Stormwater Construction General Pemit CGP TXR 150000 Lindsay

  • Slides: 20
Download presentation
Stormwater Construction General Pemit (CGP) TXR 150000 Lindsay Garza Stormwater Team – Water Quality

Stormwater Construction General Pemit (CGP) TXR 150000 Lindsay Garza Stormwater Team – Water Quality Division Texas Commission on Environmental Quality

Construction General Permit TXR 150000 Authorizes the discharge of stormwater runoff associated with small

Construction General Permit TXR 150000 Authorizes the discharge of stormwater runoff associated with small and large construction sites and certain non-stormwater discharges into surface water in the state. Effective March 5, 2018 - CGP expires five years from the permit effective date All active authorizations expire on the same date the general permit expires

CGP Authorized Discharges Stormwater associated with construction activity & construction support activities Certain non-stormwater

CGP Authorized Discharges Stormwater associated with construction activity & construction support activities Certain non-stormwater discharges • uncontaminated water used to control dust • uncontaminated air conditioning condensate

Construction Activity What is Construction? ü ü Clearing Grading Excavating, or Similar activities that

Construction Activity What is Construction? ü ü Clearing Grading Excavating, or Similar activities that disturb / expose soil • Demolition, infilling pits, and stockpiling soil for construction What is not Construction? × × Certain routine maintenance activities • Routine grading of roads • Asphalt overlay of roads • Routine clearing of ROW Agricultural land disturbance

Construction Site - Land Disturbance Large Construction disturbing five acres or more Small Construction

Construction Site - Land Disturbance Large Construction disturbing five acres or more Small Construction Disturbing an acre or more but less than five

Operators – Large Construction PRIMARY operational control over construction plans and specifications – including

Operators – Large Construction PRIMARY operational control over construction plans and specifications – including ability to make changes OR day-to-day operational control of activities – authorized to direct workers at site to carry out activities to comply with permit conditions

Before the site discharges Stormwater Pollution Prevention Plan (SWP 3) developed, implemented & maintain

Before the site discharges Stormwater Pollution Prevention Plan (SWP 3) developed, implemented & maintain copy on-site Notice of Intent (NOI) completed & submitted 2 1 3 Site Notice(s) post primary/secondary operator site notice

Stormwater Pollution Prevention Plan (SWP 3) Site Map Pollution prevention procedures Estimated dates of

Stormwater Pollution Prevention Plan (SWP 3) Site Map Pollution prevention procedures Estimated dates of construction activities Description of stormwater controls Procedures for inspections, maintenance, and corrective action

CGP and Municipalities If discharging to gutters, streets, channels, ditches or any other Municipal

CGP and Municipalities If discharging to gutters, streets, channels, ditches or any other Municipal Separate Storm Water Sewer System (MS 4) – operators must submit a copy of each of these forms to the MS 4 operator NOI NOC NOT

Small Construction Sites Activities Permit Requirements: -preparation & implementation of SWP 3 -small construction

Small Construction Sites Activities Permit Requirements: -preparation & implementation of SWP 3 -small construction site notice -notify MS 4 operator Not required to submit: -Notice of Intent -Notice of Termination disturb an acre or more but less than five

Disturb less than an Acre If the project site disturbs less than 1 acre

Disturb less than an Acre If the project site disturbs less than 1 acre and is not part of a larger common plan of development, coverage under the general permit is not required. Requirements: -implementation & maintenance of best manageable practices - notify MS 4 operator

Terminating Coverage The NOT must be submitted to TCEQ, and a copy of the

Terminating Coverage The NOT must be submitted to TCEQ, and a copy of the NOT provided to the operator of any MS 4 receiving the discharge , within 30 days after any of the following conditions are met: a) final stabilization has been achieved on all portions of the site that are the responsibility of the operator; b) a transfer of operational control has occurred; or c) the operator has obtained alternative authorization under an individual TPDES permit.

Terminating Coverage Final stabilization must be achieved prior to termination of permit coverage. All

Terminating Coverage Final stabilization must be achieved prior to termination of permit coverage. All soil disturbing activities at the site have been completed and a uniform perennial vegetative cover with a density of at least 70% of the native background vegetative cover - This does not include areas with permanent structures Large & Small Construction Operators must : q Remove temporary Best Management Practices q Remove site Notice(s) Small Constructions sites do not need an NOT.

Oil and Gas Activities & Construction ‒ The CGP does not authorize discharges from

Oil and Gas Activities & Construction ‒ The CGP does not authorize discharges from construction activities associated with the: • exploration, development, or production of oil or gas or geothermal resources • including construction associated with the transportation of crude oil or natural gas by pipeline. ‒ Operators of these construction activities may need to obtain permit coverage from the U. S. EPA and the Texas Railroad Commission

Applications via e. Permits Applications must be submitted using the State of Texas Electronic

Applications via e. Permits Applications must be submitted using the State of Texas Electronic Reporting System (STEERS) at: https: //www 3. tceq. texas. gov/steers/ “ Electronic filing is available for the following: -Notice of Intent -Notice of Termination -Notice of Chance -Low Rainfall Erosivity Waiver

Water Quality General Permits & Registration Search ‒ Track the status of applications for

Water Quality General Permits & Registration Search ‒ Track the status of applications for general permits at: http: //www 2. tceq. texas. gov/wq_dpa/index. cfm ‒ TXR 150000 - Construction (NOI & Waiver) ‒ Search for authorizations or applications under a specific general permit or for a specific registration type.

2018 CGP Changes to NOI – Estimated start date – Estimated end date –

2018 CGP Changes to NOI – Estimated start date – Estimated end date – Concrete Truck Washout

TCEQ Stormwater Program Contacts For questions regarding your STEERS account and technical difficulties with

TCEQ Stormwater Program Contacts For questions regarding your STEERS account and technical difficulties with e-NOI: (512) 239 -6925 For questions about the application process, contact the Stormwater Processing Center: (512) 239 -3700 Other questions including technical, contact the Small Business and Local Government (SBLGA) Hotline: 1 -800 -447 -2827

TCEQ Stormwater Team Members Rebecca L. Villalba, Team Leader Lindsay Garza, Work Leader Hanna

TCEQ Stormwater Team Members Rebecca L. Villalba, Team Leader Lindsay Garza, Work Leader Hanna Lehman Nielson Dan Siebeneicher Lili Martinez Macayla Coleman TCEQ Water Quality Division (512) 239 -4671 SWGP@tceq. texas. gov