WP 2 On Detector Systems Delivers Sensors ASICs

  • Slides: 19
Download presentation
WP 2: On Detector Systems Delivers Sensors, ASICs and Hybrids to the Module programme;

WP 2: On Detector Systems Delivers Sensors, ASICs and Hybrids to the Module programme; Modules, Tapes and On-Stave Interfaces to the Stavelet and Stave programmes ABCN-25 BCC 2. 2 ASICs • Digital Design • Evaluation • Wafer Test 2. 1 Strip Sensors • Layout • Evaluation 2. 4 Modules • Build Process & Tooling • Evaluation • Skill Transfer 2. 6 On-Stave Interface • Design • Evaluation 2. 5 Tapes 2. 3 Hybrids • Layout & Manufacture • Flying Probe Machine • Die Attach Tooling • Evaluation • Skill Transfer Picture shows Serially Powered Stavelet 1

WP 2. 1 Strip Sensors • Original plan: next strip sensor procurement would be

WP 2. 1 Strip Sensors • Original plan: next strip sensor procurement would be to suit 130 nm chipset – May now need to procure a few tens of sensors for 250 nm chipset. . . • ATLAS 07 Sensors for modules with ABCN-25 chips were made on two substrate materials: – FZ-1 <100> (~6. 7 kohm cm) – FZ-2 <100> (~6. 2 kohm cm) • FZ-1 sensors generally have lower leakage current than FZ-2 sensors – First stavelet uses 3 FZ-2 sensors and 1 FZ-1 sensor – Later stavelets and stave were foreseen to use only FZ-1 sensors • After module assembly, FZ-1 sensors have been seen to develop reduced breakdown voltages (micro-discharge) – Observed with UK stave modules • Hybrids glued to sensor face – Also seen with KEK/Geneva double sided designs • Nothing touches the sensor face (hybrids are bridged) – Reproduced at UCSC using sensor held under intermittent vacuum • Physical deformation is temporary but IV degradation is permanent 2

WP 2. 1 Strip Sensors IR Microscopy of Damaged Sensor Y Unno, KEK •

WP 2. 1 Strip Sensors IR Microscopy of Damaged Sensor Y Unno, KEK • • IR images of affected sensors show problem at edge of guard ring – Assembly stresses may cause damage to the Si. O 2 passivation in this region Studies continue – IR microscopy of affected sensors will be performed in Japan • Likely fix – More robust Si. O 2 passivation – May require validation studies / irradiation Hot spots • How does this affect WP 2? – Short term: build stavelets using FZ-2 sensors – Medium term: may need to buy 5 -10 sensors for the validation study, and then to replace all FZ-1 sensors needed for Stave 250 programme • X 10 IR, Bias~400 V, ~10 µA As 130 nm chipset is delayed wrt the original schedule , this can be funded within the existing WP 2 programme. 3

WP 2. 2 ASICs: 250 nm chipset • Final 4 ABCN-25 wafers to be

WP 2. 2 ASICs: 250 nm chipset • Final 4 ABCN-25 wafers to be screened in UK – Work split between RAL and Glasgow • skill transfer between institutes: both sites would participate in any production screening – 3 screened at RAL – 1 + 1 to be screened at Glasgow Wafer A 5 GJ 0 HX Preliminary Result • Dicing to be performed in UK industry (Micross) 4

WP 2. 2 ASICs: 130 nm chipset First 130 nm Test Structures • First

WP 2. 2 ASICs: 130 nm chipset First 130 nm Test Structures • First 130 nm Test Structures back – PCBs to test Serial Powering Protection elements being assembled at RAL • Many aspects of ABCN-13 baseline specification now agreed – 256 channel chip – 2 stage triggering - L 0, L 1 • to allow trigger latencies of >100 us – Regional readout track trigger functions to be included • Recent work has focussed on trigger architecture and data format – Simulations performed in UK to assess data format and compression algorithms • Addition of TD ASIC designer to the Hybrid Controller Chip (HCC) team much appreciated by the community – Was previously under resourced • SEU Logic part SPP Elements Submission Target still Q 1/Q 2 2012 5

WP 2. 3 Hybrids Circuits made by Stevenage Circuits • 120 circuits ordered late

WP 2. 3 Hybrids Circuits made by Stevenage Circuits • 120 circuits ordered late 2010 – First delivery: 106 rejects • Poor quality gold plating • Useful for mechanical assemblies • Retained at discounted price – Second Delivery: 100 good circuits • Sufficient for medium term Passives added by Hawk Electronics • 39 of latest batch populated – Best solder quality to date – 7 circuits inspected and metrologised using Smart. Scope • 2 ASIC populated – ready for next UK module • 5 sent to UCSC – Will mount their own ASICs 6

WP 2. 4 Modules: Gluing Studies • Gluing studies finished and now getting consistent

WP 2. 4 Modules: Gluing Studies • Gluing studies finished and now getting consistent glue thicknesses • 5 modules have been assembled with new gluing techniques. - Now glue uniformity limited to flatness of incoming hybrids • Of the 5 modules • 2 are ready for DC/DC stave • 1 is ready for testing • 1 is being bonded (FZ 1 with breakdown at 270 V) • 1 needed hybrid debugging (assembled with untested hybrids with bonding problems) 7

Impact of Glue thickness on Module Performance Module with thick glue layer Module with

Impact of Glue thickness on Module Performance Module with thick glue layer Module with normal glue layer Input Noise at 1 f. C 588 e 143 microns 605 e AC Inner 599 e 102 microns 647 e 15 microns AC Outer Input Noise at 1 f. C 590 e 32 microns 101 microns 584 e 57 microns DC Inner 634 e 25 microns DC Outer DC Inner 94 microns 599 e DC Outer 8

WP 2. 4 Modules: Gluing Flatness Module 13 Module 14 Module 15 Module 16

WP 2. 4 Modules: Gluing Flatness Module 13 Module 14 Module 15 Module 16 9

Hybrid and Module Production Roll-out • 6 sites are now actively pursuing gluing trials

Hybrid and Module Production Roll-out • 6 sites are now actively pursuing gluing trials of hybrids and/or modules • LBL, UCSC, Cambridge, Liverpool, DESY, Freiburg • Glasgow is beginning to plan on making a set of jigs for themselves • Freiburg and Glasgow are coming to Liverpool for training session May 17 -18 th SP Module in Test Frame • UCSC is bonding/testing first hybrid now • Cambridge has already bonded/tested first hybrids 10

Modules: Double Trigger Noise • COM The Double Trigger Noise test sends two triggers

Modules: Double Trigger Noise • COM The Double Trigger Noise test sends two triggers to a module or stave(let) with controlled, variable spacing, keeping the ASICs at fixed threshold – The trigger spacing is varied to scan for noise correlated with trigger or readout activity. • d. V The test has been applied to stave modules powered in three ways: – Serially Powered – Parallel Powered – Powered through individual DC-DC convertors DATA Stavelet Hybrid 7, BWL ON 150 n. S = 6 BCO • In all cases, a small d. V is observed on the power rails correlated with the reception of trigger commands or configuration data – Maybe specific to ABCN-25 chipset? 11

Modules: Double Trigger Noise Time • 6 BCO = 150 n. S Channel Serially

Modules: Double Trigger Noise Time • 6 BCO = 150 n. S Channel Serially Powered Module, DTN at 1 f. C threshold For a serially powered module running at 1 f. C threshold, increased occupancy is observed at certain timings on one hybrid of the pair – The time profile fits with the d. V signal – The effect spreading to the other hybrid as the threshold is lowered • For parallel powered modules or those with DC-DC convertors, the effect is seen at very low thresholds – Well below expected 0. 7 f. C operating point • For SP modules, the d. V signal is being picked up in the front end – This is most likely due to the way the two hybrids are referenced in the SP module 12

Modules: Double Trigger Noise • Tests continue to determine ways to reduce this effect

Modules: Double Trigger Noise • Tests continue to determine ways to reduce this effect – Reducing the inductance of referencing ties helps – Extra decoupling of the power rails can help • What does this mean? – Optimistic: need to improve referencing – Pessimistic: reduce powering modularity from n hybrids to n/2 modules • Places both hybrids at same DC potential wrt sensor • What does this mean for WP 2? – PCBs to permit reduced modularity operation of existing stavelet will be ordered this week – Modules and Tapes for a second SP stavelet will not be built until this issue has been resolved 13

WP 2. 5 Tapes: Shield Optimisation • Work underway to determine material needed to

WP 2. 5 Tapes: Shield Optimisation • Work underway to determine material needed to screen the detector backplane from aggressor signals on the bus tape – Potential for mass reduction • Image shows a single module mounted above a shielded test tape Shield Optimisation Studies – Basic noise results agree with expectation – Injection studies just beginning 14

WP 2. 5 Tapes: Production and QA • Power tape for DC-DC stavelet –

WP 2. 5 Tapes: Production and QA • Power tape for DC-DC stavelet – Successfully made in house at Oxford – Mounted onto a stavelet core at LBNL – Modules to be added shortly at RAL DC-DC Power Tape • Flying probe / visual inspection system is being made – An order for a computer controlled gantry system had to be cancelled as the vendor refused to deliver what their sales team had promised! • Will submit replacement order to a different vendor – A camera/capture system has been procured 15

WP 2. 6 On Stave Interface • The present End Of Stave board implements

WP 2. 6 On Stave Interface • The present End Of Stave board implements an electrical interface between the stave(let) and the off-detector electronics – Its performance is satisfactory – We plan to use the existing board for all stave(let)s using ABCN-25 • Final staves using the ABCN-13 chipset will instead use a high bandwidth optical link using the GBT Giga. Bit Transceiver protocol running over the VL Versatile Link – This work package follows developments within the GBT and VL projects to ensure their compatibility with the ABCN-13 chipset, leading toward the implementation of a suitable End Of Stave board • The international community is making good progress! – Whilst FPGA-based demonstrator systems are available, given present funding constraints in the UK we do not immediately plan to procure such a system • Meanwhile the UK’s contribution to optical links for the ATLAS tracker upgrade is focussed upon the characterisation of passive optical components as part of the VL collaboration (see WP 3) 16

WP 2: Deliverables and Key Notes Deliverable Target Status Modules for DC-DC Stavelet 03/11

WP 2: Deliverables and Key Notes Deliverable Target Status Modules for DC-DC Stavelet 03/11 50% Complete. 2 ready, 1 pending test, 1 being bonding, 1 requires hybrid debugging. Expect completion 05/11. Probe last 4 ABCN-25 Wafers 04/11 75% Complete. Expect completion 05/11. Modules for SP Stavelet Second SP stavelet delayed pending double trigger noise studies. 05/11 Key Progress Key Issues • Optimisation of module glue layer • Reduced module noise • Breakdown of FZ 1 sensors • May need to be replaced • Roll-out of hybrid and module assembly to multiple institutes • Skill Transfer • UK and Overseas • Double Trigger Noise on SP modules • Resolution may involve changes to tape design, extra decoupling and/or revised module hook-up 17

Backup

Backup

WP 2: Recent Deliverables For the DC-DC Stavelet First DC-DC Test of Stave Module

WP 2: Recent Deliverables For the DC-DC Stavelet First DC-DC Test of Stave Module First DC-DC Stavelet DETAIL • Module (WP 2) • Cu Plated Shield (WP 3) • DC-DC convertors (CERN) • Custom Module Frame PCB (WP 2) • Results in agreement with SP module provided adequate shielding used • Stavelet Core (WP 4) • DC-DC Power Tape (WP 2) • Misc. Support PCBs (WP 2, not shown) • Construction of 4 modules in progress (WP 2) 19