Analysis of TCT losses during 2017 asynch dump
- Slides: 14
Analysis of TCT losses during 2017 asynch dump tests R. Bruce With help and inputs from C. Bracco, N. Fuster, S. Redaelli, C. Wiesner
Introduction • Reminder: Losses on TCTs during an asynch dumps need to be stay below a limit to make that they do not risk to be damaged – Limiting collimation hierarchy and hence β* in Run I and 2015 • In 2016, used new optics with rematched MKD-TCT phase advance (worst at 4 deg) to remove limitation and ensure that MKDs cannot kick primary beam directly onto TCTs • 2017: Improved version of ATS optics deployed, with (worst) MKD-TCT phase advance at 154 deg – Not as good as for the nominal optics, but within specified range of 30 deg from 0 and 180 – Started carefully with larger margin TCDQ-TCT than in 2016 – Stayed at β*=40 cm and TCTs at 9 σ in spite of 1 σ more margin from IR 6/7 R. Bruce, 2017. 07. 31 2
Situation in 2017 • Based on data, would like to verify that the assumptions done for the 2017 run were correct • What can we conclude on the TCT losses from the asynch dump tests done during the 2017 validations? • – If we scale up to a full physics beam, and assume that the TCT and TCDQ placement is on the limit of the tolerated range, are the TCTs safe? – Consistent with expectations from simulations? – Can the operational TCT setting safely be moved in further? This would allow a further decrease in β*, as envisaged in Evian To check dependence of TCT losses on setting: as in 2016, did asynch dump tests with standard TCT settings as well as tighter TCTs in 2017 R. Bruce, 2017. 07. 31 3
Asynch dump tests • Asynch dump tests carried out in commissioning, TS 1 revalidation and MD • Checked TCT losses in the following tests: Timestamp Machine configuration TCT setting 22/05/17 22: 16: 07. 411 Commissioning: 40 cm collision, 150 urad 9. 0 σ 03/06/17 22: 49: 12. 753 Commissioning: 40 cm collision, , 150 urad 7. 5 σ 08/07/17 11: 35: 38. 708 TS 1: 40 cm, end of squeeze, 150 urad, B 2 only 7. 5 σ 11/07/17 08: 09: 17. 229 TS 1: 40 cm collision, 90 urad 9. 0 σ 10/07/17 04: 43: 33. 996 TS 1: 40 cm collision, 150 urad 9. 0 σ 12/07/17 02: 30. 836 TS 1: 40 cm collision, 150 urad 6. 5 σ 25/07/17 22: 34: 26. 412 MD: 30 cm end of squeeze, 175 urad, pilots only 6. 5 σ • In addition, several data sets removed since the test was not carried out properly, and several tests failed due to operational mistakes R. Bruce, 2017. 07. 31 4
Outline of TCT loss analysis (1) • Goal: scale up TCT losses during test to a full physics beam to judge safety • Method: From BSRA, calculate beam population in abort gap over slice where beam can be kicked on TCTs – Consider 8 bunches between 5 σ and 16 σ R. Bruce, 2017. 07. 31 June 6 2017 Low MKD kicks Kick[σ] vs time High MKD kicks 5
Outline of TCT loss analysis (2) • Calculate the number of protons lost on TCT by multiplying BLM signal by conversion factor (from FLUKA or measurement) – 40 us BLM data from post mortem • Take ratio of protons lost on TCT to the abort gap slice, and scale up to full physics beam in corresponding slice R. Bruce, 2017. 07. 31 BLM response 6
Updates since last presentation • First attempt at analyzing TCT losses: CWG/MPP on 9/6/2017 • Saw sharp increase in losses at 7. 5 σ in B 2 – Not real – problem in analysis – Off-momentum effect from RF switched off should be small • Repeating analysis, including also all new asynch dump tests, and including 30 cm MD • Comparing data scaled to full 25 ns physics beam with simulations – Asynch dump, all kickers firing simultaneously, as in tests – Simulations: factor ~3 larger losses for a single-module pre-fire R. Bruce, 2017. 07. 31 7
Comparison measurements / simulations • TCT losses during asynch dump, scaled to full physics beam, as function of TCT setting Using BLM conversion factor 2. 1 E-11 Gy/p, measured parasitically in aperture MDs 2015/16 NIM A 848 (2017) 19– 30 R. Bruce, 2017. 07. 31 8
Comparison measurements / simulations • Same, using FLUKA BLM conversion factor • Excellent agreement within ~30% except for 30 cm and B 2 with TCTs at 6. 5 σ Using BLM conversion factor 4. 7 E-11 Gy/p, simulated with FLUKA, E. Skordis, CWG 206 R. Bruce, 2017. 07. 31 9
Comparison measurements / simulations • Explanation (? ): Real phase to IR 5 TCT B 2 better than the ideal used in simulation • Compare: primary losses simulated with phase-space integration (method explained in NIM A 848 (2017) 19– 30) MKD-TCT IR 5 B 2 40 cm 30 cm Ideal 154 o 155 o Measured 156 o 157 o Courtesy OMC team Using BLM conversion factor 4. 7 E-11 Gy/p, simulated with FLUKA, E. Skordis, CWG 206 R. Bruce, 2017. 07. 31 10
Observations • Scaled up to full physics beam, order of 1 E 9 protons could be expected on TCTs during asynch dump and maybe 3 E 9 during single-module prefire – Given that we are still on the “flat” part of the curve given by spread-out secondary losses, this is well below estimated damage of ~1. 2 E 11 p for plastic deformations (E. Quaranta et al, IPAC 2016) – With more focused primary beam, plastic deformation limit is estimated at 5 E 9 protons (A. Bertarelli et al. , MPP workshop 2013) • All tests done with 1. 2 mm bump in IR 6 – At 40 cm, this is 2. 4 σ – At 30 cm, this is 2. 2 σ in B 1 (changing β in IR 6 during telescopic squeeze) • Assuming a TCT setting of 8 σ compatible with aperture, at 6. 5 σ as in test we have a total margin violation of 2. 4 σ + 1. 5 σ = 3. 9 σ – SIS interlock should dump already at 1 σ at TCTs and 1. 5 σ at TCDQ – Extremely pessimistic conditions in 6. 5 σ test ! We should have some margin R. Bruce, 2017. 07. 31 11
Conclusions • TCT losses analyzed in all asynch dump tests done in 2017 • In most cases, excellent agreement with simulations – At 6. 5 σ TCT setting, measure less losses than predicted by simulations • Even at 6. 5 σ TCT setting and 1. 2 mm bump in IR 6, losses scaled up to a full physics beam are well under control – Much more pessimistic than can be expected in operation • No showstopper for going to β*=30 cm from TCT losses during asynch dump – No showstopper seen in aperture measurement either R. Bruce, 2017. 07. 31 12
Backup R. Bruce, 2017. 07. 31 13
Phase space integration • For parametric studies, need faster optics-independent method • Using simplified method to study the dependence of primary impacts on the phase advance • Integrating beam distribution over the linear cuts in phase space • Again, studying 25 ns bunches separately and summing over all • Depends only on settings and phase advance - optics not needed • All collimators black absorbers => only primary impacts studied Setup described in detail in PRSTAB 18, 061001 (2015) NIM A 848 (2017) 19– 30 R. Bruce, 2017. 02. 06 14
- Contoh aliran dalam pipa
- Tct congress 2018
- Tct scan
- Tct
- Tct 2013
- Sql server crash dump analysis
- 16 losses in tpm
- What is arbitrary ratio
- Six big losses in lean manufacturing
- 16 types of losses in tpm
- Infiltration
- Nonrecaptured section 1231 losses
- In khosla's formula monthly losses is calculated as
- The bend
- Artical 231