Xray test beam Simone Mazza on behalf of
X-ray test beam Simone Mazza on behalf of the SCIPP group 1 10/12/2018
Plans for X-ray test-beam: Equipment �CAEN digitizer: 2 x available � 16 ch board: 2 x available �Motorized stage: � 1 x linear available �To be ordered: 1 x linear 1 x rotational �Mounting stages: first prototype CAD ready �Control PC: to buy �Cables: ~20 x to buy �HV/LV power supply: do we bring our own? 2 10/12/2018
Plans for X-ray test-beam: Rn. D �Read out the CAEN digitizer �William: more or less working, to be refined �William: test optical link maximum a couple days �Characterization of the 16 ch board with X-rays �Zach, Simone, Eric, Austin: Tested, data to be analyzed �Characterization of the 16 ch board with laser �Zach: preliminary characterization, amplifier is linear up to 1. 8 V �Zach, Simone, Eric, Austin: Board will be mounted and tested 3 10/12/2018
Plans for X-ray test-beam: Rn. D �Finish the Mounter design �Zach: first prototype ready, send out to print? �Key piece of information: time between ordering the piece and arrival �Conditioner board �Max: First prototype tested, working but really noisy �Key piece of information: time between ordering the piece and arrival �Control the motorized stages �William: to be done, someone else? 4 �Precise mounting of the sensors �Forest, Zach: using the smart scope and glue (instead of conductive 10/12/2018 tape)
Plans for X-ray test-beam: Priorities/Timeline �Buy new motors, PC and cables �Test the 16 ch board with the X-ray or laser with the CAEN digitizer �Test the 16 ch board with the conditioner board once new prototype is ready � 3 D print the first version of the mounter and test a mock setup �Control the motors �Mount the sensor with precision 5 10/12/2018
Plans for X-ray test-beam: Timescale � 2 months remaining to end the project �Complete setup must be ready at least 1 -2 weeks in advance We’re here 6 APS test-beam 10/12/2018
Plans for X-ray test-beam: Deadlines proposal �Buy the motors by the end of next week (05/31): Zach �CAEN digitizer test next week (05/31): William, Austin, Eric �First 3 D printed mounter by 06/07: Zach �Motor control ready by 06/14: William or someone else? �Conditioner board prototype by 06/14: Max �Sensor mounted and smart scope measurements by 06/21: Zach, Forest �Conditioner board ready by 06/28: Max �Mounter ready and milled by 07/03: Zach �Test of the entire setup by 07/14: Everyone 7 10/12/2018
Plans for X-ray test-beam: Deadlines proposal control 16 ch board laser test. Motor ready Test 16 ch board with CAEN 8 Mounting of sensors Test of entire setup Conditioner board ready and tested 3 D printed stages Mounter ready Buy material 10/12/2018
Key questions �Mounter design: time between ordering the piece and arrival �Conditioner board: time between ordering the piece and arrival 9 10/12/2018