Auditors Report Michael Clonch

Auditors Report Michael Clonch

Introduction of HOA Board and Committee President – Patricia Buchanan Members Vice President –

Introduction of HOA Board and Committee President – Patricia Buchanan Members Vice President – Don Jones Secretary – Dawn Geda Treasurer – Chad Wrigglesworth Members at Large – Steven Juris, Harshad Golakia, Member at Large - Lana D’Amico (Retired) Architecture - Ray Rapuano, Jon Parker Landscape – Joe Cahill, (John Santori, Charles Harris retired) Nominating – Darlene Stone Finance – Jim Baucom, Kathy Stephens, Darlene, Don, Chad Documentation – Lora Popke, Kathy Broniak

2019 Project Considerations • Critical Improvements/Maintenance • Potential Liabilities/Risks • Costs

2019 Project Considerations • Critical Improvements/Maintenance • Potential Liabilities/Risks • Costs

Survey § Detailed Survey of Entire Property § Required for Decisions by HOA Affecting

Survey § Detailed Survey of Entire Property § Required for Decisions by HOA Affecting - Homeowners - Town of Morrisville - Duke Energy, - Savannah On - Trees - Drainage - Right of Way Etc

Survey Quotes/Status § Awarded to Gallivan Site Contractors - Award 4/9/19 - Start 4/26/19

Survey Quotes/Status § Awarded to Gallivan Site Contractors - Award 4/9/19 - Start 4/26/19 - Complete 4/29/19 § Other Vendors Quoted - Triangle Survey Service - Newcomb Land Surveyors - George Finch/Boney and Associates

Retaining Wall Repair (120 Rama Ct) ▶ Degradation of (at least) Two Tiers ▶

Retaining Wall Repair (120 Rama Ct) ▶ Degradation of (at least) Two Tiers ▶ Replace 6 X 6’s on First Two Tiers ▶ Potential 3 rd Tier must be Replaced ▶ - Evaluation After Removal of Initial Tiers ▶ Project Costs appropriated for 3 Tiers

Wall Vendors Quotes/Status § Awarded to Gallivan Site Contractors - Award 4/9/19 - Start

Wall Vendors Quotes/Status § Awarded to Gallivan Site Contractors - Award 4/9/19 - Start 4/17/19 - Complete 4/19/19 § Other Vendors Quoted - OCI - CTI

Catch Basins § Replacement of 2 Catch Basins § Seriously Degraded § Major Liability

Catch Basins § Replacement of 2 Catch Basins § Seriously Degraded § Major Liability due to Surrounding Ground § Adding “Stub Out” to Facilitate Future Drainage

Catch Basins Quotes/Status § Awarded to Gallivan Site Contractors - Award 4/9/19 - Start

Catch Basins Quotes/Status § Awarded to Gallivan Site Contractors - Award 4/9/19 - Start 4/22/19 - Complete 4/26/19 § Other Vendors Quoted - Pipeline - 5 Others Contacted – No Quotes Received

Pic?

Pic?

River Birch Root Removal § Potential Property Damage § Two Locations - 120 Rama

River Birch Root Removal § Potential Property Damage § Two Locations - 120 Rama Ct (At Retaining Wall Repair site) - 327 Millet

Root Removal Quotes/Status § Awarded to Leaf and Limb - Award 4/25/19 - Forecast

Root Removal Quotes/Status § Awarded to Leaf and Limb - Award 4/25/19 - Forecast Start - TBD - Forecast Complete - TBD § Other Vendors Quoted - Bartlett Tree Experts - Lloyd’s Tree Service

Entrance(s) § Improve the Visuals § Maintenance of Lighting § Determine Longer Term Efforts

Entrance(s) § Improve the Visuals § Maintenance of Lighting § Determine Longer Term Efforts

Entrance(s) § Dawn Geda bought Supplies and JUST DID IT!! THANK YOU Dawn!! And

Entrance(s) § Dawn Geda bought Supplies and JUST DID IT!! THANK YOU Dawn!! And Joe Cahill!! More Work to Come

Costs of Projects Awarded to Date § Total Cost - $ 9, 865 §

Costs of Projects Awarded to Date § Total Cost - $ 9, 865 § Funded through Reserves § Left in Reserves - $ 26, 207

Property Management Assessment Detailed Assessment of William Douglas Pros - Small, Simplified Structure, Personable

Property Management Assessment Detailed Assessment of William Douglas Pros - Small, Simplified Structure, Personable Cons ▶ Processes poorly defined and inflexible ▶ Poor and untimely communication ▶ Unresponsive, Lack of ownership, No follow up ▶ ▶ ▶ Hidden fees - charge for viewing our financial records in real time Unfamiliarity with HOA law/CPSF governing documents No proactive involvement in Issues or community Consensus – Does Not Meet Needs of CPSF

New Property Management Team Search Grand. Chester Meadows - David Robbins and Amy Boe

New Property Management Team Search Grand. Chester Meadows - David Robbins and Amy Boe Community Association Services - John and Jonathan Stone York Properties - More costly with less service - did not interview AMG - Declined to interview - unable to accommodate more properties at this time

New Property Management Team Decision Grand. Chester Meadows - David Robbins – Owner -

New Property Management Team Decision Grand. Chester Meadows - David Robbins – Owner - Amy Boe – Property Manager Key Decision Points - Emphasis on Customer Service/Communication - Years of Experience and Financial Expertise - Local, Family Owned and Familiar with CPSF - References Spoke Highly of GCM

2020 and Beyond Items to Consider § Overall Drainage Issues § Arborist/Tree Maintenance §