Vacuum chambers supports of ELENA transfer lines SUMMARY
Vacuum chambers & supports of ELENA transfer lines SUMMARY Drawings Raw material Outsourcing or not? Conclusion A. SINTUREL - TE/VSC-BVO
Electrostatic lines to be installed LNE 00 LNE 02 LNE 01 LNE 03 LNE 07 LNE 06 LNE 50 LNE 05 LNE 51 A. SINTUREL - TE/VSC-BVO LNE 04
Drawings First discussion with EN-MME in November 2017 n Job started in January 2018 n Drawings for chambers & supports on Control 1 available on 1 st June 2018 n Vacuum design commitee end of June 2018 n TE-VSC approval on Control 2 end of June 2018 n A. SINTUREL - TE/VSC-BVO
Raw material • Order for Hydroformed bellows on November 2017 • 100% received • Order for Flanges on December 2017 • 90% received • Order for Stainless steel January 2018 • 100% received • Order for Collars/supports on June 2018 • Raw material on week 24 -25 • Order for Edge welded bellows on June 2018 • Foreseen for mid August 2018 A. SINTUREL - TE/VSC-BVO
Outsourcing or not? Production of vacuum chambers & supports Vacuum chambers Outsourcing Specification for manufacturing process with list of possible bidders Departmental Request signed Supports Main workshop Prepare call for tender Wait for quotation from EN-MME A. SINTUREL - TE/VSC-BVO Outsourcing 100% Specification for manufacturing process
Conclusion n Production completed for end of February 19 n Cleaning all the chambers beginning of March 19 n Acceptance test mid March 19 n Installation May 19 n Questions? A. SINTUREL - TE/VSC-BVO