ELENA Project Installation followup 1 Erwan Harrouch ENMEF

  • Slides: 13
Download presentation
ELENA Project Installation follow-up 1 Erwan Harrouch EN-MEF December 7, 2020

ELENA Project Installation follow-up 1 Erwan Harrouch EN-MEF December 7, 2020

Cable identification for the TL installation � Situation : Very tight schedule for the

Cable identification for the TL installation � Situation : Very tight schedule for the TL installation. (~9 month with very small margin) � Cabling activities : � � 2 3 months of decabling / 2 month of cabling Erwan Harrouch EN-MEF December 7, 2020

Cable identification for the TL installation Proposition : Identification and labeling of all the

Cable identification for the TL installation Proposition : Identification and labeling of all the cables concerned by the de-cabling campaign By who : Equipment owner When : March 2016 Goal : Save time during the transfer line installation and allow EN-EL to prepare the campaign 3 CODE DESCRIPTION B. . A BEAM OBSERVATION (AD) BCTC TRANSFO DE COURANT (AD) BL. A BEAM OBS. MONITORS (AA) BRPA BEAM OBS PU PATCH-PANEL BRSC ? ANCIEN CODE ANNULE BTVA BTV (AD) BWCA CHAMBRES A FILS (AD) CV. A TV MACHINE AD ER. M BT RESEAU CONVERTISSEUR M. . A AIMANTS (AA) MMDA INTERLOCKS AIMANTS (AD) MP. A ALIM AIMANT (AD) R. . A POWER SUPPLIES (AA) RC. P CONTROLE ALIMENTATION (AD) TBSA BEAM STOPPER (AD) VG. A JAUGES VIDES (AD) VP. A POMPES VIDES (AD) VRSA SUBLIMATEURS (AD) VV. A VANNES VACUUM (AD) XASA AD/LIGNE EXPERIENCE ASACUSA YA. A SECURITE ACCES (AD) Erwan Harrouch EN-MEF December 7, 2020

Worksite follow-up � Mechanical support installation � Sealing done (Drying on-going) � Alignment tables

Worksite follow-up � Mechanical support installation � Sealing done (Drying on-going) � Alignment tables installed : 6/6 sectors done! LNI tables remain to be installed � BTV Support delivered, status of the kicker support to be clarified? 4 Erwan Harrouch EN-MEF December 7, 2020

Worksite follow-up � Source re-installation � The gaz panel is relocated. Are the pipes

Worksite follow-up � Source re-installation � The gaz panel is relocated. Are the pipes cut high enough? � Metallic plate cut � Meeting at 3. 30 with EN-CV to arrange the supporting of the pipe 5 Erwan Harrouch EN-MEF December 7, 2020

Worksite follow-up � � � Reception of the cables on-going 75% done without major

Worksite follow-up � � � Reception of the cables on-going 75% done without major issue Next campaign in February for DC cables and Remaining control cables (~300) Cable to AD pulled, reception done 6 Erwan Harrouch EN-MEF December 7, 2020

Worksite follow-up � Optic fiber installation on-going � � � Panel relocated VIC done

Worksite follow-up � Optic fiber installation on-going � � � Panel relocated VIC done to pull the optic fiber from the power room (work planned for week 4) LV installation and IT Installation : � � � IT works : completed? LV Works completed : Tests to be done Start of installation of the power sockets in two weeks � 7 First step : Prototyping and marking of the position Erwan Harrouch EN-MEF December 7, 2020

Worksite follow-up � SMB-SE works � � Side platform being modified Reinstallation by next

Worksite follow-up � SMB-SE works � � Side platform being modified Reinstallation by next week Modification of the false floor by next week Support of the Btrain magnet : To be done before the 15 th of February Courtesy to O. Choisnet 8 Erwan Harrouch EN-MEF December 7, 2020

Closure of the shielding wall Modification of the opening for the vacuum chamber (delivery

Closure of the shielding wall Modification of the opening for the vacuum chamber (delivery date : 1/3/2016) Marking of the vacuum chamber foreseen by the end of the week to give the greenlight for closure 9 Erwan Harrouch EN-MEF December 7, 2020

MGNLG and MQNAF installation postponed to February LNI Installation update 10 December 7, 2020

MGNLG and MQNAF installation postponed to February LNI Installation update 10 December 7, 2020 Vacuum sector ready on the 14/03 - 1 week of margin (No changes)

Gbar bunker installation • Delivery of the LEP Yoke will start on the 18/01/2016?

Gbar bunker installation • Delivery of the LEP Yoke will start on the 18/01/2016? • Order of the standard block is being completed • Marking of the bunker will start next week 11 Erwan Harrouch EN-MEF December 7, 2020

Summary of next week � LV Installation (R. Necca) � Prototyping and ground marking

Summary of next week � LV Installation (R. Necca) � Prototyping and ground marking for the ring power sockets � Mechanical support installation (A. Kolehmainen) � Alignment tables installation for LNI � LNI installation (E. Harrouch) � Closing of the shielding � Gbar bunker installation � Cleaning of the area (E. Harrouch) � Ground marking of the bunker (T. Dobers) � Source Installation (A. Megia) � Completion 12 of the source installation Erwan Harrouch EN-MEF December 7, 2020

Planning update � TE-EPC (Date are being checked) � � LNI planning is now

Planning update � TE-EPC (Date are being checked) � � LNI planning is now in line with the magnet delivery schedule TE-ABT � � � Installation date of ELENA BTV is not defined yet (delay expected) Tune installation, date of installation not completely clear yet. Set to the 1 st of April (at the latest estimation) Delay on the delivery of the BPM expected (Impact on the schedule to be studied) TE-MSC � � � CV installation in the power room is postponed to the 15 of February BE-BI � � Fast deflectors installation postponed to the 08/02 Doublet+SEM installation strategy needs to be defined EN-CV � � HV power converters installation is postponed to the 1/6/2015 Installation of the software for 1/6/2015 Magnet installation sequence is updated for January Installation schedule of the Correctors magnets needs a close look General � � 13 The installation strategy of equipment under vacuum need to be studied The hardware tests need to be integrated to the planning Erwan Harrouch EN-MEF December 7, 2020