The status of the construction of MICE Step

  • Slides: 23
Download presentation
The status of the construction of MICE Step IV K. Long, on behalf of

The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration

Contents: • Ionization cooling • Overview of MICE • Status of MICE Step IV

Contents: • Ionization cooling • Overview of MICE • Status of MICE Step IV • Measurement programme • Preparation for Step V • Conclusions

The status of the construction of MICE Step IV Ionization cooling

The status of the construction of MICE Step IV Ionization cooling

Neuffer, Rogers Ionization cooling principal: • Neutrino Factory muon front-end: – Optimisation requires: •

Neuffer, Rogers Ionization cooling principal: • Neutrino Factory muon front-end: – Optimisation requires: • Bunching, phase-rotation, and • Ionisation-cooling

Ionisation cooling formalism: • Exponential decrease in normalised emittance: • Competition between: – d.

Ionisation cooling formalism: • Exponential decrease in normalised emittance: • Competition between: – d. E/dx [cooling] and MCS [heating] • Optimum: – Low Z, large X 0 – Tight focus – H 2 gives best performance

The status of the construction of MICE Step IV Overview of MICE

The status of the construction of MICE Step IV Overview of MICE

MICE: MICE ISIS RAL

MICE: MICE ISIS RAL

Staged implementation:

Staged implementation:

The status of the construction of MICE Step IV Status of MICE Step IV

The status of the construction of MICE Step IV Status of MICE Step IV

Step IV; requirements: * All procurement underway. Components for structure ~95% delivered to RAL.

Step IV; requirements: * All procurement underway. Components for structure ~95% delivered to RAL.

Infrastructure:

Infrastructure:

 • Both solenoids have: – Met acceptance criteria – Completed field mapping –

• Both solenoids have: – Met acceptance criteria – Completed field mapping – Been delivered to RAL • Upstream solenoid: – Tracker has been installed in solenoid – “Tracker module” installed in MICE Hall • Downstream solenoid: – Tracker installation in progress – Shared space with FC#2 commissioning – D/s “tracker module” to be installed in the MICE Hall August 2014 Spectrometers:

 • Focus coil #1: – “Solenoid mode”: • Trained to full current –

• Focus coil #1: – “Solenoid mode”: • Trained to full current – “Flip mode”: • “Just” reached nominal current: – Estimate that stable operation at 11%— 15% de-rated current – This is sufficient to support Step IV programme – Module installed in MICE Hall • Focus coil #2: – Received last fall; • Cold-leak • Returned to vendor for diagnosis and repair • Now returned to RAL with repair complete – Re-commissioning of module underway Focus coil:

Partial return yoke: • Reduce stray magnetic fields in the MICE Hall and ISIS

Partial return yoke: • Reduce stray magnetic fields in the MICE Hall and ISIS control rooms to < 5 G • Substantial civil construction: – South side (“behind” experiment) must be installed before superconducting solenoids; • Procurement underway: – Contracts let in UK and US – 95% of parts for support structure have arrived at RAL

Interleaved with commissioning.

Interleaved with commissioning.

The status of the construction of MICE Step IV Measurement programme

The status of the construction of MICE Step IV Measurement programme

Classification of analyses:

Classification of analyses:

C. Heidt, poster contribution ID 355; Friday 04 Jul 14; Accelerator Physics and Future

C. Heidt, poster contribution ID 355; Friday 04 Jul 14; Accelerator Physics and Future Colliders. • Single-particle emittance Nominal 200 Me. V/c; 6 π mm Simulation of Step IV: • Energy/emittance reduction

The status of the construction of MICE Step IV Preparations for Step V

The status of the construction of MICE Step IV Preparations for Step V

 • Focus coil #2: – Re-commissioning underway • RFCC module: – Two components:

• Focus coil #2: – Re-commissioning underway • RFCC module: – Two components: • Coupling coil: – Met acceptance criteria; – RF cavities: • Production well in hand; • Remaining item couplers, in fabrication • Partial Return Yoke: – Substantial civil construction project: • Conceptual design complete; • Moving to detailed design phase • RF power: – Amplifier has been demonstrated: • At 2 MW in test stand; and • At 500 k. W in MICE Hall • Second LH 2 system: – Procurement will start in time for it to be ready for Step V • Second LH 2 absorber vessel: – Being prepared for shipment to RAL from Osaka Step V overview:

The status of the construction of MICE Step IV Conclusions

The status of the construction of MICE Step IV Conclusions

Conclusions: • All components required for Step IV are at RAL; – PRY production

Conclusions: • All components required for Step IV are at RAL; – PRY production underway; – Confident that construction of MICE Step IV will complete Spring 2015. • Data taking to date indicates: – Instrumentation performs to specification; – MICE Muon Beam performs to specification. • Step IV data taking will start Q 1/Q 2 2015 • Preparations for Step V well advanced: – Coupling magnet and prototype cavities have met specification: • First production magnet being commissioned – Schedule for expedited completion of the MICE programme at Step V under development • Collaboration poised to begin the study of ionization cooling