www salga org za The Electrification Indaba Panel

  • Slides: 18
Download presentation
www. salga. org. za The Electrification Indaba Panel discussion: Experiences & lessons learned Mthobeli

www. salga. org. za The Electrification Indaba Panel discussion: Experiences & lessons learned Mthobeli Kolisa Executive Director: Municipal Infrastructure Services 15 March 2012 1

www. salga. org. za Achievement • The level of access to electricity rose from

www. salga. org. za Achievement • The level of access to electricity rose from 36% in 1994 to 82% at the end of 2010 (5, 2 million households in 16 yrs) • Stimulating economic activity in areas that were otherwise dormant • Improved quality of life of the citizens at home, schools, clinics, hospitals, churches, access to pumped water, etc • Provided Free Basic Electricity to the poor • These are no small achievements • However still need to do more – 92% of formal households by 2014

www. salga. org. za However. . . • Only fiscus funding electrification in areas

www. salga. org. za However. . . • Only fiscus funding electrification in areas where municipalities are not distributors - extent of opportunities for leveraging borrowings? • In areas where Eskom is a distributor, alignment of electrification investment with municipal development plans is dependent on personalities rather than inherent in processes and institutional arrangements • Costs increasing as the remaining areas are becoming more challenging • Urgent need for rehabilitation and refurbishment of infrastructure - put on hold as the focus was on extending services

www. salga. org. za Recent historical performance of the program Year 2006/7 2007/8 2008/9

www. salga. org. za Recent historical performance of the program Year 2006/7 2007/8 2008/9 2009/10 2010/11 Total Connections completed Target to date % Completed 76, 305 74, 253 97% 66, 875 66, 131 99% 48, 447 46, 381 96% 76, 263 67, 002 88% 84, 235 28, 976 34% 352, 125 282, 743 80% Always behind schedule and catching up in the following years – theoretically there are funding constraints to meet targets but implementation performance is also a major issue

www. salga. org. za 2011/12 performance of the program (as @ Jan 2012) Province

www. salga. org. za 2011/12 performance of the program (as @ Jan 2012) Province Eastern Cape Free State Gauteng Kwa. Zulu Natal Limpopo Mpumalanga North West Northern Cape Western Cape Total No. planned 80 16 14 79 85 26 6 23 34 363 Project complete > 50% with energy supply progress 35% 50% 71% 9% 60% 35% 83% 39% 56% 40% 28% 25% 21% 0% 6% 15% 17% 13% 6% 12% < 50% Construction progress not started 11% 6% 7% 53% 8% 4% 0% 22% 15% 20% 26% 19% 0% 38% 26% 46% 0% 26% 24% 28%

www. salga. org. za Some issues for consideration • Discussed in terms of 1.

www. salga. org. za Some issues for consideration • Discussed in terms of 1. Rural 2. Urban 3. Informal Settlements

www. salga. org. za Current situation Rural • 75 % of backlogs • Largely

www. salga. org. za Current situation Rural • 75 % of backlogs • Largely areas in which Eskom is a licensed distributor • Municipalities (non-licensed and licensed) access money from Do. E and Provincial Governments to implement projects in these Eskom areas of supply • Hand over infrastructure to Eskom on completion for O&M

www. salga. org. za Some concerns Rural • Non- distributing municipalities do not have

www. salga. org. za Some concerns Rural • Non- distributing municipalities do not have electricity departments – completely rely on consultants • Also many distributing municipalities have vacancy levels of skilled resources exceeding 50% of established posts (ref: EDI Holdings ringfencing study) – but still stretch themselves to Eskom areas • Consultants approach municipalities to be appointed for designing and managing implementation of projects • The design cost is purported to be at risk and the payment is recovered once the project submitted by the municipality is approved; no real risk – Desperate MMs take the first available “support” they can get – No capacity to review the appropriateness of proposed projects and quality of work – INEP offices have no capacity either to support municipalities in this regard

www. salga. org. za Current situation Urban • A fraction of the 25% of

www. salga. org. za Current situation Urban • A fraction of the 25% of backlog • Largely areas in which 177 municipalities are licensed distributors • Do. E currently does not allow upgrade of existing infrastructure required for electrification projects, but talks in place to cater for capital reinforcement projects. • Infill connections – Do. E reluctant to fund infill connections – demand for these connections in existing developments is increasing as more houses are built; also contrary to the objective of densification of spatial development patterns to improve urban efficiency. – Requirement for 80% occupancy of housing developments has also been a delaying factor; also leading to public protests about incomplete houses

www. salga. org. za Current situation Informal settlements • A significant component of the

www. salga. org. za Current situation Informal settlements • A significant component of the remaining 25% backlog • Numbers of informal settlements are increasing with a consequent requirement from political leaders and communities for `regularisation’ (including electrification) of these areas • Do. E currently providing for the electrification of informal settlements. • Apart from providing the required electrical reticulation, each informal dwelling is also provided with a Pre-paid meter connection and basic connections for electrical fittings.

www. salga. org. za Current situation Informal settlements • Need for the planning alignment

www. salga. org. za Current situation Informal settlements • Need for the planning alignment of the Informal Settlement Upgrading Programme with the electrical reticulation programme of the Department of Energy to ensure that electrical grid is available when settlement upgrading projects commence. • Will require that provincial governments to make their approved Multi Year Housing Development Plans and priority development objectives available to the Do. E enable the latter to align its electrification programme accordingly.

www. salga. org. za Current situation Informal settlements • Agreement required on the removal

www. salga. org. za Current situation Informal settlements • Agreement required on the removal and recovery of the installed Pre-paid Meters from informal dwellings and the re-installation thereof in the new dwelling units, constructed through the National Housing Programme. • This initiative will require that the National Housing Programme to be adjusted to include funding for the removal of the existing meters and the reinstallation thereof in the new dwellings.

www. salga. org. za Some concerns General • Inequitable funding from Do. E –

www. salga. org. za Some concerns General • Inequitable funding from Do. E – Do. E policy to partially fund electrification connections by municipalities (urban and rural subsidies) but provide the full cost of connections provided by Eskom, – Municipalities are thus required to `top-up’ funding of electrification projects which impacts the overall municipal budget – Some municipalities face severe financial constraints • Limits uptake in smaller municipalities • Some poor households not collecting FBS tokens – poor customer relations (service provision is not only a technical exercise)

www. salga. org. za Some concerns General • Funding application process – Not aligned

www. salga. org. za Some concerns General • Funding application process – Not aligned with the municipal budgeting process – Lack of certainty of three-year Do. RA allocations – National Treasury will only release funding to municipalities wef 1 July of each year • MFMA procurement process – Many municipalities point to the drawn out procurement processes to appoint service providers and purchase the necessary equipment and materials as reasons for the delay in completing electrification projects; need for a balance between ensuring accountability and functionality

www. salga. org. za Recommendations • Need some shared capacity to provide technical support

www. salga. org. za Recommendations • Need some shared capacity to provide technical support to under-capacitated municipalities; capacitate INEP regional offices to play this role • INEP offices should be the points of coordination/ planning alignment between various electrification projects funding agencies • Provincial Housing Departments must make their approved Multi Year Housing Development Plans and priority development objectives available to the Do. E enable the latter to align its electrification programme accordingly • Do. E should allow upgrade of existing infrastructure required for electrification projects • Do. E should fund infill connections

www. salga. org. za Recommendations • Requirement for 80% occupancy of housing developments be

www. salga. org. za Recommendations • Requirement for 80% occupancy of housing developments be done away with • Adjustment of the National Housing Programme to include funding for the removal of the existing meters and the re-installation thereof in the new dwellings • Do. E policy should provide the full cost of connections in areas provided by both Eskom and municipalities • Eskom to enter into SDAs with municipalities where Eskom is a distributor so as to ensure • alignment of expectations • That municipalities are rightfully placed at the middle of the relationship between the service and the communities

www. salga. org. za Recommendations • Upscaled and coordinated skills development program through a

www. salga. org. za Recommendations • Upscaled and coordinated skills development program through a partnership that includes the Department of Higher Education, Department of Energy, Eskom, Local Government, Private Sector and the Water and Energy SETA. • We support the strategic way forward outlined by the DG in her presentation this morning.

www. salga. org. za THANK YOU

www. salga. org. za THANK YOU