WP 3 – Spare RFQ Project Alexej Grudiev, 8 December 2020 Linac 4 Spare

WP 3 – Spare RFQ Project Alexej Grudiev, 8 December 2020 Linac 4 Spare RFQ - 8 December 2020 1

Outline • WP Introduction • Deliverables to Project • Requirements from Groups • Present

Outline • WP Introduction • Deliverables to Project • Requirements from Groups • Present Status • Schedule • Budget • Open Points • Summary Linac 4 Spare RFQ - 8 December 2020 2

WP 3: RF measurements and RF tuning of RFQ 2 • Main objective of

WP 3: RF measurements and RF tuning of RFQ 2 • Main objective of WP 3 is to bring the low power RF performance of the RFQ 2 to its nominal design performance. It includes: • RF simulations of the RFQ to determine the nominal design values for the dipole rods, tuners, pumping ports, RF plugs and coupler • Design and construction of the new tuner system • Consolidation of the bead pull system • Design(if necessary) and fabrication of RF antennas • RF measurements of the individual modules • RF measurements and tuning of the fully assembled RFQ • RF calibration of the RFQ coupler and antennas after tuning including documentation Linac 4 Spare RFQ - 8 December 2020 3

Deliverables to Project • Items that the WP delivers to the project Item Deadline

Deliverables to Project • Items that the WP delivers to the project Item Deadline Status RFQ nominal dimensions Q 4 2020 In progress New tuning system design Q 4 2020 In progress New tuning system prototype Q 1 2021 To be started New tuning system series Q 2 2021 To be started Antennas Q 2 2021 To be started Bead pull system consolidation Q 2 2021 To be done RF measurements of modules Q 3 2021 To be done RF measurements and tuning of RFQ Q 4 2021 To be done RFQ calibration and documentation Q 4 2021 To be done Linac 4 Spare RFQ - 8 December 2020 4

Requirements from Groups • Items that a group has to deliver to the WP

Requirements from Groups • Items that a group has to deliver to the WP Item Group Deadline Mech. design EN-MME Q 4/2020 – Q 2/2021 In progress Prototyping and fabrication EN-MME Q 1 -Q 2 2021 To start Mechanical Technician BE-RF Q 2 -Q 4 2021 To be confirmed Location for RF measurements and tuning, B 181 Magnet group Q 3 -Q 4 2021 To be clarified Linac 4 Spare RFQ - 8 December 2020 Status 5

RFQ simulations Linac 4 Spare RFQ - 8 December 2020 6

RFQ simulations Linac 4 Spare RFQ - 8 December 2020 6

New RFQ tuning system Linac 4 Spare RFQ - 8 December 2020 7

New RFQ tuning system Linac 4 Spare RFQ - 8 December 2020 7

Schedule Item Deadline Comment RFQ nominal dimensions for dipole rods final 01/2021 cut On

Schedule Item Deadline Comment RFQ nominal dimensions for dipole rods final 01/2021 cut On going All RF measurement and tuning equipment ready 07/2021 On going Measurement of T 1, T 3 for pumping port dimension for final cut ~Q 2/2021 After first brazing and metrology of T 1, T 3 Measurement of T 2 for RF plug dimension for final cut ~Q 3/2021 After T 2 finished RFQ tuning for tuner dimensions for final cut Q 4/2021 RFQ final calibration and documentation Q 4/2021 Linac 4 Spare RFQ - 8 December 2020 8

Budget (for WP) Item • Please Budget Year(s) highlight. Cost any/ k. CHF significant

Budget (for WP) Item • Please Budget Year(s) highlight. Cost any/ k. CHF significant issues. Design of the new 20 2020 • tuning Cost Status: system Cost status Tuning 80 2021 • system Costed : Item understood and fabrication: 32 movers intermediate costed • Preliminary - Possibly provided by intermediate Richard. First prototype of one : Guesstimate 5 2021 tuner • mover Intermediate : Reasonable level of detail known. cost well known. Bead pull consolidation 5 2021 intermediate 16+spare antennas 20 2021 intermediate Linac 4 Spare RFQ - 8 December 2020 9

Open Points • Urgent Open Points • RFQ tuning location (B 181) • Personnel

Open Points • Urgent Open Points • RFQ tuning location (B 181) • Personnel • Mech. Technician ~1 FTE month Linac 4 Spare RFQ - 8 December 2020 10

Summary • Many Thanks to Marc Timmins ; Laurent Zuccalli ; Serge Mathot; Hermann

Summary • Many Thanks to Marc Timmins ; Laurent Zuccalli ; Serge Mathot; Hermann Pommerenke Linac 4 Spare RFQ - 8 December 2020 11