Lessons learned from Cultana Pumped Hydro Project EIANZ

  • Slides: 20
Download presentation
Lessons learned from Cultana Pumped Hydro Project EIANZ Annual Conference, 4 -6 November 2019

Lessons learned from Cultana Pumped Hydro Project EIANZ Annual Conference, 4 -6 November 2019

Lessons learned from Cultana Pumped Hydro Project • Challenge of Australia’s changing National Electricity

Lessons learned from Cultana Pumped Hydro Project • Challenge of Australia’s changing National Electricity Market • Introduction to pumped hydro energy storage - Australian site options • Cultana Pumped Hydro Project – overview and impact assessment • Key lessons learned - To progress Cultana Pumped Hydro Project - For future pumped hydro projects - For environmental impact assessment 2

Challenge of Australia’s changing National Electricity Market Forecast National Electricity Market generation capacity Source:

Challenge of Australia’s changing National Electricity Market Forecast National Electricity Market generation capacity Source: AEMO, 2019 ISP Insights Development Plan, Neutral Scenario 3

Challenge of Australia’s changing National Electricity Market Forecast coal generator closures – more rapid

Challenge of Australia’s changing National Electricity Market Forecast coal generator closures – more rapid than previous forecasts Source: AEMO, 2019 ISP Preliminary Outcomes Presentation 4

Challenge of Australia’s changing National Electricity Market Levelized cost of electricity from various energy

Challenge of Australia’s changing National Electricity Market Levelized cost of electricity from various energy storage technologies Source: James and Hayward, CSIRO, 2013) 5

Introduction to pumped hydro energy storage Role of pumped hydro energy storage Source: Hyrdo

Introduction to pumped hydro energy storage Role of pumped hydro energy storage Source: Hyrdo Tas, April 2018 6

Introduction to pumped hydro energy storage 7

Introduction to pumped hydro energy storage 7

Introduction to pumped hydro energy storage Shoalhaven Scheme, Bendeela Pondage Source: Eraring Energy Yanbaru

Introduction to pumped hydro energy storage Shoalhaven Scheme, Bendeela Pondage Source: Eraring Energy Yanbaru seawater pumped hydro plan, Japan Source: Renew Economy, 2013 Tumut-3 power station, Snowy Mountains Source: Eco. Generation, 2012 8

Introduction to pumped hydro energy storage • In 2014, Melbourne Energy Institute and Arup

Introduction to pumped hydro energy storage • In 2014, Melbourne Energy Institute and Arup applied site criteria to southern coastline: - Large elevation difference between reservoirs - Proximity between reservoirs to limit piping - Terrain to minimise reservoir construction costs - Proximity to high voltage transmission grid - Land access availability - Minimal environmental and social impacts - Access to the required volume of water - Favourable geology - Low risk of surface and groundwater impacts 9

Overview of Cultana Pumped Hydro Project Source: Arup, 2019 10

Overview of Cultana Pumped Hydro Project Source: Arup, 2019 10

Overview of Cultana Pumped Hydro Project • • 225 MW generating capacity Min 1,

Overview of Cultana Pumped Hydro Project • • 225 MW generating capacity Min 1, 800 MWh generation over 8 hours Max 10 hour pumping cycle to full charge 230 -315 MW pumping capability 2 Reversible Francis Pump Turbine Uses desalinated Spencer Gulf water Round trip efficiency 75% Source: Arup, 2019 11

Overview of Cultana Pumped Hydro Project Source: Arup, 2019 12

Overview of Cultana Pumped Hydro Project Source: Arup, 2019 12

Impact Assessment – Cultana Pumped Hydro Project Environmental risk assessment • Project used an

Impact Assessment – Cultana Pumped Hydro Project Environmental risk assessment • Project used an activity-based semi-quantitative environmental risk assessment to analyse risk. This was collaboratively workshopped with the project team and specialist technical advisors • This process highlight that pumped hydro is essentially a novel application of conventional technology and construction techniques • This allowed risk to be readily analysed and project activities to be proactively planned to avoid, minimise and manage potential adverse impacts 13

Impact Assessment – Cultana Pumped Hydro Project Key environmental risks – terrestrial site: •

Impact Assessment – Cultana Pumped Hydro Project Key environmental risks – terrestrial site: • Aboriginal heritage - Potential impact to heritage sites and culturally sensitive landforms - Response – engaging with the Barngarla Determination Aboriginal Corporation to assess and manage potential cultural heritage impacts, and address Native Title requirements • Human hazard and risk - Potential for flood risk from dam break - Response – project assessed in accordance with long-established ANCOLD guidelines for design, operation and maintenance of water storage facilities 14

Impact Assessment – Cultana Pumped Hydro Project Key environmental risks – terrestrial site (cont’d):

Impact Assessment – Cultana Pumped Hydro Project Key environmental risks – terrestrial site (cont’d): • Land use and planning - Potential land use impacts that compromise Defence capability during construction or operation - Response – engaging with Department of Defence to ensure land access agreement appropriately manages current and future land use requirements • Spoil management - Potential impacts from large volumes of material during construction - Response – Contractual requirement to manage spoil in accordance with the South Australian Guideline for stockpile management 15

Impact Assessment – Cultana Pumped Hydro Project Key environmental risks – coastal and marine

Impact Assessment – Cultana Pumped Hydro Project Key environmental risks – coastal and marine site: • Ecology - Potential impact to species during operation from intake of seawater and saline discharge to Spencer Gulf - Response – modelling of intake and discharge informed design to avoid impacts, such as limiting velocity and screens for entrainment, and dispersion of plume for mixing zone • Land use and planning - Potential impacts on coastal and marine uses and zoning - Response – engaging with local community on recreational uses and opportunities to potentially leverage project infrastructure 16

Impact Assessment – Cultana Pumped Hydro Project Statutory approvals process: • Characterising pumped hydro

Impact Assessment – Cultana Pumped Hydro Project Statutory approvals process: • Characterising pumped hydro – not strictly a renewable energy under land use planning • Jurisdictional challenges - Project is largely on Commonwealth land, however area is still regulated by South Australian planning requirements - Area not covered by Bilateral Agreement – project is undertaking separate Commonwealth and South Australian approvals with no one-off accreditation • Extensive stakeholder and community engagement - Continue to engage with Department of Defence, Barngarla Determination Aboriginal Corporation and Port Augusta Council - Community consultations have also taken place to understand views on the project 17

Lessons learned from Cultana Pumped Hydro Project is progressing toward Financial Investment Decision: •

Lessons learned from Cultana Pumped Hydro Project is progressing toward Financial Investment Decision: • Public display of separate Commonwealth and South Australian statutory approvals • Land agreement with Department of Defence • Agreement with the Bangarla people For future pumped hydro projects: • Decarbonising the Australian Electricity Market requires around 450 GW of storage • Recent ANU research, led by Prof Blakers, identified up to 22, 000 potential pumped hydro sites in Australia, with only a fraction required to support 100% renewable electricity • Lessons learned from projects such as Cultana should inform next generation of pumped hydro projects – we need to revise site selection models to help identify more projects 18

Lessons learned from Cultana Pumped Hydro Project For environmental practitioners: • Risk assessment -

Lessons learned from Cultana Pumped Hydro Project For environmental practitioners: • Risk assessment - Pumped hydro is a novel application of conventional technology and construction - Presents challenges to how we conceptualise environmental impact assessment • Statutory approvals - As we decarbonise, there is a significant future pipeline of pumped hydro projects - As practitioners we need to improve how these projects are addressed by statutory approvals processes to facilitate appropriate development – opportunities for strategic assessment or preferential ‘Green Door’ approval processes (this might be ‘green tape’ worth cutting) 19

Lessons learned from Cultana Pumped Hydro Project • Thank you • Questions? 20

Lessons learned from Cultana Pumped Hydro Project • Thank you • Questions? 20