ELENA Project Installation followup 1 Erwan Harrouch ENMEF
- Slides: 13
ELENA Project Installation follow-up 1 Erwan Harrouch EN-MEF December 7, 2020
Cable identification for the TL installation � Situation : Very tight schedule for the TL installation. (~9 month with very small margin) � Cabling activities : � � 2 3 months of decabling / 2 month of cabling Erwan Harrouch EN-MEF December 7, 2020
Cable identification for the TL installation Proposition : Identification and labeling of all the cables concerned by the de-cabling campaign By who : Equipment owner When : March 2016 Goal : Save time during the transfer line installation and allow EN-EL to prepare the campaign 3 CODE DESCRIPTION B. . A BEAM OBSERVATION (AD) BCTC TRANSFO DE COURANT (AD) BL. A BEAM OBS. MONITORS (AA) BRPA BEAM OBS PU PATCH-PANEL BRSC ? ANCIEN CODE ANNULE BTVA BTV (AD) BWCA CHAMBRES A FILS (AD) CV. A TV MACHINE AD ER. M BT RESEAU CONVERTISSEUR M. . A AIMANTS (AA) MMDA INTERLOCKS AIMANTS (AD) MP. A ALIM AIMANT (AD) R. . A POWER SUPPLIES (AA) RC. P CONTROLE ALIMENTATION (AD) TBSA BEAM STOPPER (AD) VG. A JAUGES VIDES (AD) VP. A POMPES VIDES (AD) VRSA SUBLIMATEURS (AD) VV. A VANNES VACUUM (AD) XASA AD/LIGNE EXPERIENCE ASACUSA YA. A SECURITE ACCES (AD) Erwan Harrouch EN-MEF December 7, 2020
Worksite follow-up � Mechanical support installation � Sealing done (Drying on-going) � Alignment tables installed : 6/6 sectors done! LNI tables remain to be installed � BTV Support delivered, status of the kicker support to be clarified? 4 Erwan Harrouch EN-MEF December 7, 2020
Worksite follow-up � Source re-installation � The gaz panel is relocated. Are the pipes cut high enough? � Metallic plate cut � Meeting at 3. 30 with EN-CV to arrange the supporting of the pipe 5 Erwan Harrouch EN-MEF December 7, 2020
Worksite follow-up � � � Reception of the cables on-going 75% done without major issue Next campaign in February for DC cables and Remaining control cables (~300) Cable to AD pulled, reception done 6 Erwan Harrouch EN-MEF December 7, 2020
Worksite follow-up � Optic fiber installation on-going � � � Panel relocated VIC done to pull the optic fiber from the power room (work planned for week 4) LV installation and IT Installation : � � � IT works : completed? LV Works completed : Tests to be done Start of installation of the power sockets in two weeks � 7 First step : Prototyping and marking of the position Erwan Harrouch EN-MEF December 7, 2020
Worksite follow-up � SMB-SE works � � Side platform being modified Reinstallation by next week Modification of the false floor by next week Support of the Btrain magnet : To be done before the 15 th of February Courtesy to O. Choisnet 8 Erwan Harrouch EN-MEF December 7, 2020
Closure of the shielding wall Modification of the opening for the vacuum chamber (delivery date : 1/3/2016) Marking of the vacuum chamber foreseen by the end of the week to give the greenlight for closure 9 Erwan Harrouch EN-MEF December 7, 2020
MGNLG and MQNAF installation postponed to February LNI Installation update 10 December 7, 2020 Vacuum sector ready on the 14/03 - 1 week of margin (No changes)
Gbar bunker installation • Delivery of the LEP Yoke will start on the 18/01/2016? • Order of the standard block is being completed • Marking of the bunker will start next week 11 Erwan Harrouch EN-MEF December 7, 2020
Summary of next week � LV Installation (R. Necca) � Prototyping and ground marking for the ring power sockets � Mechanical support installation (A. Kolehmainen) � Alignment tables installation for LNI � LNI installation (E. Harrouch) � Closing of the shielding � Gbar bunker installation � Cleaning of the area (E. Harrouch) � Ground marking of the bunker (T. Dobers) � Source Installation (A. Megia) � Completion 12 of the source installation Erwan Harrouch EN-MEF December 7, 2020
Planning update � TE-EPC (Date are being checked) � � LNI planning is now in line with the magnet delivery schedule TE-ABT � � � Installation date of ELENA BTV is not defined yet (delay expected) Tune installation, date of installation not completely clear yet. Set to the 1 st of April (at the latest estimation) Delay on the delivery of the BPM expected (Impact on the schedule to be studied) TE-MSC � � � CV installation in the power room is postponed to the 15 of February BE-BI � � Fast deflectors installation postponed to the 08/02 Doublet+SEM installation strategy needs to be defined EN-CV � � HV power converters installation is postponed to the 1/6/2015 Installation of the software for 1/6/2015 Magnet installation sequence is updated for January Installation schedule of the Correctors magnets needs a close look General � � 13 The installation strategy of equipment under vacuum need to be studied The hardware tests need to be integrated to the planning Erwan Harrouch EN-MEF December 7, 2020
- Ignacio harrouch
- Followup edge
- Followup:actionitems
- Follow-up visits
- Noi vs ebitda
- Zidi erwan
- Dr erwan zidi
- Erwan trehiou
- Windchill bulk migrator installation and usage guide
- Cleaning tru count air clutches
- Wire and cable manufacturers alliance
- Tema configuration
- Technisonic avionics installation
- Solar company summit county