TJC (The Joint Commission) Report Generating Feature…
Let’s walk through some basic and powerful TJC report generating features…
TJC After you initiate “Start TJC Reporting” you then run your electrical system through your testing procedures. Start TJC Recording Stop TJC Recording Open TJC Reports Folder TJC
After you initiate “Start JCAHO TJC Reporting” you then run your then run electrical your electrical system through your testing procedures.
TJC Testing in Progress Status indicator pops up. TJC
TJC You have now captured all required data in the start/stop time “window”. Start TJC Recording Stop TJC Recording Open TJC Reports Folder TJC
After reports are completed, print out, email download or disseminate as needed. Start TJC Recording Stop TJC Recording TJC Open TJC Reports Folder TJC
TJC Controls Start TJC Recording Stop TJC Recording Open TJC Reports Folder Manually initiated Start time: 4: 46, end time: 6: 34. The test ran approx. two hours. Automatic or situational automatic initiation of the TJC reporting feature is also available.