Triplet string test campaign preparation Triplet string test

  • Slides: 8
Download presentation
Triplet string test – campaign preparation Triplet string test campaign preparation – 06/02/2019

Triplet string test – campaign preparation Triplet string test campaign preparation – 06/02/2019

Intro The purpose of this presentation is to : • describe the tests foreseen

Intro The purpose of this presentation is to : • describe the tests foreseen on the triplet string test • consider new test proposals in view of the previous presentations • share the tentative test planning and resource request

Past test No vacuum – limited instrumentation • Longitudinal friction in the Q 1

Past test No vacuum – limited instrumentation • Longitudinal friction in the Q 1 jacks (nut removed) – see EDMS 2033117 An average longitudinal force of ~550 kg is required to displace a “free” Q 1 magnet • Longitudinal jack body deflection (with jack nut on) • Q 2 cold mass longitudinal position range Given its supporting scheme, a longitudinal position uncertainty exists on the Q 2 cold mass. It was measured to be ~6. 5 mm longitudinal – radial/vertical dispersion are being investigated (EN/SMM)

Proposed test – without vacuum Magnet in the nominal longitudinal position • Tie-rod ears

Proposed test – without vacuum Magnet in the nominal longitudinal position • Tie-rod ears deflection when in operational conditions (Interconnection closed – in nominal and non-conformant situations) • Calibration of the relation between the Q 1 longitudinal position and the force on each tie-rods (forced by using the nut of Q 1 D – limited load) • Realignment tentative without vacuum – vacuum vessel misalignment vs. tie-rod loading

Proposed test – with vacuum Magnet in the nominal longitudinal position • Tie-rod ear

Proposed test – with vacuum Magnet in the nominal longitudinal position • Tie-rod ear deflection when under vacuum (using dial gauges) with the tie -rod instrumentation on (strain gauges) • Realignment trial on each jack to see the jack load evolution, tie-rod load evolution and triplet realignment kinematic in a nominal situation • Successive realignment to see potential magnet longitudinal position drift Is there a progressive backward drift of the magnet ?

Proposed test – with vacuum Magnet in the extreme longitudinal position (jack loaded) The

Proposed test – with vacuum Magnet in the extreme longitudinal position (jack loaded) The jack loading will be controlled by progressive unloading of the tie-rods (a safety stop will be implemented on the Q 1). • Realignment test on each jack to see the jack load evolution, tie-rod load evolution and triplet realignment kinematic Depending on the results of this test and the result of past tests, a consolidation solution will be devised and proposed for implementation.

Test recap Test proposal Instrumentation required Acquisition system Planned test start date Resource required

Test recap Test proposal Instrumentation required Acquisition system Planned test start date Resource required Longitudinal friction in Q 1 None No Done None Longitudinal jack body deflection None No Done None Q 2 cold mass position range Laser tracker EN/SMM No Finished yesterday EN/SMM (thank you Vivien !) Tie-rod ears deflection No (Dial gauges) No Next week (+1) None Q 1 position vs. force on tie-rods Tie-rod strain gauges (DOMS preferable) Preferable Week 8 or 9 (+2/3) EN/MME (strain gauge installation + output) Realignment tentative without vacuum Tie-rod strain gauges (WPS preferable or laser tracker) Preferable Week 9 -10 (+3/4) EN/SMM (WPS or laser tracker) Tie-rod ear deflection under vacuum Tie-rod strain gauges DOMS Yes Week 11 -15 (+5 +10) EN/SMM (DOMS installation + output, Acquisition set up) Realignment trial on each jack Tie-rod, DOMS, WPS, Load cells Yes Week 11 -15 (+5 +10) EN/SMM (Load cell installation, motorized jack) Successive realignment to assess the position drift Tie-rod, DOMS, WPS, Load cells Yes Week 11 -15 (+5 +10) EN/SMM (motorized jack) Blocked jack – realignment trial Tie-rod, DOMS, WPS, Load cells Yes Week 15 -19 (+10 +15) EN/SMM (motorized jack)

Conclusion • This test program should clarify the working conditions of the triplet string

Conclusion • This test program should clarify the working conditions of the triplet string in the current installation. • From there we will have hopefully a clear direction to : • • design a consolidation solution implement it in b 181 review its adequacy propose it to the management