Welcome Update on ESS Construction Project Spectroscopy STAP

  • Slides: 11
Download presentation
Welcome Update on ESS Construction Project Spectroscopy STAP Meeting 13 th of April 2018

Welcome Update on ESS Construction Project Spectroscopy STAP Meeting 13 th of April 2018 Ken Andersen, Neutron Instruments Division, European Spallation Source ERIC

Welcome! • This is a test! – we are trying a video-conferencing format for

Welcome! • This is a test! – we are trying a video-conferencing format for some STAP meetings – two STAP meetings per year, synchronised with SAC meetings 2

Purpose and Remit of Instrument STAPs • Scientific and Technical Advisory Panels – one

Purpose and Remit of Instrument STAPs • Scientific and Technical Advisory Panels – one per instrument class • STAP: instrument advisory body – science case and functional requirements – all aspects which impact on scientific output of instrument (not just instrument project) – technical and project decisions – early science • Advice to both NSS management and instrument teams – collaborative & non-adversarial setting – NSS management & instrument teams take advice constructively – allows NSS management & instrument teams to make good, informed decisions • Each STAP meeting results in written recommendations – followed up in subsequent meeting(s) – presented at following SAC meeting 3

Construction and Operations Budgets Construction Initial Operations Steady-State Operations 4

Construction and Operations Budgets Construction Initial Operations Steady-State Operations 4

Current Baseline Instrument Ramp-up Version 17/11/2017, based on Instrument Construction Working Schedule V 3.

Current Baseline Instrument Ramp-up Version 17/11/2017, based on Instrument Construction Working Schedule V 3. 4 Instrument 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 LOKI 5 MW 8 instruments in user programme ODIN NMX ESTIA 4 MW CSPEC DREAM SKADI BEER BIFROST 3 MW MAGIC T-REX HEIMDAL MIRACLES 2 MW VESPA FREIA Instrument 16 Instrument 17 1 MW Instrument 18 Instrument 19 Instrument 20 Instrument 21 Instrument 22 Construction Project Hot Commissioning 50 75 100% User Programme

Re-baselining in Progress • Delays to Conventional Facilities (CF) – changes imposed by Swedish

Re-baselining in Progress • Delays to Conventional Facilities (CF) – changes imposed by Swedish Radiation Protection Authority (SSM) on dealing with earthquake requirements – redesign of target and instrument buildings delaying CF construction by 1 -2 years • Timeline – – – – Preliminary dates communicated to instrument teams in December additional information on instrument installation provided integrated installation plan presented at IKON 14 13 -15/2 updated CF dates received early March instrument schedule integration workshop 8 th May SAC meeting 3 -4/5 external review 22 -24/5 Council meeting in June: new baseline approved 6

Science Directorate re-baseline proposal (based on CF building access dates of 5 th March)

Science Directorate re-baseline proposal (based on CF building access dates of 5 th March) A. Three user instruments be ready to start operation by end of 2023. Preferred First instruments to be: DREAM, ODIN & LOKI (+ Test Beam Line), B. First eight instruments ready to start operation by end of 2024. Add BEER, CSPEC, ESTIA, MAGIC & BIFROST to User Program C. All fifteen instruments ready to start operation by end of 2026. Add 7 more instruments to User Program over next two years Major schedule delays: Beam on Target Beam on 1 st Instrument Eight Instrument into User Program NSS project completion Preserved milestones: Start of user program (SOUP) in 2023 NSS project completion in 2025 = 21 months = 17 months = 16 months < 12 months (with zero float) (also with zero float). 7

First out-of-bunker access dates for Instrument Installation E 04 Dec 2019 1 Dec 2019

First out-of-bunker access dates for Instrument Installation E 04 Dec 2019 1 Dec 2019 Black = baseline dates from 2016 Jan 2020 15 Dec 2019 E 03 May 2019 Sep 2019 E 01 15 Aug 2019 (incl. crane E 01) E 02 (2) Nov 2019 March – Sept 2021 30 April 2021 Grey = estimation 30 th Jan 2018 (shown at IKON 14) RED = fixed dates 5 th March 2018 December 2019 Dec 2020 - May 2021 21 Dec 2020 (crane operational 28 Jan 2021) D 03 D 02 April 2020 D 01 February 2020 April –Sep 2021 (full D 01 same date range) 19 May 2021 (crane operational 16 June 2021) 8

 • Black = baseline dates from 2016 • Grey = estimation 30 th

• Black = baseline dates from 2016 • Grey = estimation 30 th Jan 2018 (shown at IKON 14) • RED = fixed dates 5 th March 2018 First in-bunker access dates for Instrument Installation 1. Start of joint work with Target in D 02 (R 6, NBOA & LS etc. ) Start of bunker work in D 01 & D 03 2. Start of first in-bunker access for Neutron Instrument construction D 03 Jun 2019 April - Oct 2020 26 Oct 2020 D 02 Feb 2019 Oct 2019 -March 2020 28 Feb 2020 D 01 Aug 2019 July 2020 – Jan 2021 17 Feb 2021 D 02 D 03 Dec 2019 June – Dec 2021 5 July 2021 D 01 Dec 2019 March – Sep 2021 31 Aug 2021 9

Proposed rebaseline schedule for NBI* Installation (TG 4 –> TG 5) (V 4. -1,

Proposed rebaseline schedule for NBI* Installation (TG 4 –> TG 5) (V 4. -1, 26 th March 2018) (based on CF building access dates of 5 th March) NSS access to E 01 Cave installation & fitout OOB Guides & shielding Beam on Target Start User Program (3 NBI*) 8 NBI* in User Program In bunker installation Cold commissioning 0. 00 West sector North sector NSS access to D 03 East and South sectors NSS access to D 01 2019 * NBI = Neutron Beam Instrument 2020 2021 2022 2023 2024 2025 10

Thank you! ESS site 2016 11 5 th June 2015

Thank you! ESS site 2016 11 5 th June 2015