WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Didier Voulot : : Operation Athos integration

WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Didier Voulot : : Operation Athos integration into Swiss. FEL operation Athos Machine Commissioning Workshop, 1 February 2019

Experience from first Athos operation • Seven dedicated Athos shifts in 2018 • Some

Experience from first Athos operation • Seven dedicated Athos shifts in 2018 • Some important goals already achieved - Establish set-up procedure for 2 bunch operation - Develop LLRF tools for second bunch phase/amplitude tuning - Demonstrate acceleration of 2 bunches in the same RF macro-pulse - Establish preliminary optics for Athos dogleg - Commission of emittance measurement at the Athos branch - Demonstrate kicker operation with 2 -bunch and Aramis lasing - Basic commissioning of diagnostics with 2 bunch and Athos diagnostics (BPM, BCM/CDR, ICT, loss monitors) • Problems/limitations - DRPS limits are very low for Athos operation (will get better when the new shielding is taken into account) - Need orbit feedback in Athos Page 2

2 -bunch timing set-up 1. DWCM: rough adjustment, correct RF bucket 2. Gun phase

2 -bunch timing set-up 1. DWCM: rough adjustment, correct RF bucket 2. Gun phase scan for both bunches, adjust laser delay of second bunch 3. Fine tuning with BAM Page 3

Kicker operation with 2 -bunch and lasing Bunch 1 to Aramis dump Bunch 2

Kicker operation with 2 -bunch and lasing Bunch 1 to Aramis dump Bunch 2 to Athos stopper Bunch 2 ON Gas det signal: 9 ke. V, 150 u. J Page 4

Objectives 2019 • April 2019: 2 -bunch operation permanently allowed => Athos independent of

Objectives 2019 • April 2019: 2 -bunch operation permanently allowed => Athos independent of Aramis operation • November 2019: Bunch 2 at end of dog-leg should have quality for lasing • December 2019: transmission to beam dump and 1 st lasing 2 nd bunch permanent Optics dogleg ready for lasing Lasing Page 5

Requirements for the April milestone Tool/panel Priority DRPS • • Validate new limits Check

Requirements for the April milestone Tool/panel Priority DRPS • • Validate new limits Check compatibility with Aramis operation Laser • Provide fix configuration: Alcor for Aramis (B 1), Jaguar for Athos (B 2) LLRF • Make timing and pulse length settings permanent • Provide operation tools for the second bunch phase/amplitude tuning • Test impact on Aramis lasing and RF performances Compression monitor • • Timing • • Orbit feedback • • Comment 1 shift, maybe after the SD, change detector layout Jaguar: max 10 Hz, best effort after April SD 2 -3 shifts Ensure safe operation of CDR/BCM with 2 bunches Provide compression signal for bunch 2 (same compression and charge) 4 shifts Provide independent rep. rate control for the 2 bunches Acceptable to have fixed destination and laser-bunch association Very limited resources in 2019. Complete timing upgrade not possible Set-up feedback tool Test with beam 1 -2 shifts, can be done after the April shutdown Page 6

Estimated required shifts for April milestone DRPS 1 LLRF 2 -3 BCM/CDR 4 Total

Estimated required shifts for April milestone DRPS 1 LLRF 2 -3 BCM/CDR 4 Total 7 -8 (36 MD shifts available until April shutdown) Page 7

Tools and panels for Athos Tool/panel Priority Comment Orbit feedback 1 BPM overview 1

Tools and panels for Athos Tool/panel Priority Comment Orbit feedback 1 BPM overview 1 Already available Loss monitor overview 1 Adapt existing tool Beam rate control 1 Impact many panels/tools Kicker control 1 Already available Optics scaling 2 Already available Save and restore 2 Undulator panel 2 End of 2019 Photon diagnostics 2/3 End of 2019 Swiss. FEL overview panel 3 2020 (Many panels and tools need modification/adaptation for Athos) Page 8

Control room organization • Do we need a specific organization for Athos? Probably not…

Control room organization • Do we need a specific organization for Athos? Probably not… - Same team to operate both FELs - Aramis operation should have priority • Need to define fixed console layout • Adapt the Swiss. FEL overview or new overhead screen Page 9

Commissioning planning and organization • Technical issues -> STC • Shift allocation - If

Commissioning planning and organization • Technical issues -> STC • Shift allocation - If Athos independent of Aramis -> Athos commissioning team (Romain, Eduard, Didier) - If not -> SPP • Athos commissioning planning / progress report -> new dedicated meeting ? (Eduard) Page 10

Wir schaffen Wissen – heute für morgen • Athos operation independent of Aramis •

Wir schaffen Wissen – heute für morgen • Athos operation independent of Aramis • Establish Athos as routine operation Page 11