Vigyan Ashram (VA) INDUSA Infrastructure updates Annual Update for 2014 -2015 Budget Proposal 2015

Vigyan Ashram (VA) INDUSA Infrastructure updates Annual Update for 2014 -2015 Budget Proposal 2015 -2016

BEFORE THE PROJECT PRESENT BUILDING

BEFORE THE PROJECT PRESENT BUILDING

2013 -2014 INDUSA Fund Utilization Approved Rs. 12, 10, 000 Individual donations for the

2013 -2014 INDUSA Fund Utilization Approved Rs. 12, 10, 000 Individual donations for the project Rs. 19, 30, 355 Completed kitchen construction expenses Rs. 20, 48, 502 Remaining kitchen work Rs. 8, 93, 250 INDUSA Fund History 2013 -2014 USD 11, 000 for computer practical training institute USD 10, 000 for OER generation 2013 -2014 USD 20, 000 for kitchen construction

2013 -2014 INDUSA Fund Utilization Sr No Head Fund/ Donation Expences 1 Asha/ Indusa

2013 -2014 INDUSA Fund Utilization Sr No Head Fund/ Donation Expences 1 Asha/ Indusa 1210000 2 Loksatta Donation 1930355 3 Kitchen Construction 2048502 3140355 Sub-head wise details * Kitchen meason labour charges ( Suresh Jadhav/Narsing 1) 294115 2 Kitchen Furniture 104125 3 Kitchen Construction Material Cost 4 Kitchen Light Fitting Cost Balances 1348101 197944 5 Kitchen construction Travelling cost 13566 6 Kitchen Capital Material 90651 2048502 1091853

2013 -2014 INDUSA Remaining work Sr No Material / Work nature Quantity (Unit Construction)

2013 -2014 INDUSA Remaining work Sr No Material / Work nature Quantity (Unit Construction) Cost / Unit Total Cost 1 Construction of straircase 193 Sq Ft 250 Rs/ Sq Ft 48250 2 Fabrication work at First Floor 800 Sf T 450 Rs/ Sq Ft 360000 3 Side wall of hall 3 Brass (300 Sq Ft) 500 Rs Sq Ft 150000 4 Floor tiles 8 Brass 5000 Rs/ Brass 40000 5 Windows and door 6 Electrification Aprox 10000 7 Coloring Aprox 15000 8 fall-ceiling 200 Rs/ Sq Ft 160000 9 Other Misc 60000 50000 893250 Cost Rs/ Unit area 1117

INDUSA Proposal 2015 -2016 • • Construction new classroom and open hall at Vigyan

INDUSA Proposal 2015 -2016 • • Construction new classroom and open hall at Vigyan Ashram; 2000 sq. ft. in a two story building with ground and first floors (each 1000 sq. ft. ). Existing room which VA uses as a classroom was old Poultry shed having an area of 630 sq. feet. VA uses this room as a multipurpose room like classroom, hall for cultural events, etc. The existing structure is now beyond the repair and at depleting stage so needs reconstruction. As it was old poultry; the height of structure is much low and ventilation is not proper. In summer season when temperature rises up, we are unable (uncomfortable) to use the room. Due to low structural height, windows are inefficient to provide sunlight and fresh air. We are unable to fix our LCD projector permanently due to unavailability of proper space. We don’t have proper door and storage at current room, therefore always need to carry LCD projector from office when it requires. The room is not designed as classroom hence backbenchers could not see the presenter and presentation.

INDUSA Proposal 2015 -2016 • • • We are unable to fix our LCD

INDUSA Proposal 2015 -2016 • • • We are unable to fix our LCD projector permanently due to unavailability of proper space. We don’t have proper door and storage at current room, therefore always need to carry LCD projector from office when it requires. The room is not designed as classroom hence backbenchers could not see the presenter and presentation. We celebrate different festivals and on these occasions students use different musical instruments like Dhol, drum, zanj, lezim, tabla, mrudang, and harmonium pump organ, and many more. All these instruments are stored on the backside of the classroom. We do not have proper storage room for those. VA believes in ‘Learning while doing’ philosophy and organizes different training programs and workshops. So we need a hall to organize the program/workshops. Currently we need to move the benches from the classroom to get it converted into the hall. In order to overcome the problem we are proposing ground floor + 1 building. In the reconstructed building classroom will be at the ground floor and on first floor will be a hall plus some storage space for musical instruments (total 2000 sq ft. ) At present, we also use the existing 630 sq. ft. classroom as a dormitory for 30 -35 people by removing benches outside.

INDUSA Proposal 2015 -2016 • Existing classroom

INDUSA Proposal 2015 -2016 • Existing classroom

INDUSA Proposal 2015 -2016 • The costing is based on our experience of construction

INDUSA Proposal 2015 -2016 • The costing is based on our experience of construction of kitchen. We will get the actual drawing from architect and then will make final costing. • Like our entire previous project, we wish to involve our students in execution of project. • Construction work will begin: 6 – 8 months from receipt of the funds. • We estimate that approx. 60 students will benefit 2 hrs daily basis of the facility. • It will be useful for number of workshops, cultural programs and common assembly of VA throughout the year. • Approx. 200 students for 7 days in a year will use it as a dormitory facility.

INDUSA Budget 2015 -2016 Specifications Height Area Existing Structure Low 630 sq. ft. Proposed

INDUSA Budget 2015 -2016 Specifications Height Area Existing Structure Low 630 sq. ft. Proposed Structure Appropriate 1000 sq. ft. +1000* sq. ft. (* provision is made for future) Material Ventilation Solar System Rain water harvesting Sunlight Classroom and hall Ferro- cement fabricated roof Improper (for poultry) No No Improper- dim 630 sq. ft. classroom cum hall R. C. C. double floor (ground+2) Proper Yes – underground tank Proper and clear Classroom : 1000 sq. ft. at ground flour Hall: 1000 sq. ft. at first flour Second floor: Second Floor: Provision is made in the designing of construction but will not be constructed immediately. Hence funds are not asked for the second floor in this proposal. Dormitory Need to relocate the furniture like benches tables and then we place beds As hall is going to be a dormitory no need to relocate the furniture LCD projector Audio visual system musical instruments Need to carry Don’t have proper storage room Fixed Will have proper storage room At single platform Combined Properly as classroom separate for ladies and gents at each floor Seating Arrangement Washroom and

INDUSA Budget 2015 -2016 Sr. No. Item Per unit * Quantity Total Cost 1

INDUSA Budget 2015 -2016 Sr. No. Item Per unit * Quantity Total Cost 1 Construction cost for new Classroom construction Rs. 1100 per sq. ft * 2000 sq. ft. 22, 000 2 Furniture, light fitting, cupboards, sound and LCD 3 Design / Architect consultancy 4 Travel / admin / miscellaneous TOTAL 3, 000 50, 000 6% 1, 53, 000 27, 03, 000

INDUSA Funds – Intended Utilization KKB family trust grant of USD 25000 (INR 16,

INDUSA Funds – Intended Utilization KKB family trust grant of USD 25000 (INR 16, 75, 000. ) INDUSA-VA Library Fund - INR 50, 000 Hybrid Fitness Therapy book publishing costs - INR 1, 000 Construction of Classroom and Assembly Hall building – INR 15, 25, 000 Remaining amount is to be raised from other sources.

Hybrid Fitness Training book • A book titled, "A Guide to Positive Health with

Hybrid Fitness Training book • A book titled, "A Guide to Positive Health with Hybrid Fitness Training by Kishan Bhatia" based on a draft submitted to VA for copy editing as well as adding original graphics. Book rights will rest with VA and all revenues generated from the sale of this book be used for student activities. Book should interest mixed audience (Americans, Europeans and Indians).