Ground Improvement Project Large water storage tanks Carrington

  • Slides: 29
Download presentation
Ground Improvement Project – Large water storage tanks Carrington NSW Douglas Partners’ Technical Seminar

Ground Improvement Project – Large water storage tanks Carrington NSW Douglas Partners’ Technical Seminar 2019 Scott Mc. Farlane & Richard Merifield

Background • Douglas Partners are a trusted consultant to PWCS; • PWCS needed to

Background • Douglas Partners are a trusted consultant to PWCS; • PWCS needed to upgrade their stormwater management system; • PWCS engaged GHD as the design consultant (civil, hydraulic, mechanical, electrical & geotechnical); • PWCS provided GHD previous nearby geotechnical data (by DP) to assist GHD with conceptual geotechnical ground improvement options for tank; • PWCS provided DP the concept geotechnical design options by GHD to develop scope of works (i. e. data report).

Stormwater Management System • Manage stormwater to minimise off-site uncontrolled discharge; • Above ground

Stormwater Management System • Manage stormwater to minimise off-site uncontrolled discharge; • Above ground steel tanks; • Supported on concrete slab; • Tank 1 – 20 m dia, 11 m high, 5 Ml; • Tank 2 – 32 m dia, 11 m high, 8 Ml; • Tank 3 – 32 m dia, 11 m high, 8 Ml; • Pipeline to connect into existing pond. Trench to be excavated adjacent to rail line.

Previous Data Fill Soft Clay VL Sand -0 Clay / Silt and Sand -10

Previous Data Fill Soft Clay VL Sand -0 Clay / Silt and Sand -10 Dense Sand Stiff Clay -20 Very Stiff to Hard Clay -30 -40 Rock

GHD Concept Ground Improvement Options Ground Improvement Option Do nothing Design Details - Estimated

GHD Concept Ground Improvement Options Ground Improvement Option Do nothing Design Details - Estimated Post Construction Settlement (mm) 700 Constraints Settlement Preload CFA piles Driven Piles Cutter Soil Mixing (CSM) 8 m high preload (3 month wait) 600 mm dia; Installed to >35 m, 3 m c/c 400 mm sq; Installed to >35 m, 2. 5 m c/c CSM to 35 m 15% area replacement ratio 5 to 10 With preload: 20 mm Without: 100 mm Depth of piles, ASS Depth of Piles 250 to 300 Space, time PWCS – very risk adverse with any ground improvement (past experience)

DP Difference

DP Difference

DP Revised Scope • Investigation – Provide data to GHD to undertake Design; •

DP Revised Scope • Investigation – Provide data to GHD to undertake Design; • Parallel modelling to compare with GHD design; • Review technical specification; • Review tenders methodology; • Review preferred tenderers design, QA and alternate design.

Investigation Geotechnical Risks • Soft clay layer? • Sand stratum? • Deeper clay? •

Investigation Geotechnical Risks • Soft clay layer? • Sand stratum? • Deeper clay? • Ground water? • Rock strength?

Subsurface Profile Tank 1 – 20 m dia Tank 2 – 32 m dia

Subsurface Profile Tank 1 – 20 m dia Tank 2 – 32 m dia

Design & Analysis

Design & Analysis

Tank Design Loads Design Life = 50 years

Tank Design Loads Design Life = 50 years

Serviceability Criteria • Max settlement at centre ≤ 100 mm; • Max settlement around

Serviceability Criteria • Max settlement at centre ≤ 100 mm; • Max settlement around perimeter ≤ 100 mm; • Max settlement between centre and edge ≤ 40 mm; • Max edge to edge tilt ≤ 30 mm; • Differential settlement ≤ 1 in 500.

Conceptual Time-Settlement Behaviour

Conceptual Time-Settlement Behaviour

Initial Ground Improvement Options • No Ground Improvement; • Piles with Pile Transfer Layer

Initial Ground Improvement Options • No Ground Improvement; • Piles with Pile Transfer Layer (PTL); • Deep Soil Mixing (GHD preference); • Tank Interaction (3 D analysis). Max Total Settlement: Case 1 – 71 300 80 mm 76 mm Case 2 – 53 225 mm 60 mm

Initial Tender Review – Mix Soil Option • Large QA component in design spec

Initial Tender Review – Mix Soil Option • Large QA component in design spec by GHD: • Sampling and lab mix design to determine strength properties; • Additional CPTs; • Trial sites (curing time); • Core sampling of mixed soil; • Lab testing during mixing; • Column Penetration Test or Pull-out resistance test. • 1 m preload.

Alternative Tender – Rigid Inclusions • Concrete Injected Columns (CIC); • Controlled Modulus Columns

Alternative Tender – Rigid Inclusions • Concrete Injected Columns (CIC); • Controlled Modulus Columns (CMC); • Controlled Stiffness Columns (CSC).

a) A “unit cell” axisymmetric model consisting of the CSC and its surrounding soils

a) A “unit cell” axisymmetric model consisting of the CSC and its surrounding soils was analysed; b) Based on the results from a), an equivalent set of soil properties was generated; c) Using the result from b), a larger model was generated. Plaxis 2 D Unit Cell Model of CSC

Plaxis 2 D axisymmetric model (half model) with equivalent composite CSC/Soil Zone

Plaxis 2 D axisymmetric model (half model) with equivalent composite CSC/Soil Zone

Tank Total Settlement mm Sustained Constant Load – 120 k. Pa Keller Prediction DP

Tank Total Settlement mm Sustained Constant Load – 120 k. Pa Keller Prediction DP Prediction Tank 1 (20 m dia) 74 62 Tank 2 (32 m dia) 86 71

QA During Construction • Proof rolling & Plate Load Testing rather than density testing

QA During Construction • Proof rolling & Plate Load Testing rather than density testing of working platform; • Additional CPTs; • Concrete testing (by others); • Review of concrete takes & penetration depths; • Plate load testing of installed columns (similar to pile test)

Plate Load Testing – Working Platform

Plate Load Testing – Working Platform

Installation of Trial Columns

Installation of Trial Columns

Installation of Trial Columns

Installation of Trial Columns

60 50 40 30 20 10 0 5/ Stats Range Average No. Metres per

60 50 40 30 20 10 0 5/ Stats Range Average No. Metres per day No. of Piles per Day 72 – 400 8 – 53 264 35 No of Piles per 450 400 350 300 250 200 150 100 50 0 18 /2 5/ 018 20 /2 5/ 018 22 /2 5/ 018 24 /2 5/ 018 26 /2 5/ 018 28 /2 5/ 018 30 /2 01 8 6/ 1/ 20 6/ 18 3/ 20 6/ 18 5/ 20 6/ 18 7/ 20 18 Number of Metres Production Rate of Columns

Column Load Testing (10 MPa – 7 days)

Column Load Testing (10 MPa – 7 days)

Pile Load (k. N) Typical Column Load Test Result 400 350 300 250 200

Pile Load (k. N) Typical Column Load Test Result 400 350 300 250 200 150 100 50 0 0 Column Diameter – 0. 4 m Column Depth – 7. 5 m 5 10 Deflection (mm) 15 20 Total No. of Column Tests – 9 Range of Max Deflection – 2. 1 to 28 mm

Thanks to All Involved with this Project 41. 75 310. 5 Ground Test Melbourne

Thanks to All Involved with this Project 41. 75 310. 5 Ground Test Melbourne Lab Newcastle Geo 487. 5 Newcastle Lab 66. 25