WP 1 2 Photon Detectors Slides for OSC

  • Slides: 13
Download presentation
WP 1. 2 – Photon Detectors Slides for OSC q Budget q Milestones q

WP 1. 2 – Photon Detectors Slides for OSC q Budget q Milestones q Progress Report • Dependencies q Risk Register Edinburgh, 18. 11. 2016 Stephan Eisenhardt University of Edinburgh

WP 1. 2 Budget o o Photon Detector contract with Hamamatsu: signed in 12/2015

WP 1. 2 Budget o o Photon Detector contract with Hamamatsu: signed in 12/2015 Expenditure scales with photon detector delivery – main production for R 13742 (1’’) has started, ‘end-of-month’ shipments: • batch 1&2 of 84 x R 13742 each has been delivered, batch 3 is in transit – latest delivery plan(*) (06/2016): 03/2016 (pre-series) 1 mth 08/2016 -09/2016 2 mths 10/2016 1 mths 08/2016 -11/2016 1 mths 12/2016 -01/2017 2 mths 02/2017 -05/2017 4 mths 06/2017 -03/2018 10 mths 04/2018 1 mth sum 21 mths monthly shipments R 13742 (1’’ tubes) CERN INFN total 28+4 22 = 54 59 25 = 84 115 25 =140 152 28 =180 154 28 =182 2520 580 3100 R 13743 (2’’ tubes) CERN 20 delivered in transit 25 25 30 450 (*) note: shipments due at very end of month, i. e. will arrive at CERN ~10 th of following month Edinburgh, 18. 11. 2016 Stephan Eisenhardt 2

WP 1. 2 Milestones o Milestones: – WP 1. 2. 1: Characterisation of photon

WP 1. 2 Milestones o Milestones: – WP 1. 2. 1: Characterisation of photon detectors in the lab • • A: Photon Detectors qualified for TDR B: Optimisation with front-end readout chip for EDRs – WP 1. 2. 2: Photon detector test facilities, fully qualify 3100 Ma. PMTs, 450 Flatpanel PMTs and spares • • • A: Facilities fully commissioned ready to start production run B: Photon detector production testing starts C: Photon detector production testing completed – WP 1. 2. 3: Fully assembled photon detector columns • • A: Start Elementary Cell assembly B: Start mounting Elementary Cells on columns C: Mounting Elementary Cells on columns completed D: Photon detectors commissioned in situ – WP 1. 2. 4: Photon detector monitoring and calibration fully operational • A: System ready for installation 01/15 completed 12/13 completed 01/15 completed 11/18 04/16 completed in report period: 05/2016 06/16 completed in report period: 05/2016 11/18 03/20 was 11/19 03/18 was 05/17, next milestone coming up 10/18 was 08/17, 2 nd next milestones coming up 03/20 was 04/19 06/20 was 01/20 04/20 was 12/19 (adapt to commissioning) 06/19 was 12/18 (adapt to commissioning) – notes for changes in milestones: • • now make full use of shift in LHC schedule announced a year ago shift in schedule for the production of Front-End-Boards and base boards push the schedule of the production of the components for the Elementary Cell to 10/17 or later • change of strategy in testing ECs components: all components will now be fully tested by manufacturing institutes, only assembly and final functionality remains here, tests start in 03/18 to minimise overlap with testing of photon detectors Edinburgh, 18. 11. 2016 Stephan Eisenhardt 3

WP 1. 2 Progress Report o Photon Detector Quality Assurance test facilities: – Edinburgh

WP 1. 2 Progress Report o Photon Detector Quality Assurance test facilities: – Edinburgh test facilities: • test systems (for R 13742 & R 13743) and core DAQ software fully working (old news) • ongoing software development: – automation of DAQ workflow (to reduce operator work-load) – on-line feedback for data quality (to aid human interpretation of gathered data) – Padova test facilities: • test system for R 13742 and DAQ software fully working (new) – cross-calibration with Edinburgh yielded well consistent results • test system for R 13743 in commissioning • ongoing software development: (new) – off-line bulk signal spectra fitting and parameter extraction for storage in data base – state of software development causes still a lot of manual labour (this will ease) o Production Ma. PMT testing: deliveries to CERN, then forwarded to Edi/Pad – batch 1: 84 x R 13742 (1’’) delivery ~10. 09. @CERN: fully tested at Edi • 6 test loads a 16 x R 13742: i. e. 6 days of data acquisition – data analysed: 0 rejects – batch 2: 84 x R 13742 (1’’) delivery ~10. @CERN: fully tested at Padova • 6 test loads a 16 x R 13742: i. e. 6 days of data acquisition – analysis of data ongoing: Edinburgh, 18. 11. 2016 Stephan Eisenhardt 4 expect 0 rejects

WP 1. 2 Progress Report o Example production test results (batch 1): tube gain

WP 1. 2 Progress Report o Example production test results (batch 1): tube gain uniformity way above specs tube gain vs. Hamamatsu gain very good correlation batch 1&2 tube gain distribution average ~3. 5 Meunexpected tail to very high gain batch 1: 0 rejects batch 2: 0 rejects expected from preliminary analysis peak-to-valley ratio for 16 Ma. PMT (single photon signal quality) pixel gain in 13 Ma. PMT: Edi vs. Padova cross-calibration better than expected: only 1 pixel in 84 Ma. PMT below 1. 03 very good correlation Edinburgh, 18. 11. 2016 Stephan Eisenhardt 5 (allowed are up to 3 pixels below 1. 03 per Ma. PMT) (1 Ma. PMT with gain setting off-scale, 1 DAQ board broken: subsequently all fixed)

WP 1. 2 Progress Report – Dependencies o Photon Detector contract with Hamamatsu –

WP 1. 2 Progress Report – Dependencies o Photon Detector contract with Hamamatsu – Hamamatsu production deliveries (months 1 -3 of 21 -month schedule) worked like clock-work – Ma. PMT production quality very good o CLARO 8 v 3 chip – submission returned in January as expected (old news) – studied in lab, beam test just finished this week (preliminary results? ) – needed in time for Elementary Cell o Electronics/Elementary Cell test systems: – EC PRR held on 02. 09. : start of EC assembly moved to 03/2018 (was 05/17) • to match tender & production of EC components (Front-End-Boards, base board) • overlap with final phase of Ma. PMT testing has raised concern (to be mitigated by automation of Ma. PMT testing and analysis & optimisation of work force) – EC testing developed by Ferrara: EC assembly & testing work shop at Ferrara on 22. 11. 2016 • pool and discuss current plans and ideas & kick off development – on track compared to plan and revised milestones Edinburgh, 18. 11. 2016 Stephan Eisenhardt 6

WP 1. 2 Risk Registers ate d p u In: d o t o

WP 1. 2 Risk Registers ate d p u In: d o t o RISK s ghte k s i i l r h – WP 1. 2. 2: hig 1 Development of photon detector test LIKELIHOOD IMPACT facilities delayed Possible (has already happened) Major redundancy in testing facilities, allows increase of Mitigation (fill in next field testing rate; ultimately could use the datasheet values ) provided by Hamamatsu for photon detector selection 2 Delay in photon detector quality assurance programme Possible (has already happened) Major redundancy in testing facilities, allows increase of Mitigation (fill in next field testing rate; ultimately could use the datasheet values ) provided by Hamamatsu for photon detector selection 3 Hamamatsu slipping in delivery schedule Possible (has already happened) Major redundancy in testing facilities, allows increase of Mitigation (fill in next field testing rate; ultimately could use the datasheet values ) provided by Hamamatsu for photon detector selection Rare (never happens) Catastrophic 4 Hamamatsu going bust 5 Currency fluctuations, funds not sufficiend for requred tubes 6 Development of CLARO test facilities delayed 7 DECISION Acceptance HOW TO MITIGATE IT large international company, with healthy base of customers Major Mitigation (fill in next field Create a yen account (if it's OK to say that ) ? ? ? ) Possible (has already happened) Major Mitigation (fill in next field using redundancy and Hamamatsu data as above, and ) diverting other manpower to support development Development of FEB test facilities delayed Possible (has already happened) Major Mitigation (fill in next field using redundancy and Hamamatsu data as above, and ) diverting other manpower to support development 8 Development of EC test facilities delayed Possible (has already happened) Major Mitigation (fill in next field using redundancy and Hamamatsu data as above, and ) diverting other manpower to support development 9 Delay in CLARO chip & base board production Possible (has already happened) ? ? ? Major Mitigation (fill in next field final version close to submission, all technical issues ) with penultimate chip version solved ? ? 10 Photon detector monitoring system delayed Possible (has already happened) Moderate new system uses largely existing infrastructure, late Mitigation (fill in next field development is possible or reuse of existing ) infrastructure Edinburgh, 18. 11. 2016 Likely (50% probability)? ? ? Stephan Eisenhardt 7

Spare Slides Edinburgh, 18. 11. 2016 Stephan Eisenhardt 8

Spare Slides Edinburgh, 18. 11. 2016 Stephan Eisenhardt 8

WP 1. 2 Progress Report o Example pre-series test results (preliminary): valley single pixel

WP 1. 2 Progress Report o Example pre-series test results (preliminary): valley single pixel photon signal spectra (from dark count & HV scan) peak fitted photon signal spectrum 54 x R 13742 & 10 re-tests gain extraction for 64 channels(1 x R 13742) 5 x R 13742: K-factor (“gain rise with HV”) 20 x R 13743 <gain> correlation with Hamamatsu data <gain>: >1… 6 x 106 e- 4 x R 13743: peak-to-valley ratio typically >>1. 03 ! Edinburgh, 18. 11. 2016 Stephan Eisenhardt 9

rt. w ge 15 n a ch 06/20 o n ort rep o WP

rt. w ge 15 n a ch 06/20 o n ort rep o WP 1. 2 Partners International Collaborating Groups: – WP 1. 2. 2: Photon detector test facilities and quality assurance Padova, Italy: • testing 50% of the photon detectors • replacing the cut Glasgow group – WP 1. 2. 3: Photon detector module assembly Ferrara, Italy: • providing Elementary Cell testing facility • testing 50% of Elementary Cells using the photon detectors tested at Padova o Industrial Suppliers: – Hamamatsu, Japan: • supplying photon detectors Edinburgh, 18. 11. 2016 Stephan Eisenhardt 10

rt. w ge 15 n a ch 06/20 o n ort rep Quality Assurance

rt. w ge 15 n a ch 06/20 o n ort rep Quality Assurance Program o Developed an Integrated Quality assurance Programme, comprising: – – o readout electronics photon detectors assembly installation & commissioning p Involving collaborating institutes: – UK: Edinburgh, Cambridge – Italy: Ferrara, Padova, Milano, Genova – Poland: Krakow o sho k r wo h g ur. 2015 b n di 04 E. t 4 a &1 d. e 3 e 1 agr on With distributed responsibilities and shared workload – relevant for WP 1. 2 are: – Edinburgh will perform 50% of the QA tests on the photon detectors and assemble 50% of the Elementary Cells (detector modules) – Padova will test the other 50% of the photon detectors and Ferrara will assemble the other 50% of the Elementary Cells – Edinburgh leads the development of the photon detector QA test systems Edinburgh, 18. 11. 2016 Stephan Eisenhardt 11

rt. w ge 15 n a ch 06/20 o n ort rep Industry Front-end

rt. w ge 15 n a ch 06/20 o n ort rep Industry Front-end QA: Workflow / Logistics Hamamatsu X 1 X 2 X 3 X 4 X 5 R 11265 & R 12669 production Back Board production CLARO chip production FEB production EC mechanics production Base Board production * = outsourced Padova Ferrara Milano Krakow Genova Photon Detector QA CLARO QA* CLARO QA mech QA? FEB QA BB QA LHCb QA centres Edinburgh BB QA Cambridge EC Assembly EC QA EC Assembly: 2 x 2 R 11265 1 x 1 H 12699 EC Assembly + Digital Boards EC QA DB QA CERN? CERN + m-metal Assembly CERN EC Mounting on Columns Column Functionality Test shipments: by industry LHCb pit electronic components Commissioning Photon Detectors no shipment needed Edinburgh, 18. 11. 2016 Stephan Eisenhardt ECs CERN site to pit 12

rt. w ge 15 n a ch 06/20 o n ort rep Assembly and

rt. w ge 15 n a ch 06/20 o n ort rep Assembly and Commissioning at CERN Edinburgh, 18. 11. 2016 Stephan Eisenhardt 13