Lessons learnt during Front End preparation and installation
- Slides: 22
Lessons learnt during Front End preparation and installation William Ledda Control System Integrator (ICS) on behalf of Thomas Shea (Beam Diagnostic Section Leader) www. europeanspallationsource. se 2018 -04 -06
Outline • • • Overview Organization & coordination Technical challenges Lessons learnt Conclusions 3
Overview • The "Injection system" – Ion source produce the beam – LEBT "transports" the beam till the RFQ for the first stage of acceleration • The "Control system" • – Infrastructure (HW and SW) that make it possible provide required data, information and services to engineers, operators, physicists and the facility itself. The "Integrated Control System Division (ICS)" – responsible of defining and providing control systems services for the entire ESS facility (accelerator, target, neutron scattering instruments and conventional facilities) 4
Outline • • • Overview Organization & coordination Technical challenges Lessons learnt Conclusions 5
Organization & Coordination Distributed team ESS INFN-LNS In-kind contributor for the ISRC & LEBT CEA In-kind contributor for the control system ESS ICS Division ACC Division INFN-LNS 6
Organization & Coordination Distributed team • Relations between the teams are very good, there are bonds between the different team members. • Communications, either through phone, videoconference or in person. • Frequent travels in Catania during for the installation, set-up and testing and acceptance of the system. 7
Organization & Coordination Distributed Development 8
Outline • • • Overview Organization & coordination Technical challenges Lessons learnt Conclusions 9
Technical challenges Device integration • Many different devices to be integrated (PLCs, Field devices, Power Supplies etc. ) • Different interfaces and protocols (Serial vs Ethernet, Modbus, SCPI, GPIB, Step 7, Ether. CAT, etc. ) • The “glue” that makes all these devices to communicate each other is the EPICS framework (Experimental Physics and Industrial Control System) adopted as standard by ICS – ~ 10 IOCs running – ~ 9500 EPICS PVs 10
Ion Source Controls Architecture Archiving PC Vacuum System 11 Server Scalance X 204 -2 (0) Source IPC Source PLC 4 Scalance X 212 -2 (1) Scalance X 204 -2 (2) CAT 5 Ethernet (10. 0. xxx, Channel Acces, boot, nfs, …) Serial, etc. CAT 5 Ethernet (10. 1. xxx) Fibre Electrical, etc. (physical I/O, power, etc. ) 5 Source Ether. CAT I/O 8 1 3 CU 1561 Scalance X 204 -2 (3) SCPI Repeller Electrodes PS (x 2) 2 Scalance X 212 -2 (4) 10 Scalance X 204 -2 (5) Modbus TCP 9 Modbus TCP Scalance X 212 -2 (6) Source I/O Controller ACQ Source Ether. CAT I/O Serial Server SCPI Profinet SCPI HV PS CU 1561 Magnetron ATU ASCII Mass Flow & Gauge Controller Source Coils PS (x 3) Source PLC Remote I/O HV Platform Controls Equipment (PLC, IPC, I/O, etc. ) LINAC Equipment (PS, etc. )
Serial, etc. LEBT Controls Architecture CAT 5 Ethernet Fibre ASCII 5 9 NPM MC 8 Electrical, etc. (physical I/O, power, etc. ) To Source PLC DSM IPC To Source PLC IRIS NPM To Source CB EVR DSM Spectrometer FC Chopper Camera FC Bias PS DSM BCM EMU To Isrc VME Control Box SCPI 2 SCPI 10 4 EMU Plate PS (x 2) ASCII EMU Ether. CAT I/O BCM I/O Controller EMU Bias PS Solenoid PS (x 2) Steerer PS (x 4) EMU MC 3 EMU I/O Controller EMU PLC s 7 plc ACQ To Isrc VME Control Box ASCII IRIS MC BCT RTM Interface Unit ACQ NPM IPC 1 EMU IPC Future Controls Equipment (PLC, IPC, I/O, etc. ) LINAC Equipment (PS, etc. )
Technical challenges Control GUI • Simplified GUI for the operator to have everything under control
Technical challenges Compromises • ICS Integration strategy tailored and adapted to the situation. – Processes and procedures not fully in place when ISRC&LEBT started – Calendar pressure advised to keep moving forward – Expertise of teams involved allowed to mitigate potential risks • EPICS v 3 instead of v 4 used for stability at the time. • Timing system deployed not the final one but required to run the machine. • Machine modes not defined, controls implementation left open to deploy them in the future. • VME architecture was used instead of µTCA. • Geobrick instead of Ether. CAT for motion control • Local Protection System includes also Safety functions required to operate the machine safely.
Technical challenges Achievements • ISRC & LEBT is a reality!!!! – ISRC Control system accepted in July 2017 – LEBT Control system accepted in September 2017 • All EPICS modules under control version, tested, documented. • All equipment are integrated in the control system.
Outline • • • Overview Organization & coordination Technical challenges Lessons learnt Conclusions 16
Lessons General • Structure, methodologies, processes and standards non fully defined since the beginning. • ISRC & LEBT seen as "test stand" more than a final system – Some systems need to be updated. • From VME to µTCA • Timing system • Motion control (Geobrick -> Ether. CAT) • Compression in time schedule led to take fast decisions on the fly – This require a structure inspired to the "agile" thinking. • Sometimes lack of communication between all parties – "Who is doing what? ", misunderstanding, delays, late deliveries. • Documentation is "spread" and sometimes not fully updated. • Some systems integrated but not fully tested in operational conditions.
Lessons Organization and coordination • The "human" factor cannot be underestimated: – A team spread between different countries is a challenge in terms of organization, and it can be very time consuming. – Different teams have different views and expectations. – Side by side work is very useful to keep good relations, to solve issues and to take decisions. • We have always to keep in mind how efficient the communication is - Are the meetings efficient and solve problems? - Do we need to have in regular meetings are they useful to improve the system understanding and speed up the process? - What things do we discuss when we have a crisis? Do we prioritize properly? • Even the strongest team player have a tendency to communicate less or try to solve problems on their own. 18
Lessons Installation • The installation should be seen as for the whole system, not my part and then your part. • The installation involves a huge number of decisions that should not be underestimated in terms of time. • First time a real system installation is happening in ESS and there are many things still to learn from. • Good communication between all parties involved is essential to drive the installation in the right way. 19
Lessons Continuous Improvement Example of continuous improvement through lessons learned Experience: • Beam-induced damage of the Emittance Measurement Unit Analysis: • Delays led to aggressive commissioning schedule and ad-hoc activities • System operated without complete verification Improvement: • Schedule - Include explicit float Molten tungsten - Emittance Measurement Unit • Conduct of operations – • Avoid ad-hoc interlock management • Measure ”safe” beam prior to increasing duty factor 20
Outline • • • Overview Organization & coordination Technical challenges Lessons learnt Conclusions 21
Conclusions • ISRC & LEBT are the first "big" achievements for ESS, result of a strong collaboration of different teams. • We have had issues, of course! We have to extract many good lessons from them in order to avoid the same mistakes. • ISRC & LEBT are the starting point from which ESS can improve methodology, structure, process and knowledge. • The synergy between all parties is essential to avoid decision has to be reconsidered after. • Documentation is important but also the communication between all stakeholders is essential in all phases of the project. 22
Questions? Thank you!
- Explain compiler construction tools
- Front end compiler
- End fed zepp
- Occluded front gif
- Dead front vs live front transformer
- Cover page of school magazine
- Front-end rounding
- Front end rounding decimals
- Rf front end receiver design
- Front end loading fel
- Interdash board
- Idscenter
- Fuzzy front end
- Front end schedule
- Front end inspection
- Front end stage
- What have we learnt from the story?
- What have we learnt from the story
- What have we learnt from the story?
- What have learnt from the story
- What have learnt from the story
- Go kiss the world mcq questions
- A gift of chappals ppt