Norwegian Spirit Dry Dock Dates Jan 2 2020

  • Slides: 22
Download presentation

Norwegian Spirit Dry Dock • • Dates: Jan 2, 2020 – Feb 11, 2020

Norwegian Spirit Dry Dock • • Dates: Jan 2, 2020 – Feb 11, 2020 Location: Marseille, France

Working plan: Click here Click here Click here Description of works Page Deck 7:

Working plan: Click here Click here Click here Description of works Page Deck 7: Demolition of old teak. Deck preparation for Bolidt covering. 5 Deck 10 Aft: Demolition of concrete covering. 6 Deck 6 (Galley)/Deck 3 (Laundry): Demolition of old tile. 7 Deck 12/Main Pool: Demolition of old Bolidt covering. 8 Deck 12/Main Pool: Grinding of old paint. Preparation for applying new covering. 9 Demolition of teak wood from stairs on all open decks. Steel preparation works. 10 Deck 7: Grinding and cleaning of old painting 11 Deck 5/Lobby: Demolition of concrete floor and preparation works for new covering. Support for installing of new floor covering. 12 Deck 13: Grinding of metal construction. Applying of primer and new paint. 13 Deck 13: Preparation works for painting of new superstructure. Applying of primer and new paint. 14 Deck 7: Setting-up of tables in the Dining room. 15

Working plan: Click here Description of works Page Deck 10/Balconies: Preparation works before painting

Working plan: Click here Description of works Page Deck 10/Balconies: Preparation works before painting the balconies. 16 -18 Deck 7/Portside: Extension of ladder. Welding of new stairs. 19 Deck 10: Deck preparation and welding of foundation for new sculpture. 20 Deck 12/New SPA zone: Assistance with metal replacement. 21

Deck 7: Demolition of old teak. Deck preparation for installation of Bolidt covering Back

Deck 7: Demolition of old teak. Deck preparation for installation of Bolidt covering Back to working plan 5

Deck 10/Aft: Demolition of concrete covering Back to working plan 6

Deck 10/Aft: Demolition of concrete covering Back to working plan 6

Deck 6 (Galley)/Deck 3 (Laundry): Demolition of old tile Back to working plan 7

Deck 6 (Galley)/Deck 3 (Laundry): Demolition of old tile Back to working plan 7

Deck 12/Main Pool: Demolition of old Bolidt covering. Back to working plan 8

Deck 12/Main Pool: Demolition of old Bolidt covering. Back to working plan 8

Deck 12/Main Pool: Grinding of old paint. Preparation for applying new covering Back to

Deck 12/Main Pool: Grinding of old paint. Preparation for applying new covering Back to working plan 9

Demolition of teak wood from stairs on all open decks. Steel preparation works Back

Demolition of teak wood from stairs on all open decks. Steel preparation works Back to working plan 10

Deck 7/Starboard and portside: Grinding and cleaning of old painting Back to working plan

Deck 7/Starboard and portside: Grinding and cleaning of old painting Back to working plan 11

Deck 5/Lobby: Demolition of concrete floor and preparation works for new covering. Support for

Deck 5/Lobby: Demolition of concrete floor and preparation works for new covering. Support for installing of new floor covering Back to working plan 12

Deck 13: Grinding of metal constructions. Applying of primer and new paint Back to

Deck 13: Grinding of metal constructions. Applying of primer and new paint Back to working plan 13

Deck 13: Preparation works for painting of new superstructure. Applying of primer and new

Deck 13: Preparation works for painting of new superstructure. Applying of primer and new paint Back to working plan 14

Deck 7: Setting-up of tables in the Dining room Back to working plan 15

Deck 7: Setting-up of tables in the Dining room Back to working plan 15

Deck 10/Balconies: Preparation works before painting the balconies Back to working plan 16

Deck 10/Balconies: Preparation works before painting the balconies Back to working plan 16

Deck 10/Balconies: Metal preparation works before painting the balconies Back to working plan 17

Deck 10/Balconies: Metal preparation works before painting the balconies Back to working plan 17

Deck 10: Cleaning and painting of balconies Back to working plan 18

Deck 10: Cleaning and painting of balconies Back to working plan 18

Deck 7/Portside: Extension of ladder. Welding of new stairs Back to working plan 19

Deck 7/Portside: Extension of ladder. Welding of new stairs Back to working plan 19

Deck 10: Deck preparation and welding of foundation for new sculpture Back to working

Deck 10: Deck preparation and welding of foundation for new sculpture Back to working plan 20

Deck 12/SPA zone: Assistance with metal replacement in the new superstructure Back to working

Deck 12/SPA zone: Assistance with metal replacement in the new superstructure Back to working plan 21

Always at your service CHESVA MARINE CONTRACTORS Our contacts: Cyprus office Anrea Araouzou Str.

Always at your service CHESVA MARINE CONTRACTORS Our contacts: Cyprus office Anrea Araouzou Str. 2 Stephanos Plazza, Office 203 Kato Polemidia 4150 Limassol - Cyprus Mike Shyrokov - Managing director +35799469529 +380503953568 Denys Shyrokov – Logistics +357 99460405 Julia Exinta – Accountant +35799347279 Ukrainian office 5, Sadovaya Str. , Odessa, 65023, Ukraine E-mail: office@chesva. com. ua Elena Artemenko – Director +38(050)391 64 99 Nataly Kostenko – HR manager +38(050) 494 44 03 Kateryna Melnychuk – Senior manager +38(050) 391 64 97 Mariya Guivan - HR manager +38 (099) 021 45 78 Irina Zhenuntiy – Accountant +38(095) 283 56 61 Victoria Stepanchenko - HR manager +38 (099) 486 84 64 Olga Uzun – Logistics +38(050) 391 64 87 Anastasia Ivanova – Office manager +38 (048) 731 75 25