Workpackages for CNGS CERN Neutrinos to Gran Sasso

  • Slides: 33
Download presentation
Workpackages for CNGS (CERN Neutrinos to Gran Sasso) + experience with the CNGS project

Workpackages for CNGS (CERN Neutrinos to Gran Sasso) + experience with the CNGS project by Konrad Elsener, CERN (project leader 2000 -2006) Apologies: CNGS was a “small” project – few % of the LHC The CNGS project CNGS – same additional remarks --Project management tools used – work packages/units Acknowledgement: Malika Meddahi, Natacha Lopez 1

The CNGS project Task: build and commission a muon-neutrino beam at CERN in direction

The CNGS project Task: build and commission a muon-neutrino beam at CERN in direction of Gran Sasso (Italy) 2

3

3

4

4

CNGS budget and schedule total materials budget (incl. contract labor): 77. 6 MCHF total

CNGS budget and schedule total materials budget (incl. contract labor): 77. 6 MCHF total CERN staff: 105 person-years 5

Civil Engineering > 3 km of tunnels several caverns > 45’ 000 m 3

Civil Engineering > 3 km of tunnels several caverns > 45’ 000 m 3 of excavation > 12’ 000 m 3 of concrete poured + a 1 km long steel tube (vacuum decay tube) (2. 45 m diameter, 18 mm wall thickness, embedded in concrete) 6

7

7

8

8

CNGS “materials” budget (incl. contract labor) project budget total: 77. 6 MCHF of which

CNGS “materials” budget (incl. contract labor) project budget total: 77. 6 MCHF of which “income” special contributions cash: 54. 3 MCHF special contributions “in-kind”: 6. 8 MCHF --------------------------------Civil Engineering (a) underground works 28. 8 MCHF (b) steel vacuum tube (decay) 8. 4 MCHF (c) consultants* for (a)+(b) 3. 7 MCHF Infrastructure 11. 0 MCHF Equipment 23. 2 MCHF Contingency 2. 5 MCHF 9 * includes a contract for safety co-ordination

CNGS project completed - on time - a few MCHF below the estimated cost

CNGS project completed - on time - a few MCHF below the estimated cost beam fully operational: 18 August 2006 10

CNGS – additional remarks project “ready for approval” in Dec. 1998 one year to

CNGS – additional remarks project “ready for approval” in Dec. 1998 one year to finalise layout, produce CE drawings -> saved a lot of money project approval Dec. 1999: 71 MCHF completion May 2005 “re-baseline” in 2002 77. 6 MCHF first beam May 2006 (minor) schedule change in 2006: first beam 10 July 2006 “end of project” 18 August 2006 11

27 October 2006: water leak on the “reflector” (2 nd focusing lens after target)

27 October 2006: water leak on the “reflector” (2 nd focusing lens after target) experiment at Gran Sasso not ready – beam again mid-Sept. 2007 12

CNGS – before project approval (1997 -1999) Technical Committee on CERN-INFN Neutrino Programme 19

CNGS – before project approval (1997 -1999) Technical Committee on CERN-INFN Neutrino Programme 19 meetings in 20 months (2 INFN managers, 4 INFN neutrino physicists, + 18 CERN staff – chair: director of accelerators) CERN Internal Working Group 37 meetings in 24 months 1998: Conceptual Technical Design Report 1999: Addendum to C. T. D. R. no formal “value-engineering” performed – but a lot of brainstorming on possible cost reduction for CNGS 13

Project Management Tools standard methods and tools: -> PBS (“what? ” - product) ->

Project Management Tools standard methods and tools: -> PBS (“what? ” - product) -> Project Equipment Coding Convention (<->SPS) -> WBS (deliverables -> incl. project management, installation, commissioning) -> OBS. . . did not produce a RRM (Resource-Responsibility Matrix). . . May 2003: -> EVM (Earned Value Management) CERN Tool: PPT (Project Progress Tracking) -> work-units (incl. CERN manpower) 14

Work Breakdown Structure 15

Work Breakdown Structure 15

CNGS total: 112 workpackages 16

CNGS total: 112 workpackages 16

CFS Workpackages – part 1 17

CFS Workpackages – part 1 17

CFS Workpackages – part 2 (inside: workunits) 18

CFS Workpackages – part 2 (inside: workunits) 18

Earned Value Management key parameters: Planned Value vs. Actual Cost / Earned Value Money

Earned Value Management key parameters: Planned Value vs. Actual Cost / Earned Value Money Today PV AC Cost variance Schedule variance EV time 19

PPT: Project progress tracking 20

PPT: Project progress tracking 20

EVM for CNGS -- following the WBS 1 st baseline frozen 9 May 2003

EVM for CNGS -- following the WBS 1 st baseline frozen 9 May 2003 (313 work-units) 2 nd baseline frozen 18 June 2004 at the end: 450 work-units 56 wu – project management / co-ordination 6 wu – civil engineering incl. decay tube, doors, etc. 230 wu – engineering and supply 9 – cooling, ventilation, electrical services 158 wu – installation in different areas 62 - cooling, ventilation, electrical services (10 wu cancelled ‘on the way’) NB. LHC has 12452 wu, 142 cancelled, 878 active, 218 late, 62 planned, 40 draft 21

PPT data I/O interface: EXCEL (or web-page) CNGS example (work-unit) 22

PPT data I/O interface: EXCEL (or web-page) CNGS example (work-unit) 22

Status of Work Units / SEARCH facility 23

Status of Work Units / SEARCH facility 23

Work unit reporting done once per month data in workunits updated when required 24

Work unit reporting done once per month data in workunits updated when required 24

Staff plan 25

Staff plan 25

EVM summaries in PPT: an example Target station Proton Beam dump Windows Shielding Helium

EVM summaries in PPT: an example Target station Proton Beam dump Windows Shielding Helium tubes Shutter Hadron Stop 26

Engineering Data Management System - EDMS (existing tool, cf. LHC) • allows data storage

Engineering Data Management System - EDMS (existing tool, cf. LHC) • allows data storage with many options. . . • in CNGS used for all files, including minutes, slides from presentations, internal notes, etc. (E -> electronic) • Engineering Change Request procedures • Non-Conformity procedures • CNGS-EDMS is now being used and updated by the teams operating the facility 27

CNGS-EDMS: Who are the users? Single storage/source of data Make sure that people find

CNGS-EDMS: Who are the users? Single storage/source of data Make sure that people find the right information (e. g. latest, approved or relevant information). D. Widegren 28

CNGS-EDMS tree structure based on PBS (+ some additional branches) 29

CNGS-EDMS tree structure based on PBS (+ some additional branches) 29

30

30

Loading a document 31

Loading a document 31

Document release procedure 32

Document release procedure 32

Summary • CNGS: a “medium-size” project (100 MCHF), 2000 -2006 • WBS (and EDMS)

Summary • CNGS: a “medium-size” project (100 MCHF), 2000 -2006 • WBS (and EDMS) used from the project start 27 main branches; varying granularity 2 -(4) levels; total 112 entries in WBS N. B. CNGS-EDMS still extremely useful today • EVM (PPT) introduced at the end of 3 rd year would have been much easier at project start approx. 400 workunits N. B. PPT-CNGS still sometimes useful today 33