U. S. DEPARTMENT OF ENEGY Resource-Loaded Schedule (RLS) Mu 2 e Independent Cost Estimate

U. S. DEPARTMENT OF ENEGY Resource-Loaded Schedule (RLS) Mu 2 e Independent Cost Estimate F. Leavell Mu 2 e Project Controls Lead 8/26/2014 Mu 2 e Office of Science

Organization of Project Schedule 475 Mu 2 e Project 475. 01 Project Management L

Organization of Project Schedule 475 Mu 2 e Project 475. 01 Project Management L 2 – R. Ray PCS – F. Leavell 475. 02 Accelerator L 2 – S. Werkema PCS - M. Gardner 475. 03 Conv. Construction L 2 – T. Lakowski PCS – M. Gardner 475. 04 Solenoids L 2 – M. Lamm PCS – D. Leeb 475. 06 Tracker L 2 – A. Mukherjee PCS – H. Brown 475. 07 Calorimeter L 2 – D. Hitlin PCS – D. Leeb 475. 08 Cosmic Ray Veto L 2 – C. Dukes PCS – M. Gardner 475. 09 Trigger & DAQ L 2 – M. Bowden PCS – F. Leavell 475. 05 Muon Beamline L 2 – G. Ginther PCS – H. Brown Mu 2 e 2 F. Leavell- Mu 2 e Independent Cost Estimate 8/26/14

Schedule Development • Scope - WBS Dictionary from Level 1 down to Activity •

Schedule Development • Scope - WBS Dictionary from Level 1 down to Activity • Milestones – Tiers – LX = External Milestone – Dictionary for each • Time-phased Logic Network – – 5 -day workweek with holidays Predecessor and Successor for each activity Constraints (104); mostly FY (90) or External Lags – accompanied by a note in P 6 • Resources Loaded – Total Estimated Cost Mu 2 e 3 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Total Estimated Cost (TEC) TEC (P 6/Cobra) Actuals through April 30, 2014 Balance of

Total Estimated Cost (TEC) TEC (P 6/Cobra) Actuals through April 30, 2014 Balance of Project (Originates with Basis of Estimate) Budget Resources Contingency Estimate Uncertainty Factor Mu 2 e 4 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Development of Total Estimated Cost (TEC) Basis of Estimate (BOE) Resources Loaded into Schedule

Development of Total Estimated Cost (TEC) Basis of Estimate (BOE) Resources Loaded into Schedule QC Pricing Cost Book BOE Report Supporti ng Docume nts Mu 2 e 5 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Iterative Process • General – Schedule network created in consultation with responsible party –

Iterative Process • General – Schedule network created in consultation with responsible party – Units obtained from Basis of Estimate – Data check – Are durations and resources reasonable and realistic? – Data check – Has the correct Estimate Uncertainty Factor been assigned? – Data check for accuracy • Critical Path – – Schedules calculated together Critical path analyzed for accuracy Iterations performed, as needed Critical path for each Subproject can also be evaluated Mu 2 e 6 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Resources • Labor – Units in hours – 8 hours/day – Full Time Equivalent

Resources • Labor – Units in hours – 8 hours/day – Full Time Equivalent (FTE) = 1768 hours/year • Material & Services (Nonlabor) – Material • Units in direct dollars (FY 14 Base Year) – Non-Fermi Labor • Other Labs, Universities, Augmented Staff • Units in hours Mu 2 e 7 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Complex Resource Layout Mu 2 e 8 F. Leavell - Mu 2 e Independent

Complex Resource Layout Mu 2 e 8 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Critical Path • Driven by constrained release of FY-16 funds • Goes through Detector

Critical Path • Driven by constrained release of FY-16 funds • Goes through Detector Solenoid (DS) fabrication, delivery, testing and assembly • Then critical path flows through installation of Rail System, installing Muon Beam Stop, Calorimeter Disks, and Tracker on Rail System, and testing their alignment • This is followed by a test of the calibration system and conducting the Cosmic Ray System test • This leads to completion of the final KPP (KPP 3 – Detector System Ready for Commissioning) • Next to critical path also calculated Mu 2 e 9 R. Ray - Mu 2 e Independent Cost Estimate 8/26/14

Critical Path & Major Milestones (pg 1) Mu 2 e 10 F. Leavell -

Critical Path & Major Milestones (pg 1) Mu 2 e 10 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Critical Path & Major Milestones (pg 2) Mu 2 e 11 F. Leavell -

Critical Path & Major Milestones (pg 2) Mu 2 e 11 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14

Summary • The PMB is based on actuals FY-10 through April 30, 2014 and

Summary • The PMB is based on actuals FY-10 through April 30, 2014 and BOEs May 1, 2014 to project completion • Resource loaded schedules are mature • Resources are traceable to BOEs • Durations and resources are reasonable • Estimate uncertainty is identified for each incomplete activity • Critical path is visible and realistic Mu 2 e 12 F. Leavell - Mu 2 e Independent Cost Estimate 8/26/14