identical approach as LNG Carriers • Membrane installed directly on the hull during construction • Maximization of the LNG volume • Cheapest solution for LNG use

Retrofit • Several option for retrofit operation: – – Installation of membrane inside the

Retrofit • Several option for retrofit operation: – – Installation of membrane inside the hold n° 8 Jumboisation Installation of an exoskeleton inside the hold n° 8 Installation of an exoskeleton on deck • Necessity to prepare LNG conversion at design stage to insure feasibility and avoid additional cost during retrofit operation • Retrofit of engines (if not dual fuel) must also be considered anticipated

Retrofit by jumboisation • Section containing fully equipped LNG tank and fuel gas handling

Retrofit by jumboisation • Section containing fully equipped LNG tank and fuel gas handling system is added to the ship • No loss of cargo space

Retrofit using an exoskeleton • A self standing tank equipped with membrane is installed

Retrofit using an exoskeleton • A self standing tank equipped with membrane is installed on the ship • Work mostly done in the shipyard before ship immobilization -> reduced immobilization time • Possibility to include the fuel gas handling system in the structure

Exoskeleton on deck • First option: install the exoskeleton on deck • Easy and

Exoskeleton on deck • First option: install the exoskeleton on deck • Easy and quick operation • Minimal welding work • No additional hold is needed by room on deck is required

Exoskeleton inside the hull • Other option is to install the tank inside a

Exoskeleton inside the hull • Other option is to install the tank inside a hold • More complex operation • No wasted space • Weight optimization by integrating the tank to the hull

Impact of retrofit operations Immobilization time Work performed on the hull Installation of membrane

Impact of retrofit operations Immobilization time Work performed on the hull Installation of membrane inside a cargo hold Several months (depending of the size of the tank) Cutting and welding of the top of the tank Jumboisation ~6 weeks Important cutting and welding work Exoskeleton integrated to the hull ~6 to 8 weeks Cutting and welding work Exoskeleton on deck ~4 weeks Only welding of the exoskeleton to the hull

Cost of using LNG • 20% more CAPEX for newbuilding LNG fuelled ship compared

Cost of using LNG • 20% more CAPEX for newbuilding LNG fuelled ship compared to conventional • 5% more compared to ships with scrubbers and EGR / SCR • LNG ready ship a little more expensive than conventional but most of the cost comes from the retrofit operation • Loss of cargo space depending on LNG tank location • Loss of vessel time due to retrofit operation to be taken into account

Why 2 barg? • Longer holding time, with or without spraying, during blackout periods

Why 2 barg? • Longer holding time, with or without spraying, during blackout periods or extended period at anchor -> more flexibility during ship operation • Boil-off gas generated during bunkering operations is kept inside the tank for future use -> more flexibility • Ability to bunker warmer LNG -> More flexibility toward LNG supply Holding time for a small tank; Larger tanks will result in longer holding time

IGF and 2 barg • Pressure inside LNG tanks historically limited to 0. 7

IGF and 2 barg • Pressure inside LNG tanks historically limited to 0. 7 barg in IGC Code • MARVS usually at 0. 25 bar on LNGC -> decision not justified by the code but by other consideration (additional weight, operational needs…) • FEA now extremely common and reliable -> no problem in dimensioning a structure supporting 2 barg • No problem for membrane technology • 2 possibilities in the code to go to 2 barg – Alternative design – Limit state design

Impact of 2 barg on the ship • No impact on GTT membrane •

Impact of 2 barg on the ship • No impact on GTT membrane • No impact on the ship if exoskeleton is on deck but around 50% more steel in the exoskeleton • If tank integrated to the hull, impact on the ship is dependant of the scantling. In case of VLOC, scantling are important enough due to heavy cargo loads

Impact of 2 barg on cost • CAPEX: – Only related to additional steel

Impact of 2 barg on cost • CAPEX: – Only related to additional steel weight – Not significant on VLOC (already very strong hull) – 15 additional tons for liquid and gas dome • OPEX: – No need to use Boil-off gas management solution thanks to longer holding time

Conclusion • Mark FIT is an interesting option to comply with new norms: –

Conclusion • Mark FIT is an interesting option to comply with new norms: – Based on reliable and sea-proven technical choices – Maximization of the volume of LNG stored – Retrofit options for all configurations • Abundance of LNG in Australia make supply easier and cheaper • Most significant problems regarding flexibility solved by raising pressure to 2 bar: – LNG supply – Ease of use by the crew