GANTT CHARTS SCHEDULES Chris Hammond P E Transportation

  • Slides: 11
Download presentation
GANTT CHARTS & SCHEDULES Chris Hammond, P. E. Transportation Department Manager, United Consulting August

GANTT CHARTS & SCHEDULES Chris Hammond, P. E. Transportation Department Manager, United Consulting August 27, 2014

Indiana Design Manual n IDM 104 -1. 03 (3) Utility Coordinator n #58. Prepare

Indiana Design Manual n IDM 104 -1. 03 (3) Utility Coordinator n #58. Prepare a Gantt chart for all utility relocation work that reflects the start time, finish time and duration for each independent section of the utility facility relocation work. Ensure the chart has information regarding the geographical direction (east to west) the utilities are operating.

When should we do Schedules? n Schedules now need completed at 3 points in

When should we do Schedules? n Schedules now need completed at 3 points in time: n n n Preliminary Stage: At/During PFC Meeting, to estimate how long Relocations will take…. could affect Letting Prior to Work Plan Approved Stage To be sure there is proper summation of Utilities’ Relocations…. could affect Contractor Start Date Construction Stage Based on actual progress made by each Relocating Utility…. could lead to Contractor “delay” claim

Types of Schedules n n INDOT now requires a visual Schedule, such as “Gantt

Types of Schedules n n INDOT now requires a visual Schedule, such as “Gantt Project” n http: //www. ganttproject. biz/ n Free, public domain software You may use other programs: MS Project Schedule n Excel spreadsheet n Others acceptable (key is visual) n Keep them as simple and practical as possible n

Gantt Charts n Remember these from College? n Various types of Schedules Bar Charts

Gantt Charts n Remember these from College? n Various types of Schedules Bar Charts (low complexity) n CPM (high complexity) n Gantt Charts (mid-level complexity) n

Gantt Charts n Advantages n n n Multiple work elements/tasks Tracks “Start” and “Finish”

Gantt Charts n Advantages n n n Multiple work elements/tasks Tracks “Start” and “Finish” Dates Shows Durations Obvious interconnection/Relationships Visual easy to understand/interpret

Utility Schedule n So why is INDOT requiring it? n n n To determine

Utility Schedule n So why is INDOT requiring it? n n n To determine IF construction can be DONE: n without conflicts with Utilities n simultaneous with Relocations To avoid overlaps BETWEEN: n Utilities’ Schedules vs. Contractor’s n various Utilities’ Relocation Schedules To help: n Utilities be aware & coordinate amongst selves n Identify “under-builds” on Aerial Electric lines n Facilitate preceding activities, even Pre-construction (acquire R/W, stake R/W, clear Trees, etc. )

Utility Schedule n So what inputs are needed? n n n n Preconstruction schedules

Utility Schedule n So what inputs are needed? n n n n Preconstruction schedules of each Utility Relocation schedules of each Utility R/W Clear and R/W Staked Dates Direction each Utility plans to proceed “Target Date” Contractor wants Utilities moved Engineer’s MOT Schedule Engineer’s Phasing/Sequencing of CX Contractor’s overall Schedule

Example Gantt Chart

Example Gantt Chart

Example Conflict from Gantt Chart

Example Conflict from Gantt Chart

Conclusion n Why do a Gantt Chart? n n n Required by IDM 104

Conclusion n Why do a Gantt Chart? n n n Required by IDM 104 -1. 03, Item #58 Presents all Schedule conflicts visually Shared easily w/ P. M. , Utilities, & Area Eng. Substantiates the completed “Work Plans” Reinforces the submitted “Utility Spec. ” Aids in avoiding costly Delays— citizens of Indiana PAY either way