Wave 2001 Mildred van der Zwan Architect TUDelft

  • Slides: 40
Download presentation
Wave 2001 Mildred van der Zwan Architect - TUDelft Valerie Ou Engineer – Stanford

Wave 2001 Mildred van der Zwan Architect - TUDelft Valerie Ou Engineer – Stanford Diego Aviles Construction Manager Stanford Daniel Kwon Apprentice – Stanford Brooke Barrett Owner - DPR Wave 2001

Architect’s Vision • Flexible building and workplaces • Central areas for interaction • Ocean

Architect’s Vision • Flexible building and workplaces • Central areas for interaction • Ocean view • Context Wave 2001

Matrix Architect Engineer CM New Design 1 • Undeveloped circulation • High Tech •

Matrix Architect Engineer CM New Design 1 • Undeveloped circulation • High Tech • Clear structural grid • Possible difficulty casting slope slab • Excavation required for Auditorium • High cost of the exterior (glass) • Possible savings by exposing slab New Design 2 • Good organization, elegant, interesting for good detail • Structure integrated with architecture • No visual intrusion to architectural components • High learning curve due to the symmetry of the structure • No excavation required for auditorium Wave 2001

3 D Model Wave 2001

3 D Model Wave 2001

Floor 1 auditorium classrooms lab seminar computer offices Wave 2001 lounge storage MEP elevator

Floor 1 auditorium classrooms lab seminar computer offices Wave 2001 lounge storage MEP elevator

Floor 2 auditorium classrooms lab seminar computer offices Wave 2001 lounge storage MEP elevator

Floor 2 auditorium classrooms lab seminar computer offices Wave 2001 lounge storage MEP elevator

Floor 3 auditorium classrooms lab seminar computer offices Wave 2001 lounge storage MEP elevator

Floor 3 auditorium classrooms lab seminar computer offices Wave 2001 lounge storage MEP elevator

A Section B B” A” A A” B B” Wave 2001

A Section B B” A” A A” B B” Wave 2001

Building Performance Large classrooms: Sloped, 2 exits, 65 seats Auditorium: sloped, 5 exits, 197

Building Performance Large classrooms: Sloped, 2 exits, 65 seats Auditorium: sloped, 5 exits, 197 seats All classrooms, LAB, Computer: ocean view All offices: daylight Wave 2001

Structural Requirements Design wind speed: V 33 = 80 mph • NBCC (National Building

Structural Requirements Design wind speed: V 33 = 80 mph • NBCC (National Building Code of Canada) • Most severe case: North wind Wind parallel to corridor Design snow load: • Uniformly distributed load • 25 psf Wave 2001

Final Structural Solution Beam : W 18 X 35 Girder: W 24 X 76

Final Structural Solution Beam : W 18 X 35 Girder: W 24 X 76 Column: W 14 X 48 • Steel Moment resisting frame • 3” 20 GA full composite slab • 12 m girder, column/column span Wave 2001

Foundation Design • Spread footings : 1. 5 m X 60 cm • Grade

Foundation Design • Spread footings : 1. 5 m X 60 cm • Grade beams: 30 cm X 60 cm Wave 2001

Architectural/Structural Integration Column!! • No structure element intrusion in architectural space in 1 st

Architectural/Structural Integration Column!! • No structure element intrusion in architectural space in 1 st and 2 nd floor • One column intruded flexible offices are, but acceptable to architect Wave 2001

Architectural/Structural Integration Architect Engineer • Elevator Check for beam & girder location and frame

Architectural/Structural Integration Architect Engineer • Elevator Check for beam & girder location and frame around slab opening • Sloped slab Design supporting structure for gravity load Wave 2001

Final Roof Design: Structure N • Conventional Truss: Double angles • Truss Spacing: 20’

Final Roof Design: Structure N • Conventional Truss: Double angles • Truss Spacing: 20’ oc • Purlin Spacing: 5’oc EW, 7 oc NS • Simple connections to main structure Wave 2001

Roof Design: Truss Configuration N WIND L 2 X 2 ½ X 5/16 L

Roof Design: Truss Configuration N WIND L 2 X 2 ½ X 5/16 L 2 X 2 ½ X 3/16 • Sloping N-S direction WIND • Suction effect due to North wind at wing trusses—uplifting L 2 X 2 ½ X 3/16 • Compression on end trusses Wave 2001

Roof Design: Truss Configuration con’t N WIND L 2 X 2 ½ X 3/16

Roof Design: Truss Configuration con’t N WIND L 2 X 2 ½ X 3/16 • Sloping E-W direction • Wind parallel to ridge suction effect L L 2 X 2 ½ ½X X 3/16 • Uplifting at connections Wave 2001

Roof Design: Truss Configuration con’t • Purlin size: C 9 X 20 • 1

Roof Design: Truss Configuration con’t • Purlin size: C 9 X 20 • 1 ½” steel deck • Expanded perlite and fibers impregnated with integral asphalt waterproofing • 2 hr fire rating with 1” slab Wave 2001

Roof Connections Truss / Truss connection Deck/channel/truss connection Truss member connection Truss end connection

Roof Connections Truss / Truss connection Deck/channel/truss connection Truss member connection Truss end connection Wave 2001

Structure Connections Girder to column connection Moment connection Beam to column connection Column to

Structure Connections Girder to column connection Moment connection Beam to column connection Column to footing connection Wave 2001

Structural Analysis: • P-d effect included • Story drift : 1. 2 in •

Structural Analysis: • P-d effect included • Story drift : 1. 2 in • Truss element forces are verified by MASTAN • Large horizontal shear force • Average element force at truss/structure connection ranging from 10 kips to 50 kips Wave 2001

Pro’s and Cons Pro’s Cons • Minimum space intrusion • Deep beams and girders

Pro’s and Cons Pro’s Cons • Minimum space intrusion • Deep beams and girders limiting floor to ceiling height • Flexible future upgrades • Conservative structural member sizes • Simple structure Wave 2001

Construction Objectives • Budget: $5. 5 Million in 2015 (4. 6 Million PV) •

Construction Objectives • Budget: $5. 5 Million in 2015 (4. 6 Million PV) • Time Constraints: • 1 year (construction duration ) • Computer Lab Occupied by May 30, 2016 • Preserve Architecture Wave 2001

Site Plan Wave 2001

Site Plan Wave 2001

Construction Equipment Crane Dump Truck Concrete Pump Truck Excavator Material Handler Wave 2001

Construction Equipment Crane Dump Truck Concrete Pump Truck Excavator Material Handler Wave 2001

4 D Simulation Wave 2001

4 D Simulation Wave 2001

Schedule - Milestones Milestone 1 Foundation (week 5) Wave 2001

Schedule - Milestones Milestone 1 Foundation (week 5) Wave 2001

Schedule - Milestones Milestone 2 Set HVAC Equipment (week 18) Wave 2001

Schedule - Milestones Milestone 2 Set HVAC Equipment (week 18) Wave 2001

Schedule - Milestones Milestone 3 Exterior Closure (week 24) Wave 2001

Schedule - Milestones Milestone 3 Exterior Closure (week 24) Wave 2001

Schedule - Milestones Milestone 4 Project Completion (week 31) Wave 2001

Schedule - Milestones Milestone 4 Project Completion (week 31) Wave 2001

Schedule Analysis • Total Pre-construction Time: 8 months • Total Construction Duration: 7 months

Schedule Analysis • Total Pre-construction Time: 8 months • Total Construction Duration: 7 months • Milestones: – Foundation (by June 30, 2015) – Exterior Closure (by November 30, 2015) – Project Completion (by January 15, 2016) • Time savings achieved by: – Simple Foundation – Steel Structure – On time Enclosure Wave 2001

Construction Estimate $611, 176 $3, 756, 820 Wave 2001

Construction Estimate $611, 176 $3, 756, 820 Wave 2001

Cost Distribution Wave 2001

Cost Distribution Wave 2001

Cost Analysis • Where are the main costs? $3, 756, 820 $3, 590, 600

Cost Analysis • Where are the main costs? $3, 756, 820 $3, 590, 600 – Superstructure (Roof-Truss) – Larger Surface Area (2, 736 sf) • How did we save? – Simple Foundation – Avoided Mass Excavation (Bedrock) – Local Wood Facade Wave 2001

Equipment Specifications (1) Chiller • 60 Tons Nominal Capacity • Dimensions: • Length =

Equipment Specifications (1) Chiller • 60 Tons Nominal Capacity • Dimensions: • Length = 9. 5 ft • Width = 7. 3 ft • Height = 6. 5 ft • Weight = 2465/3010 lbs Wave 2001

Equipment Specifications (2) Air Handling Unit • 120 Tons with 20, 000 CFM airflow

Equipment Specifications (2) Air Handling Unit • 120 Tons with 20, 000 CFM airflow • Dimensions: – Length = 12. 4 ft – Width = 6 ft – Height = 8 ft( – Weight = 8, 000 lbs Wave 2001

MEP Layout Floor 1 Floor 2 Wave 2001 Floor 3

MEP Layout Floor 1 Floor 2 Wave 2001 Floor 3

Team Process: Roof Design A E C Wave 2001

Team Process: Roof Design A E C Wave 2001

Lessons Learned • Explanation of concepts in other disciplines • Good design requires interaction

Lessons Learned • Explanation of concepts in other disciplines • Good design requires interaction and collaboration • Technology is only as good as the user Wave 2001

Thank You A Carel Weeber (TUDelft), Rutger Smook (TUDelft), Sevil Sariliydize (TUDelft), Dennis Scott

Thank You A Carel Weeber (TUDelft), Rutger Smook (TUDelft), Sevil Sariliydize (TUDelft), Dennis Scott (MBT), David Bendett (MBT), Bart Luiten (HBG), Bart van der Pot (HBG), Cor Notenboom (HBG) E Greg Luth (KLAA), Shilin Jiang (KLAA), Eduardo Miranda (Stanford) C Eric Horn (Webcor Builders), Bob Tatum (Stanford) and Eduardo Miranda (Stanford) Wave 2001