F 2 D 2 MEETING 13092018 31122021 F
![F 2 D 2 MEETING 13/09/2018 31/12/2021 F 2 D 2 Coil maufacturing | F 2 D 2 MEETING 13/09/2018 31/12/2021 F 2 D 2 Coil maufacturing |](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-1.jpg)
![AGENDA • Coil 3 -4 development (Maria) • Magnetic design update (Valerio) • Mechanical AGENDA • Coil 3 -4 development (Maria) • Magnetic design update (Valerio) • Mechanical](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-2.jpg)
![COIL MANUFACTURING COIL HEAD STUDIES Maria Durante 07/09/2018 31/12/2021 F 2 D 2 Coil COIL MANUFACTURING COIL HEAD STUDIES Maria Durante 07/09/2018 31/12/2021 F 2 D 2 Coil](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-3.jpg)
![• Study of the feasability of the external joints • Study of coil • Study of the feasability of the external joints • Study of coil](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-4.jpg)
![COIL 3 -4 STUDIES – HF LAYER JUMP R min hardway 450 mm Rmin COIL 3 -4 STUDIES – HF LAYER JUMP R min hardway 450 mm Rmin](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-5.jpg)
![COIL 3 -4 STUDIES - HF LAYER JUMP 31/12/2021 F 2 D 2 Coil COIL 3 -4 STUDIES - HF LAYER JUMP 31/12/2021 F 2 D 2 Coil](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-6.jpg)
![COIL 3 -4 STUDIES – LF LAYER JUMP R min hardway 450 mm Rmin COIL 3 -4 STUDIES – LF LAYER JUMP R min hardway 450 mm Rmin](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-7.jpg)
![COIL 3 -4 STUDIES – HF CABLE GOING OUT R min hardway 450 mm COIL 3 -4 STUDIES – HF CABLE GOING OUT R min hardway 450 mm](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-8.jpg)
![NEXT STEPS • Continue components design • Starts tooling design • Plan for cable NEXT STEPS • Continue components design • Starts tooling design • Plan for cable](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-9.jpg)
![| PAGE 10 F 2 D 2 Coil maufacturing | Coil Head Studies 31/12/2021 | PAGE 10 F 2 D 2 Coil maufacturing | Coil Head Studies 31/12/2021](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-10.jpg)
- Slides: 10
![F 2 D 2 MEETING 13092018 31122021 F 2 D 2 Coil maufacturing F 2 D 2 MEETING 13/09/2018 31/12/2021 F 2 D 2 Coil maufacturing |](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-1.jpg)
F 2 D 2 MEETING 13/09/2018 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 1
![AGENDA Coil 3 4 development Maria Magnetic design update Valerio Mechanical AGENDA • Coil 3 -4 development (Maria) • Magnetic design update (Valerio) • Mechanical](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-2.jpg)
AGENDA • Coil 3 -4 development (Maria) • Magnetic design update (Valerio) • Mechanical design update (Etienne) • Supporting work: update on SD (Philip) • Protection: point on comsol • New meeting time slot 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 2
![COIL MANUFACTURING COIL HEAD STUDIES Maria Durante 07092018 31122021 F 2 D 2 Coil COIL MANUFACTURING COIL HEAD STUDIES Maria Durante 07/09/2018 31/12/2021 F 2 D 2 Coil](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-3.jpg)
COIL MANUFACTURING COIL HEAD STUDIES Maria Durante 07/09/2018 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 3
![Study of the feasability of the external joints Study of coil • Study of the feasability of the external joints • Study of coil](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-4.jpg)
• Study of the feasability of the external joints • Study of coil 3 -4 only • Critical points: • Layer jumps of low grade and high grade • Coil leads exit Objective is to keep the coil as compact as possible => several versions are considered 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 4
![COIL 3 4 STUDIES HF LAYER JUMP R min hardway 450 mm Rmin COIL 3 -4 STUDIES – HF LAYER JUMP R min hardway 450 mm Rmin](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-5.jpg)
COIL 3 -4 STUDIES – HF LAYER JUMP R min hardway 450 mm Rmin easy way 10 x Cable thickness HF Layer Jump S on one side LJ lenght : 200 mm 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 5
![COIL 3 4 STUDIES HF LAYER JUMP 31122021 F 2 D 2 Coil COIL 3 -4 STUDIES - HF LAYER JUMP 31/12/2021 F 2 D 2 Coil](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-6.jpg)
COIL 3 -4 STUDIES - HF LAYER JUMP 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 6
![COIL 3 4 STUDIES LF LAYER JUMP R min hardway 450 mm Rmin COIL 3 -4 STUDIES – LF LAYER JUMP R min hardway 450 mm Rmin](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-7.jpg)
COIL 3 -4 STUDIES – LF LAYER JUMP R min hardway 450 mm Rmin easy way 10 x Cable thickness LF Layer Jump – version B S on one side R min HW 286 mm Same side that Layer 3 going out Opposite to Layer 4 going out BASELINE F Layer Jump – version A S in two parts to imprpve compaction 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 7
![COIL 3 4 STUDIES HF CABLE GOING OUT R min hardway 450 mm COIL 3 -4 STUDIES – HF CABLE GOING OUT R min hardway 450 mm](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-8.jpg)
COIL 3 -4 STUDIES – HF CABLE GOING OUT R min hardway 450 mm Rmin easy way 10 x Cable thickness HF Going out – version A Layer 4 going out on layer 4 side, in the pad Exit toward the pad HF going out – version B Layer 4 going out on layer 3 side, Layer 3 and 4 going out on the same side, between the coils « exit jump » requires to extend length BASELINE 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 8
![NEXT STEPS Continue components design Starts tooling design Plan for cable NEXT STEPS • Continue components design • Starts tooling design • Plan for cable](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-9.jpg)
NEXT STEPS • Continue components design • Starts tooling design • Plan for cable bending tests using cable samples sent by CERN 31/12/2021 F 2 D 2 Coil maufacturing | Coil Head Studies | PAGE 9
![PAGE 10 F 2 D 2 Coil maufacturing Coil Head Studies 31122021 | PAGE 10 F 2 D 2 Coil maufacturing | Coil Head Studies 31/12/2021](https://slidetodoc.com/presentation_image_h2/43db253ee0baa162041b36bbc3e80fc7/image-10.jpg)
| PAGE 10 F 2 D 2 Coil maufacturing | Coil Head Studies 31/12/2021 Commissariat à l’énergie atomique et aux énergies alternatives Centre de Saclay | 91191 Gif-sur-Yvette Cedex T. +33 (0)1 69 08 71 27 | F. +33 (0)1 69 08 69 49 Etablissement public à caractère industriel et commercial | RCS Paris B 775 685 019 DSM IRFU SACM
Today meeting or today's meeting
Meeting objective
What is meeting and types of meeting
Types of meeting
Iep meeting do's and don'ts
Interest meeting agenda
Meeting will begin shortly
Cft meeting in company
Icca scandinavian chapter meeting 2021
Do meeting minutes have to be approved
Behavioral observation scales adalah