Turner Construction Company SLAC LCLS Construction Status Date 10/25/2006 Construction Status 1 Tom Malloy tmalloy@tcco. com
Turner Construction Company Project Safety Schedule Review Tunneling Purchasing Critical Issues Project Information Systems TCCO Senior Management Support Date 10/25/2006 Construction Status 2 Tom Malloy tmalloy@tcco. com
Turner Construction Company Safety First JSA’s and Pre-Task Planning Establishing the Culture of Safety at SLAC Safety Training at Orientation Team Safety: SLAC/TCCO/Subcontractors Date 10/25/2006 Construction Status 3 Tom Malloy tmalloy@tcco. com
Turner Construction Company Project Schedule NTP: August 1, 2006 Start of Construction: September 11, 2006 Mass Excavation Complete: December 28, 2006 Tunneling: Nov. 06 to Nov. 07 Beam Line Complete: Feb. 08 Closeout Complete: June 08 Date 10/25/2006 Construction Status 4 Tom Malloy tmalloy@tcco. com
Turner Construction Company Tunneling Procurement Three bidders Low bidder: Affholder Inc of St Louis – nationally known contractor with excellent safety performance $1 Million savings achieved during negotiation phase Methodology Equipment Support materials Status Submittals Mobilization Portal construction Date 10/25/2006 Construction Status 5 Tom Malloy tmalloy@tcco. com
Turner Construction Company Tunneling Schedule Management Method Progress rates Resources Sequencing Cost Management Geotechnical baseline report Value engineering Schedule of values Issue resolution Disputes review board Date 10/25/2006 Construction Status 6 Tom Malloy tmalloy@tcco. com
Turner Construction Company Purchasing Bid Group 1: Mod Released, Under Contract Bid Group 2: Recommendations Submitted Misc. Packages Scopes Bid with CLOC Re-bid Packages Re-Evaluated Packages Date 10/25/2006 Construction Status 7 Tom Malloy tmalloy@tcco. com
Turner Construction Company Critical Issues Rainy Season Work Indoctrination of New Subs to Safety Culture Tunnel Spoils Traffic Issues & Dewatering Design Change Impacts to Critical Path Date 10/25/2006 Construction Status 8 Tom Malloy tmalloy@tcco. com
Turner Construction Company Information Systems RFI’s Submittals Field Change Orders Turner. Talk Web Based Project Management Document Scanning Date 10/25/2006 Construction Status 9 Tom Malloy tmalloy@tcco. com
Turner Construction Company Project Specific Items SLAC-Turner Team: CFM-UTRs-TCCo-Subs Turner Oversight Support Date 10/25/2006 Construction Status 10 Tom Malloy tmalloy@tcco. com