Turner Subcontract Closeout Jim Dee, Procurement Compliance Mgr and Carol Silva, Subcontract Administrator May 14, 2009 Turner Contract Closeout Lehman Rev (May 13 -15) J. Dee /C. Silva csilva@slac. stanford. edu
Turner Subcontract Closeout • Distributed a Project Closeout Guide with Forms to ensure systematic final acceptance and all contractual requirements are met. • Notice of Substantial Completion 11/17/2008 • Physical Completion 4/24/2009 Turner Contract Closeout Lehman Rev (May 13 -15) 2 2 J. Dee /C. Silva csilva@slac. stanford. edu
Turner Subcontract Closeout Turner Subcontract Overview DOE Approved Value $95, 640, 600 Available Ceiling $1, 363, 712 Current Total Value (Thru Mod. 81) $94, 276, 888 Trade value $81, 138, 049 Turner fee value $13, 138, 839 Closed FCO Process w/ Mod 80 & deobligated Turner Contract Closeout Lehman Rev (May 13 -15) 3 3 $264, 624 J. Dee /C. Silva csilva@slac. stanford. edu
Turner Subcontract Closeout Pending PCO/COR Status Owner Actions Turner Construction SLAC Facilities SLAC Procurement Total Turner Contract Closeout Lehman Rev (May 13 -15) 4 4 Value 13 $495, 608 1 $27, 048 10 $16, 087 24 $538, 743 J. Dee /C. Silva csilva@slac. stanford. edu
Turner Subcontract Closeout • Retention – Turner retention dollar amount $479, 025 – Total Trades retention dollar amount $5, 821, 383 – NO retention amounts shall be paid without AMD express authorization • No final retention amounts have been released Turner Contract Closeout Lehman Rev (May 13 -15) 5 5 J. Dee /C. Silva csilva@slac. stanford. edu
Turner Subcontract Closeout • Activities – Redline as-built’s sent to Jacobs for Record Drwgs – 23 of 26 trade subcontracts require closeout binders – Turner off-site to SJ Offices – AAA Mediation – Townsend Audit – • Phase II (audit of Western Maint T&M subcontract, etc. ) Turner Contract Closeout Lehman Rev (May 13 -15) 6 6 J. Dee /C. Silva csilva@slac. stanford. edu