Totem Gas Systems T 1 T 2 F

  • Slides: 14
Download presentation
Totem Gas Systems ( T 1 , T 2 ) F. Hahn and S.

Totem Gas Systems ( T 1 , T 2 ) F. Hahn and S. Haider PH / DT 1 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1

Outline Work package General layout and functionality – Mixer unit – Gas Distribution unit

Outline Work package General layout and functionality – Mixer unit – Gas Distribution unit Schedule Cost estimate Conclusions 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 2

Gas system work package 2 gas systems: CSC (T 1) and GEM (T 2)

Gas system work package 2 gas systems: CSC (T 1) and GEM (T 2) – 2 mixer units (not for 07 startup) – 4 UX distribution units Each endcap 1 rack with 2 distribution units for T 1 and T 2 – Pipe work done by TOTEM and/or Criotec 2 control racks: – 1 in SG and 1 in US for T 1 and T 2 – In SG, each system will have it’s own PLC control User interface in PVSS 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 3

Can we run from the CMS CSC mixer? General parameters GEM’s (T 2) Gas:

Can we run from the CMS CSC mixer? General parameters GEM’s (T 2) Gas: CSC (T 1) Ar/CO 2 70/30 Ar/CO 2 50/50 (CF 4 optional) (40/50/10) Total volume: ~40 litres 400 litres Total flow: 50 -100 l/h 70 -200 l/h Chamber pressure 1 mbar 1 to 3 mbar Max. overpressure < 10 mbar < 20 mbar No. of Channels 10 channels/endcap 10 channels per endcap No. of Chambers 20 per endcap 30 per endcap No. of Distribution Racks 07/03/2006 TOTEM Engeneering Design Review 1 per endcap S. Haider, F. Hahn PH/DT 1 4

Schematic overview of the gas systems Gas Rack situated on HF platform 07/03/2006 TOTEM

Schematic overview of the gas systems Gas Rack situated on HF platform 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 5

T 1 T 2 Gas mixing unit Gas 1 Ar 50 (40) Ar 70

T 1 T 2 Gas mixing unit Gas 1 Ar 50 (40) Ar 70 (not for ‘ 07 startup) Gas 2 CO 2 50 CO 2 30 Gas 3 CF 4 - (10) - 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 6

Comments Mixer Module Both Mixer staged until second year of LHC running. In the

Comments Mixer Module Both Mixer staged until second year of LHC running. In the first year: – T 1: Gas could be taken from CMS mixer ? (I have contacted Ole. G P. no reaction for the moment…) – Otherwise one could use pre-mixed bottles like for T 2. 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 7

UX distribution unit for T 1 and T 2 Altogethere will be two racks

UX distribution unit for T 1 and T 2 Altogethere will be two racks of this type, one for each endcap. 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 8

T 2 telescope 5 planes with 2 x 3 chambers ~3 m Gas System:

T 2 telescope 5 planes with 2 x 3 chambers ~3 m Gas System: 3 chambers (on the same plane) are connected to one common gas supply 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 9

Pipe connections for T 1 and T 2 UX distribution rack (one endcap): T

Pipe connections for T 1 and T 2 UX distribution rack (one endcap): T 2 To / from T 2 T 1 To / from T 1 US UX US-UX supply / return CO 2 line for backup Note: Return lines 4 x Ø =12 mm And Analysis lines 4 xØ = 6 mm Are unused for the moment. Gas exhaust into the cavern! Analysis lines 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 10

Top view: Gas pipes from Racks to Chambers: T 1 : supply 10 *

Top view: Gas pipes from Racks to Chambers: T 1 : supply 10 * Ø = 4/6 mm Return 10 * Ø =10/12 mm T 2 T 1 flexibles UX distribution Rack for T 1 and T 2 CMS Interaction Point Note: Due to infrastructure all pipe runs have flexible parts requiring cable chains, etc. Supply lines from USC: through central cable chain underneath CMS 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 11

Schedule Production: – All material for 2 distribution racks are at CERN – Assembly

Schedule Production: – All material for 2 distribution racks are at CERN – Assembly will start beginning of February, - finish probably March, delivery > April possible Installation – Cables are procured now (by CMS / Totem) and installed for +Side from May onward – Gas rack installation will start around June – In July, Criotec will install the gas pipes to the UX racks Commissioning – Probably toward the end of 06 (t. b. c. ) 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 12

Preliminary cost estimate Gas Supply (special items only) GEM (T 2) CSC (T 1)

Preliminary cost estimate Gas Supply (special items only) GEM (T 2) CSC (T 1) - - Mixer Pump, purifier, analysis Distribution Aux. Purge 17’ 000 19’ 000 - 22’ 000 included in UX-Distribution Piping SG-USA not costed Piping USA-UXA not costed Detector Piping not costed Electrical Control Total material Manpower (racks) Total 07/03/2006 TOTEM Engeneering Design Review 40, 000 SFr. 79’ 000 SFr. 81’ 000 24, 000 SFr. 103’ 000 SFr. 105’ 000 S. Haider, F. Hahn PH/DT 1 Mixer will increase by ~2’ 000 SFr 13

Conclusions The Totem UX distribution racks are well established in our production line. Mixers

Conclusions The Totem UX distribution racks are well established in our production line. Mixers will come later. Construction of UX racks has started, they will be ready in two months. 07/03/2006 TOTEM Engeneering Design Review S. Haider, F. Hahn PH/DT 1 14