1 TULE RIVER SPILLWAY ENLARGEMENT PROJECT 237 237

  • Slides: 6
Download presentation
1 TULE RIVER SPILLWAY ENLARGEMENT PROJECT 237 237 217 217 200 200 0 163

1 TULE RIVER SPILLWAY ENLARGEMENT PROJECT 237 237 217 217 200 200 0 163 163 131 132 122 80 119 27 252 174. 59 110 135 120 112 92 56 CVFPB INFORMATIONAL BRIEFING 255 255 239 65 53 62 102 130 102 56 48 130 120 111 Katie Jane Charan Senior Project Manager 29 March 2019 “The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation. ” FOUO – Contains Pre-Decisional Information – Do Not release 07/06/18 KJC

2 TULE RIVER SPILLWAY ENLARGEMENT PPA #1 Total Project Cost: $74, 000 - Change

2 TULE RIVER SPILLWAY ENLARGEMENT PPA #1 Total Project Cost: $74, 000 - Change from 2003 PCA which was cost shared 65/35 - Supplemental is 100% Federally Funded (minus LERRDs) o LERRDs will be reimbursable to the NFS § Subject availability of funding - Lower Tule River Irrigation District (LTRID) will be responsible for flood control and water supply - LTRID will be lead agency for CEQA As of xx December 2016

TULE RIVE SPILLWAY ENLARGEMENT PROJECT Fraizer Dike HWY 190 Rip Rap Spillway As of

TULE RIVE SPILLWAY ENLARGEMENT PROJECT Fraizer Dike HWY 190 Rip Rap Spillway As of xx December 2016 Relief Wells 3

TULE RIVE SPILLWAY ENLARGEMENT - CONCEPTUAL Construction Sequence: Phase 1 – Right Abutment /

TULE RIVE SPILLWAY ENLARGEMENT - CONCEPTUAL Construction Sequence: Phase 1 – Right Abutment / Bench Road Phase 2 – Spillway Raise, Fraizer Dike & HWY 190 Phase 3 - Mitigation As of xx December 2016 4

Tule River Basin – Schedule Activity Dates Li. DAR Survey Award 08 Feb 19

Tule River Basin – Schedule Activity Dates Li. DAR Survey Award 08 Feb 19 (A) Operational Use from NFS 30 Jan 19 (A) Public Meeting 4 Feb 19 (A) Geotechnical Borings 4 Feb – 29 Mar 19 AE Design Contract Award 28 Mar 19 Right Spillway Cut Draft EA 15 Apr 19 Environmental & Cultural Surveys March-May 2019 PPA Signed & Take Letters Issued 30 Mar 19 Right Spillway Cut 35% Design 30 Jun 19 Construction Contracts 5 100% Design Award Dates Completion Dates Right Spillway Cut / Road 20 Jan 20 14 Jun 20 28 Feb 21 Spillway Enlargement 21 Oct 20 22 Feb 21 28 Feb 23 Monitoring 28 Feb 28 FOUO – Contains Pre-Decisional Information – Do Not release 07/06/18 KJC

6 DISCUSSION/QUESTIONS 07/06/18 KJC