Current Progress • Solving installation issues in grid node in Egypt. • Registering the grid site in Egypt on GOCDB. • Learning Ansible is attempted to automate IT by making deploying, configuring, and updating software on one machine like doing it on thousand of machines. • To use Ansible we have to configure playbooks. Those playbooks are the files which contain the commands that will deployed on the machines. • Test deploying grid node with Ansible.
Work Package Three Progress Perspectives and schedules Selection and Knoweldge training of grid Selection of transfer to the management team. the grid team WP 3 team in France and Italy. administration assistance to facilitate their travel to Pre. Europe. Production test of tier 3 gride node. 3 2 Production of tier 3 gride node. 4 Continue formations at LLR. 6 5 Pre. Production test of tier 2 gride node. Production of tier 2 gride node. 1 May-Aug Sep-Nov 2013 Dec-Feb Mar-Jun Jul-Sep 2014 Oct-Dec
Current status • Currently Grid node is up and working with some issues • The grid is consisting from the following 1. One machine acts as a BDII_SITE. 2. One machine acts as a UI. 3. One machine acts as a CE. 4. One machine acts as a WN. 5. One machine acts as a DPM_MYSQL. 6. One machine acts as a DPM_DISK. 7. One machine acts as a SQUID. • All the machines are installed on Physical machines.
Current status • All the machines have the following specs: CPU Two Quad core processor, Intel(R) Xeon(R) CPU E 5345 @ 2. 33 GHz x 86_64 Arch, with 4 M L 2 cash HD 320 Gb Ram 16 G Display (AMD/ATI) ES 1000 • Also we have two virtual machines acting as TOP-BDII and UI. • The site is now registered on GOCDB under this link: https: //goc. egi. eu/portal/index. php? Page_Type=Site&id=961 • It is important to mention that all the services registered on GOCDB are monitored with Africa. Arabia ROC in South Africa. • We have one last issue with the servers certificates.
- Slides: 6