Welcome Town of Taber Emergency Services Building Information
Welcome
Town of Taber Emergency Services Building Information Session Thursday, March 21, 2019
Purpose of the Information Session • To provide the community with an overview of the new location for the Emergency Services Building • To respond to information-based questions or clarification questions • To provide information regarding next steps of how the Town will move forward with the Emergency Service Building Project
Agenda • Welcome • Session Overview • Session Hopes & Expectations (Table Discussions) • Information Update (Presentation) • Dialogue about the Project (Table Discussions) • General Comments, Q & A (Facilitated Discussion) • Closing & Adjournment
Effective Participant Conversations • • We minimize distractions. We balance air time fairly. We speak one at a time. We listen to understand before we speak. We can disagree respectfully. We can change our mind. We will respect personal and group privacy when using social media tools.
Session Hopes & Expectations (table discussion) • Introductions around the table • Discuss what brought you to the meeting tonight • Report Back
Town of Taber Emergency Services Building Information Session Thursday, March 21, 2019
What Council has heard… Extensive past public engagement has shown us • Not in a public park • Not near our schools • Not in a residential area
What Council has done about it… With public input in mind, Council has selected a new location • In the downtown • Covering the ten minute response area for all residential development in Taber • Not in the vicinity of residential development, schools or parks • In a revenue generating existing leasehold facility
New Site Location • Lots 1 -6, Block 15, Plan 5638 L • 5207 49 Avenue • Current Canada Post Building
10 -Minute Response Time
Project Timeline • Conditional offer to purchase in place, conditions to be met by July 1, 2019 • Conceptual designs in place • Funding proposal developed – tender dependent • Public Information Session – today
Project Timeline • Tender for building construction to be completed by end of June (earlier date may be possible) • Potential Award by July 1, 2019 (earlier date may be possible) • Construction to follow (startup dependent on earlier dates – hopeful for 2019 construction season but potentially spring of 2020
Project Funding Total cost for the Project • Ferguson Estate $1, 400, 000 • Energy Conservation Fund (Green efficiency) • 2019 MSI • Offsite Levy $1, 200, 000 Total approved budget • Savings - 2018 approved projects $4, 500, 000 $ 496, 000 $ 404, 000 $3, 500, 000 $ 1, 000 (internal borrowing) Variance (Shortfall) $ 0
Internal Borrowing Fund • Funding beyond the $3. 5 million is proposed to be borrowed from internal sources. • This internal source funding will be repaid over a period of years depending on the shortfall. • The funding sources for repayment will be lease arrangements already in place with Canada Post and Alberta Health Services.
Next Steps • Finalize design concepts and prepare tender package • Potential award of tender • Waiver of conditional sale agreement • Construction of new Emergency Services Building
Questions and Implementation Considerations (table discussion) • What questions do you have about the project? • What else might need to be considered as the Town moves forward towards implementation? • Report Back
Thank you for coming out tonight