VILLAGE OF EAST AURORA SYCAMORE STREET WATER IMPROVEMENTS
- Slides: 13
VILLAGE OF EAST AURORA SYCAMORE STREET WATER IMPROVEMENTS
INTRODUCTIONS Clark Patterson Lee 26 Mississippi Street, Suite 300 Buffalo, NY Steven R. Tanner, P. E. – Senior Associate, Phone: (716) 2184741 Email: stanner@clarkpatterson. com Kim Vongries, P. E. – Project Engineer, Phone: (716) 218 -4734 Email: kvongries@clarkpatterson. com Village of East Aurora Matt Hoeh – Superintendent, Department of Public Works Email: Matt. hoeh@east-aurora. ny. us, phone: (716) 652 -6057 Bryan Gazda – Village Administrator Email: Bryan. gazda@east-aurora. ny. us, phone: (716) 6526000
Sycamore St. Oakwood Ave. Linden Ave. South St. PROJECT AREA
PROJECT COMPONENTS • NEW 8” CLASS 52 DUCTILE IRON PIPE AND FITTINGS • NEW WATER SERVICES TO THE RIGHT-OF-WAY, INCLUDING NEW CURB STOP AND CURB BOX, AND CONNECT TO EXISTING SERVICE LINES • SERVICES UNDER THE ROAD SHALL BE DIRECTIONALLY DRILLED TO LIMIT STREET DISTURBANCE • INSTALL NEW FIRE HYDRANTS AND REMOVAL OF OLD • REMOVAL OF 5 TREES AS RECOMMENDED BY INDEPENDENT ARBORIST HIRED BY THE VILLAGE • TUNNELING UNDER REMAINING TREES ALONG THE ALIGNMENT • SOME AREAS OF SIDEWALK TO BE REPLACED • DRIVEWAY APRONS TO BE REPLACED IF IMPACTED
PROJECT SCHEDULE • ADVERTISE TO BID: SECOND WEEK OF FEBRUARY • BID OPENING: MARCH 10, 2017 • VILLAGE AWARD OF BID: MARCH 20, 2017 • ESTIMATED START OF CONSTRUCTION: MID-APRIL, 2017 • PROJECT SUBSTANTIALLY COMPLETE: END OF JULY, 2017 • RESTORATION COMPLETE AND READY FOR FINAL PAYMENT: END OF AUGUST, 2017
DURING CONSTRUCTION • DRIVEWAY ACCESS MAY BE LIMITED FROM TIME TO TIME CONTRACTOR WILL BE REQUIRED TO NOTIFY RESIDENTS IN ADVANCE. • THERE WILL BE DUST. CONTRACTOR IS REQUIRED TO MINIMIZE THIS, HOWEVER, CONSTRUCTION WORK IS DIRTY WORK. • WATER SHOULD ONLY BE SHUT DOWN WHEN THE CONTRACTOR SWITCHES THE SERVICE FROM THE OLD MAIN TO THE NEW MAIN, AND NOTIFICATIONS WILL BE MADE. SHUT DOWN SHOULD LAST NO LONGER THAN 4 HOURS. • ACCIDENTS DO HAPPEN. CONTRACTOR CAN HIT UNMARKED OR INCORRECTLY LOCATED SERVICES. THEY WILL NOTIFY RESIDENTS IF HOME AND PROCEED WITH REPAIRS.
PROJECT DRAWINGS
PROJECT DRAWINGS
PROJECT DRAWINGS
PROJECT DRAWINGS
PROJECT DRAWINGS
CONTACTS DURING CONSTRUCTION Clark Patterson Lee Kim Vongries, P. E. – Project Engineer Phone: (716) 218 -4734 Email: kvongries@clarkpatterson. com Steve Tanner, P. E. – Senior Associate Phone: (716) 218 -4741 Email: stanner@clarkpatterson. com Clerk of the Works: To be Determined Village of East Aurora Matt Hoeh – Superintendent, Department of Public Works Email: Matt. hoeh@east-aurora. ny. us, phone: (716) 652 -6057 Bryan Gazda – Village Administrator Email: Bryan. gazda@east-aurora. ny. us, phone: (716) 652 -6000
QUESTIONS?
- Water and water and water water
- Driveway installation east aurora, ny
- I vocab
- Drop and roll seed dispersal examples
- Sycamore tree restorative justice
- Sycamore bible bowl
- Sycamore crossing hercules
- 275 east main street frankfort ky 40621
- Go direkt
- 900 east washington street
- West north west wind direction
- Kalahari desert on africa map
- East is east and west is west
- Improvements & betterments