Wages

Wages

What is a wage? This is a payment by the hour Many people who

What is a wage? This is a payment by the hour Many people who work in factories, in building and construction industry are paid by the hour. Often there is a basic wage for a certain number of hours, called a basic week.

Example #1 A basic work week is made up of 40 hours at a

Example #1 A basic work week is made up of 40 hours at a rate of $12 per hour. What are the wages paid for that week? Solution Basic wage = basic hours × hourly rate Basic wage = 40 × 12 = $ 480

Example #2 An agricultural field worker is paid $400 for a basic 40 hour

Example #2 An agricultural field worker is paid $400 for a basic 40 hour week. What is the hourly rate paid? Solution Basic wage = basic hours × hourly rate 400 = 40 × r 400/40 = r

Overtime Any number of hours worked beyond the basic week is paid at a

Overtime Any number of hours worked beyond the basic week is paid at a different rate than the basic rate. These extra hours are referred to over-time. Over time rate are calculated as Time and a quarter = 1 ¼ times the basic rate Time and a half = 1 ½ times the basic rate Double time = 2 times the basic rate Triple time = 3 times the basic rate

Example A road cleaner works a 40 hour week for a basic wage of

Example A road cleaner works a 40 hour week for a basic wage of $270. He also works 4 hours overtime at time and a half and 3 hours overtime at double time. Calculate this total wages for the week. Basic wage = basic hours × hourly rate 270 = 40 × r r = 270/40 r = $6. 75

Example A road cleaner works a 40 hour week for a basic wage of

Example A road cleaner works a 40 hour week for a basic wage of $270. He also works 4 hours overtime at time and a half and 3 hours overtime at double time. Overtime wage = # hrs overtime × overtime rate × basic rate Overtime wage = (4 × 1 ½ × 6. 75) + (3 × 2 × 6. 75) Overtime wage = 40. 50 + 40. 50 = $81 Total wage = Basic wage + Overtime wage Total wage = 270 + 81 = $351

#1 Wages A man’s basic wage for a 40 hour work week is $225.

#1 Wages A man’s basic wage for a 40 hour work week is $225. Calculate his total wages for the week that he works an additional 5 hours overtime at time and a half. A man is paid a basic hourly rate of $5. 60 for a 40 hour week. On weekdays, he is paid overtime at time and a half. If his wages for a given week was $308. 00, how many hours #2

#3 A construction company pays a basic wage of $275 for 35 hour week.

#3 A construction company pays a basic wage of $275 for 35 hour week. Overtime from Monday to Friday is paid at time and a quarter, overtime on Saturday is paid at time and a half and overtime on Sunday is paid at double time. Calculate the total wages for the following workers: a) Mr. Boyce worked 4 hours overtime between Monday and Friday, and 3 hours on Saturday. b) Ms. Mallett worked 6 hours overtime between Monday and Friday, and 2 hours on Saturday. c) Mr. Edwards worked 3 hours overtime between Monday and Friday, 3 hours on Saturday and 4 hours on Sunday.