WEIS MARKET TRIALS Helping our members work together
WEIS MARKET TRIALS Helping our members work together to keep the lights on. . . today and in the future. Southwest. Power. Pool SPPorg southwest-power-pool
MARKET TRIALS WEEKLY STATUS MEETING SEPTEMBER 14, 2020 Helping our members work together to keep the lights on. . . today and in the future. Southwest. Power. Pool SPPorg southwest-power-pool 2
AGENDA • Market Trials Overview • Test Checklists • MTE Testing and Data Submission • WEIS Market Trials Scenarios • Markets Scorecard • Settlements Scorecard • Known Issues Report • Recap of Key Points and Next Steps • Questions 3
WEIS MARKET TRIALS OVERVIEW CHRIS BALDWIN 4
MARKET TRIALS CALENDAR Date Party Action June 3, 2020 SPP MPs MP Testing Kick-Off Call and walk through of system changes June 1, 2020 – June 30, 2020 MPs set up APIs and listeners in MTE, LSAs set up users with certificates and roles in MTE July 1, 2020 – July 31, 2020 SPP MPs Connectivity Testing in MTE July 20, 2020 – January 18, 2021 SPP MPs Weekly WEIS Market Trials test communication calls August 3, 2020 – November 20, 2020 SPP MPs Tues & Thurs each week: Structured Testing in MTE Wed & Fri each week: Unstructured Testing in MTE August 3, 2020 – November 20, 2020 (Mon. , Tue. , Fri. ) SPP MPs BAs West RC Deployment Testing in MTE November 23, 2020 – December 9, 2020 MPs set up APIs and listeners in Production, LSAs set up users with certificates and roles in Production November 23, 2020 – December 9, 2020 SPP MPs PRD Connectivity Testing and Verification December 10, 2020 – January 14, 2021 SPP MPs Parallel Operations testing in Production February 1, 2021 SPP MPs WEIS Market Go-Live 5
MTE TESTING & DATA SUBMISSIONS DOUG CLARK 6
MTE TESTING & DATA SUBMISSIONS • Continue updating (as appropriate): • Resource parameters (Ramp Rates, Limits) and dollarbased offers • Ensure real-time data (Control Mode via ICCP) is available to SPP • Resource (Commit Status) and Ancillary Service (Fixed OR) Plans • Enter tags using appropriate sources and sinks • Submit realistic meter data on a regular basis and review meter reports to gain familiarity with the meter data process • Contact SPP via RMS with any questions and issues 7
NEW FOR THIS WEEK • Sign Up for Repricing Scenario Notification • Login to your account at SPP. org • Select “SPP WEIS Repricing Notification” • Complete Markets and Settlements Base Case test checklists (Does not include Attestations) • New Due Date: COB September 30, 2020 8
WEIS MARKET TRIALS SCENARIOS DOUG CLARK 9
STRUCTURED SCENARIOS * Requires specific MP actions to complete the scenario. See Structured Scenario Test Guide WEIS Market Trials folder on SPP. org for more information. 10
LAST WEEK (8/31 -9/11) • Mitigation • 9/4: Identified/repaired issues preventing mitigation • 9/8 & 9/10: Mitigation on reference resources • OOME & URD • 9/1, 3, 8, 10: Various types of OOMEs placed on fully participating and partial participating resources • Updates to Market Software include Marginal Losses & Pivotal Supplier Mitigation 11
THIS WEEK (9/14 -9/18) • LMP Repricing & URD • SPP will initiate Repricing for the Operating Days of 9/15. • Settlement statements will most likely include URD due to resources not following dispatch • To Do Items for MPs: • Sign Up for the WEIS Repricing Exploder • Keep updating offers & tags as necessary, submitting meter data to settlements and monitoring statements 12
NEXT WEEK (9/21 -9/25) • LMP Repricing & URD (continued) • SPP will initiate Repricing for the Operating Days of 9/22. • Offer Cap • 9/24, 9/29, 10/1, & 10/6: Testing energy offer cap functionality for offers in excess of the safety net offer cap ($1000/MWh). • Begin reviewing Structured Test Guide for additional information 13
MARKETS SCORECARD DON MARTIN 14
MP MARKET METRICS • % Commitment Status Conflicts • SCADA MW vs Commitment Status • MUI/API Submissions (Operations) • Frequency and type • Quality of Market Data • Seeded resource data replacement • ICCP submissions complete • Control Status (CMOD) conflicts, etc. • Timely Test Checklist & Attestation Submissions 15
CURRENT STATUS 16
SETTLEMENTS SCORECARD STEVE WHITE 17
SETTLEMENTS SCORECARD • Scorecards are updated each week on Friday and include updates through the current Thursday’s settlement postings. • Posted to the WEIS Market Trails and ‘Phase 2’ folder: https: //spp. org/spp-documents-filings/? id=235151. 18
SETTLEMENTS SCORECARD 19
KNOWN ISSUES LOG CHRIS BALDWIN 20
KNOWN ISSUES LOG (CLOSED ISSUES) • SPP will publish Market Trials materials to the WEIS Market Trials folder on SPP. org. 21
KNOWN ISSUES LOG (OPEN ISSUES) 22
KEY POINTS • Structured / Unstructured Testing Period: August 3 – November 20 • Submit all inquiries through the SPP Request Management System (RMS) using the WEIS Market Quick Pick and Subtype 1 of Market Trials. • Return the following documents as soon as completed via RMS. Due no later than November 20: • WEIS WRTBM Market Test Cases • WEIS WRTBM Settlement Test Cases • Structured/Unstructured Test Completion Attestation Statement • Deployment Test Completion Attestation Statement • Next Steps… 23