PRDS Commissioning and Acceptance Procedure Dominik Sikora Preliminary

  • Slides: 8
Download presentation
PRDS Commissioning and Acceptance Procedure Dominik Sikora Preliminary Design Review 15. 03. 2017, Lund

PRDS Commissioning and Acceptance Procedure Dominik Sikora Preliminary Design Review 15. 03. 2017, Lund

Phase Drifts Verification Issue • Power levels and phase noise are easy to measure

Phase Drifts Verification Issue • Power levels and phase noise are easy to measure • Direct phase drift measurements are not possible – measuring equipment has to be much better than PRL performance – PRL is very long, measuring cables influence • Final phase drifts must be estimated indirectly basing on laboratory characterization 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 2

Laboratory Work • Rigid line characterization – phase drifts – insertion loss • Couplers

Laboratory Work • Rigid line characterization – phase drifts – insertion loss • Couplers characterization – phase drifts vs. coupling factor – Insertion loss vs. coupling factor • Tap Point characterization • Couplers assignment to specific location of PRL • Coupling factor set based on RF model 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 3

Pre-Commissioning Steps • Heating cables assembly – rigid lines – couplers with tap points

Pre-Commissioning Steps • Heating cables assembly – rigid lines – couplers with tap points • Functional tests of assembled heating cables before installation • Tests of each coupler section (rigid lines with one coupler) after installation – temperature control system functional tests (without final power cables) – transmission from line input to coupler output measurements – coupler adjustment if needed 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 4

Issue of the Ion-Source-to-MO PRL Branch • Measurement of PRL branch is more complicated

Issue of the Ion-Source-to-MO PRL Branch • Measurement of PRL branch is more complicated because installation is done in opposite direction to signal flow • Transmission of installed section changes after installation of following sections • RF model containing all transmissions in all installation steps is needed • Coupling adjustment should be considered after PRL branch installation 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 5

Commissioning Steps • MO amplifier stage commissioning – output power levels measurements – diagnostics

Commissioning Steps • MO amplifier stage commissioning – output power levels measurements – diagnostics verification • Temperature control system pre-commissioning – PRL warm up – functional tests with final power cables and Beckhof modules – temperature stabilization with final set-point • Pressure and humidity control system commissioning – filling slowly the rigid line with nitrogen and checking if PRL is leakages free – diagnostics checking • Temperature control system commissioning – Long term temperature tests during significant environment temperature changes 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 6

Acceptance Tests • Power levels measurements at all outputs – 352. 21 MHz and

Acceptance Tests • Power levels measurements at all outputs – 352. 21 MHz and 704. 42 MHz reference signals – harmonics • Phase noise measurements at several outputs • Phase drifts estimation based on temperature measurements and laboratory characterization data • Phase drifts of only entire branch can be measured directly – Problem with short/termination exchanging: nitrogen is flowing out 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 7

Thank you. 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 8

Thank you. 15. 03. 2017, Lund PRDS Commissioning and Acceptance Procedure, D. Sikora 8