PRESENTATION TO PORTFOLIO COMMITTEE: Department of Local Government and Housing, North West Province: Third

PRESENTATION TO PORTFOLIO COMMITTEE: Department of Local Government and Housing, North West Province: Third Quarter Performance and Year to Date Mziwonke Dlabantu NHBRC: CEO

Table of Content • • • Mandate of organization Performance of the Province per

Table of Content • • • Mandate of organization Performance of the Province per District: Enrolment Performance of the Province per District: Inspection Performance of the Province: Technical Assessments Conclusion

Mandate of NHBRC VISION To be champion of the housing consumer MISSION To protect

Mandate of NHBRC VISION To be champion of the housing consumer MISSION To protect the housing consumers and to regulate the homebuilding environment MOTTO Assuring Quality homes STRATEGY – To ensure that housing consumers and homebuilders are educated on their rights and obligations – To entrench a culture of compliance through fair and efficient enforcement mechanisms – To research and introduce innovative products, methods and technologies within the homebuilding industry – To maintain a sustainable warranty fund.

Bojanala District: Enrolment of Homes Township / Project name Unique No Danie Estate-190 Reagile-100

Bojanala District: Enrolment of Homes Township / Project name Unique No Danie Estate-190 Reagile-100 Bokamoso-270 Bokamoso-365 Moema, Matlhwaela, Mocheko, Lekgolo -66 Dinie Estate - 300 Moretele Various -384 PELLA - 81 Tlokweng - 81 B 16120006/1 B 14070002 B 17050001 B 17050005/1 B 17050004/1 B 17060002 B 160400039/1 B 16040026/2 B 17090001 B 17100003 Units Programme enrolled 190 100 270 365 66 300 384 81 81 RURAL UISP RURAL RURAL

Bojanala District: Inspection of Homes

Bojanala District: Inspection of Homes

Dr Ruth S Mompathi: Enrolment of Homes Township / Project name Unique No Taung-119

Dr Ruth S Mompathi: Enrolment of Homes Township / Project name Unique No Taung-119 Glaudina-66 Tseoge- 340 Ipelegeng Ext 3 - 119 Ipelegeng Ext 5 - 93 Glaudina-500 Phaposane - 93 B 16110003 B 1501008 B 08030001 B 16040121 B 17080001 B 17050006 B 16040123/2 Units enrolled Programme 119 66 340 119 93 500 93 UISP RURAL UISP RURAL

Dr Ruth S Mompathi: Inspection of Homes

Dr Ruth S Mompathi: Inspection of Homes

Kenneth Kaunda: Enrolment of Homes Township / Project name Unique No Units enrolled Jouberton

Kenneth Kaunda: Enrolment of Homes Township / Project name Unique No Units enrolled Jouberton Ext 3 -40 Alabama Ext 4 - 951 Morena-80 Frisgewaagte- 80 Majeng - 80 Klein Soutpan- 150 Deelpan - 80 B 17050002 B 17040017/1 B 16040099/2 B 16040085/2 B 16040049/3 B 16040105 B 16040081/2 40 951 80 80 80 150 80 Programme UISP RURAL RURAL

Kenneth Kaunda: Inspection of Homes

Kenneth Kaunda: Inspection of Homes

Ngaka Molema: Enrolment of Homes Units enrolled Township / Project name Unique No Programme

Ngaka Molema: Enrolment of Homes Units enrolled Township / Project name Unique No Programme Khunwana-200 B 16040090/2 200 RURAL Agisanang-148 B 16020003 148 IRDP Borakalalo- 50 B 16040102 50 RURAL Mogopa- 125 B 15010018 125 RURAL Borothamadi Village- 50 B 16040102/2 50 RURAL Driefontein - 50 B 16040102/3 50 RURAL

Ngaka Molema: Inspection of Homes

Ngaka Molema: Inspection of Homes

Conclusion on Performance • All houses under construction are enrolled with the NHBRC. •

Conclusion on Performance • All houses under construction are enrolled with the NHBRC. • Monthly meetings between the Department and the NHBRC assist with project preparation. • The NHBRC has seconded a registered engineer to the Department to oversee project preparation before construction commences.

FORENSIC ENGINEERING ASSESSMENT MARANG PROJECT MAFIKENG

FORENSIC ENGINEERING ASSESSMENT MARANG PROJECT MAFIKENG

Project Background • • • Municipality: Mahikeng Project Name: Marang Estate Project was enrolled

Project Background • • • Municipality: Mahikeng Project Name: Marang Estate Project was enrolled with the NHBRC in 2014 Construction started in 2014. The NHBRC inspected all during construction In the mid-2014, the Department stopped the project By the time the Department stopped the project, a total of 612 out of 2400 housing units were constructed In June 2017, the Department approached the NHBRC to conduct structural assessment of houses already build The project was undertaken by NHBRC at the Department’s cost.

Project Objective • • To assess the quality of construction of 612 housing units

Project Objective • • To assess the quality of construction of 612 housing units To determine the extend of defects, if any To recommend any remedial where applicable To estimate cost of such remedial.

Assessment outcomes Block Construction stage Identified defects 1, 2, 8, 16, 17 Second floor

Assessment outcomes Block Construction stage Identified defects 1, 2, 8, 16, 17 Second floor • • • 3, 4, 5, 6, Roof top • • Cause of defects Recommended rectification Cracks on the floor screed Moisture and damage to walls Rusted column reinforcement Water ingress and wind • Cracks on the floor screed Moisture and damage to walls Rusted column reinforcement Roof slab not sealed Roof blown away Cracks on the floor screed Staircase bricks removed Water ingress and wind, vandalism • • • Demolish and rebuild walls and columns Remove and replace floor screed Demolish and rebuild staircase and roof Re-plaster all walls Remove and replace roof slabs

Assessment outcomes cont… Block Construction stage Identified defects 7, 9, 10, 11, 15 First

Assessment outcomes cont… Block Construction stage Identified defects 7, 9, 10, 11, 15 First floor • • 12, 13, 14, Ground • • • Cause of defects Recommended rectification Cracks on the floor screed Moisture and damage to walls Rusted column reinforcement Collapsed internal wall Water ingress and wind, vandalism • Cracks on the floor screed Moisture and damage to walls plaster Rusted column top reinforcement Water ingress and wind • Total estimated cost of rectification ( VAT incl. ) • • • R 11 703 678 Demolish and rebuild walls and columns Remove and replace floor screed Remove plaster and replaster Remove and replace rusted reinforcement Remove and replace floor screed

Conclusion • Apart from defects identified, the project has suffered vandalism. • The NHBRC

Conclusion • Apart from defects identified, the project has suffered vandalism. • The NHBRC has submitted report of the findings to the Department.